BOILER – DUCT

Summary Air Duct #1

Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)

1 Secondary Air Duct 144 144 (100%) 116 (80.6%) 0 28 74.0%

2 Primary Air Duct 125 125 (100%) 108 (86.4%) 0 17 74,4%

3 Tempering Air Duct 46 46 (100%) 42 (91.3%) 0 4 76.3%

4 PA Fan to AH Duct 20 20 (100%) 0 (0%) 0 20 58.0%

5 FD Fan to AH Duct 17 17 (100%) 0 (0%) 0 17 57.8%

6 Windbox 104 98 (98.7%) 0 (0%) 6 104 45.1%

TOTAL 456 450 (98.7%) 266 (58.3%) 6 190 66.4%


Summary Air Duct #1

L3 BASELINE CURRENT QUANTITY

AREA Accum. Progress Progress


START FINISH START FINISH Total Last This (A) + (B) Remaining
Week (A) Week (B)

Air Duct System Unit 1 15-Oct-21 27-Feb-23 08-Oct-21 22-Feb-23 456 450 0 450 6 98.7%
Summary Air Duct #1

L3 BASELINE CURRENT QUANTITY

AREA Accum. Progress Progress


START FINISH START FINISH Total Last This (A) + (B) Remaining
Week (A) Week (B)

Air Duct System Unit 1 22-Nov-21 13-May-23 08-Oct-21 08-May-23 456 266 0 266 190 58.3%
PROGRESS OF PRIMARY HOT AIR DUCT TO MILLS BOILER UNIT #1

Expansion Joint

Damper

Installed Damper

Complete Joint

Status

Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
20 0
Joint

Damper 20 16

Joint 78 74
PROGRESS OF SECONDARY AIR DUCT TO WINDBOX UNIT #1
Legend

Expansion Joint

Damper

Installed Expansion

Complete Joint

Status

Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
45 0
Joint

Damper 18 0

Joint 96 89
PROGRESS OF TEMPERING AIR DUCT TO MILLS UNIT #1
Legend

Expansion Joint

Damper

Installed Damper

Complete Joint

Status

Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
13 0
Joint

Damper 8 6

Joint 32 30
Summary Gas Duct #1

Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)

1 Eco Hopper 17 0 (0%) 0 (0%) 17 17 0%

2 Eco Bypass 12 0 (0%) 0 (0%) 12 12 0%

3 Gas Duct to AH 18 17 (94.4%) 0 (0%) 1 18 35.7%

4 AH Hopper 22 1 (4.5%) 0 (0%) 21 22 2.0%

5 Gas Duct to SCR 22 8 (36.4%) 0 (0%) 14 22 17.5%

6 Gas Duct to EP 36 0 (0%) 0 (0%) 36 36 0%

7 Gas Duct to ID Fan 28 0 (0%) 0 (0%) 28 28 0%

TOTAL 155 26 (16.8%) 0 (%) 136 155 6.9%


Summary Gas Duct #1

L3 BASELINE CURRENT QUANTITY

AREA Progress Progress


Accum. Last
START FINISH START FINISH Total This (A) + (B) Remaining
Week (A)
Week (B)

Gas Duct System 29-Jan-22 20-Jun-23 26-Oct-22 20-Jun-23 155 26 0 26 129 16,8%
Summary Gas Duct #1

L3 BASELINE CURRENT QUANTITY

AREA Progress Progress


Accum. Last
START FINISH START FINISH Total This (A) + (B) Remaining
Week (A)
Week (B)

Gas Duct System 5-Mar-22 05-Sep-23 12-Jan-23 05-Sep-23 155 0 0 0 155 0%


Summary Air Duct #2

Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)

1 Secondary Air Duct 144 65 (45.1%) 9 (6.3%) 79 135 20.4%

2 Primary Air Duct 125 119 (95.2%) 87 (69.6%) 6 38 65.5%

3 Tempering Air Duct 46 46 (100%) 34 (73.9%) 0 12 77.6%

4 PA Fan to AH Duct 20 0 (0%) 0 (0%) 20 20 0%

5 FD Fan to AH Duct 17 0 (0%) 0 (0%) 17 17 0%

6 Windbox 104 0 (0%) 0 (0%) 104 104 0%

TOTAL 456 230 (50.4%) 130 (29.0%) 226 326 32.2%


Summary Air Duct #2

L3 BASELINE CURRENT QUANTITY

AREA Progress Progress


Accum. Last
START FINISH START FINISH Total This (A) + (B) Remaining
Week (A)
Week (B)

Air Duct System Unit 2 2-Mar-22 02-Aug-23 08-April-22 28-Jul-23 456 215 15 230 226 50.4%
Summary Air Duct #2

L3 BASELINE CURRENT QUANTITY

AREA Progress Progress


Accum. Last
START FINISH START FINISH Total This (A) + (B) Remaining
Week (A)
Week (B)

Air Duct System Unit 2 22-April-22 06-Oct-23 24-Jun-22 08-Sep-23 456 130 0 130 326 29,0%
PROGRESS OF TEMPERING AIR DUCT TO MILLS UNIT #2
Legend

