Professional Documents
Culture Documents
Concrete pump
Concrete mixer
• Excavator: used to excavate soil (to carry out
excavation work).
• Trucks: Trucks have high role on construction
especially during the earthwork by removing out soil
and also during backfill.
Truck Excavator
Construction Materials
Cement:-It is inorganic material which has cohesive & adhesive
properties that can able to bind two or more materials together into a
solid mass.
Cement should not be:-
stored above six months in store.
stay above 30 min after mixing.
stay above 2 hours after opening the bag.
• There are two types of cement
1. Ordinary Portland cement (OPC) A mixture of
limestone and other raw materials like argillaceous,
calcareous and gypsum is prepared and then grinded to
prepare OPC.
It has lower resistance against alkalis, chlorides and other
attacking chemicals.
Used for screening.
2. Portland Pazzonolic Cement (PPC) The main
components are OPC, gypsum and pozzolanic materials
(15~35%) which includes calcined clay, volcanic ash,
silica fumes.
It has higher resistance against alkalis, chlorides and other
attacking chemicals.
• Sand constituent for concrete and should be free
from impurities which reduces the strength of
concrete
Aggregates Are filler materials which make up
60-75 % of the concrete volume.
Course aggregate:- Is an aggregates retained on
the No.4 (4.75mm) sieve.
Fine aggregate retained on the No. 200 (0.075mm)
sieve.
0.2 aggregate for column and 0.1 for slab and beam
• Formworks
Formwork is temporary construction material used
as a mold for structure.
Column Formwork
Timber
column Steel column
Formwork Formwork
kerebat
Crachare
Tumbi
Beam formworks
Beam formworks are three-sided box supported
and propped in the correct position and to the
desired level.
Fondo
Sponda
Slab formworks
• The slab formwork should retain and support
the initial loads of the poured concrete and live
load.
Play wood
Scaffolding
5 litters of admixture
Concrete Preparation processes
Batching and mixing
Handling and transporting
Placing and compacting
Leveling
Concrete is batched by two method
Batching by weight This is a method where a
beam balance is used to measure and adjust the
right quantity of sand and aggregate.
Batching by volume This method is highly
practiced on site and widely spread on the
project sites.
Reinforcement Work
• Reinforcement include cutting, bending, placing in position,
tie and spacer.
• Column Reinforcement
• Main bars in columns are placed vertically up along the
column.
They take compressive stress in the columns.
They protect the column from bending moment.
• As we know total load transfer to the foundation is greater as
we move down from the top of building.
to avoid buckling of the longitudinal bars and protect the
column from shear stress we use stirrup.
Overlap length: overlapping length between two
successive bars.
Overlap length is given as: -
Vertical overlap length=4D (diameter of bar)
Anchorage length is used for continuous load transfer.
Beam Reinforcement
Beams are provided with reinforcements to:-
• protect the concrete from shear stress.
• Prevent tension of concrete
• protect the concrete from cracks caused by
temperature and shrinkage stresses.
The reinforcement on the beam are classified in
to three based on their position
Positive bars (main bars): provided at the
bottom of beam.
• purpose of the main bars is to prevent tensile
stress in the beam.
Negative bars are;
• Provided to resist tensile stresses that caused by the
push of columns upwards.
• Provided to resist negative moment.
• They are found at the top support of the beams.
• They are placed at one third of the span length.