Expansion
Joint
Damper

Complete
Joint

Status
Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
13 0
Joint

Damper 8 0

Joint 32 28
PROGRESS OF SECONDARY AIR DUCT TO WINDBOX UNIT #2
Legend

Expansion
Joint
Damper

Complete
Joint

Status
Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
45 1
Joint

Damper 18 0

Joint 96 46
PROGRESS OF PRIMARY AIR DUCT TO MILLS UNIT #2
Legend

Expansion
Joint
Damper

Complete
Joint

Status

Total Complete
Items Design Arrange
(pcs) (pcs)

Expansion
20 0
Joint

Damper 20 0

Joint 78 59
BOILER – AIR PREHEATER
AIR PREHEATER INSTALLATION SEQUENCE

Installation of The Rotor Lifting Device Installation of Casing Bottom Installation Bearing Pivot & Rotor Core Installation of Casing Top Main Parts Installation of Guide Bearing
Trust Bearing Main Parts Installation of Rotor “CLOSE” Segments Installation of Casing Top Side Parts Installation of Thrust Bearing Set-
Rotor Lifting Device Side Parts Installation of Rotor “OPEN” Segments Installation of Casing Top Completed ting
Completed Parts Installation of Rotor Completed

Installation of Cold Basket Adjustment of Seal Frame, Axial Installation of Water Washing Device Installation of Guide Bearing Protec- Installation of Guide Bearing Plat-
And Interm & Hot Basket Plate and Core Seal Frame (Upper and Lower Side) tion Hood form
Installation of All Piping
Installation of Electrical Conduit,
Wiring and Connection
SCHEDULE AIR PREHEATER #1

"A" "B"

No Description
Start Finish Start Finish Start Finish Start Finish
Dur Dur % Finish Dur Dur % Finish
(Plan) (Plan) (Actual) (Actual) (Plan) (Plan) (Actual) (Actual)

Bearing Compo-
1 23-Sep-22 2-Nov-22 41 23-Sep-22 19-Nov-22 58 100% 17-Oct-22 27-Nov-22 41 23-Sep-22 8-Nov-22 47 100%
nent

2 Bottom Casing 3-Nov-22 12-Dec-22 39 7-Oct-22 98.7% 28-Nov-22 6-Jan-23 39 3-Oct-22 98.7%

Bottom Sealing
3 13-Dec-22 18-Dec-22 5 7-Oct-22 100% 7-Jan-23 12-Jan-23 5 3-Oct-22 100%
Frame

4 APH Rotor 19-Dec-22 23-Jan-23 35 10-Nov-22 56.2% 13-Jan-23 17-Feb-23 35 28-Oct-22 56.2%

5 Middle Casing 24-Jan-23 9-Feb-23 16 18-Feb-23 6-Mar-23 16

Top Sealing
6 10-Feb-23 19-Feb-23 9 7-Mar-23 16-Mar-23 9
Frame

7 Top Casing 20-Feb-23 22-Mar-23 30 17-Mar-23 16-Apr-23 30

Basket & Heat-


8 23-Mar-23 4-May-23 42 17-Apr-23 29-May-23 42
ing Element

APH Compo-
9 5-May-23 29-Aug-23 116 30-May-23 23-Sep-23 116
nents
SUMMARY AIR PREHEATER #1

L3 BASELINE CURRENT QUANTITY

AREA Accum. Progress Progress


START FINISH START FINISH Total Last This (A) + (B) Remaining
Week (A) Week (B)

Air Preheater 16-Aug-22 23-Sep-23 23-Sep-22 23-Sep-23 1,680 340 15 355 1325 27.2%
SUMMARY PROGRESS AIR PREHEATER #1
SCHEDULE AIR PREHEATER #2

"A" "B"

No Description
Start Finish Start Finish Start Finish Start Finish
Dur Dur % Finish Dur Dur % Finish
(Plan) (Plan) (Actual) (Actual) (Plan) (Plan) (Actual) (Actual)

Bearing Compo-
1 23-Sep-22 2-Nov-22 41 23-Sep-22 19-Nov-22 58 100% 17-Oct-22 27-Nov-22 41 23-Sep-22 8-Nov-22 47 100%
nent

2 Bottom Casing 3-Nov-22 12-Dec-22 39 7-Oct-22 98.7% 28-Nov-22 6-Jan-23 39 3-Oct-22 98.7%

Bottom Sealing
3 13-Dec-22 18-Dec-22 5 7-Oct-22 100% 7-Jan-23 12-Jan-23 5 3-Oct-22 100%
Frame

4 APH Rotor 19-Dec-22 23-Jan-23 35 10-Nov-22 56.2% 13-Jan-23 17-Feb-23 35 28-Oct-22 56.2%

5 Middle Casing 24-Jan-23 9-Feb-23 16 18-Feb-23 6-Mar-23 16

Top Sealing
6 10-Feb-23 19-Feb-23 9 7-Mar-23 16-Mar-23 9
Frame

7 Top Casing 20-Feb-23 22-Mar-23 30 17-Mar-23 16-Apr-23 30

Basket & Heat-


8 23-Mar-23 4-May-23 42 17-Apr-23 29-May-23 42
ing Element

APH Compo-
9 5-May-23 29-Aug-23 116 30-May-23 23-Sep-23 116
nents
SUMMARY AIR PREHEATER #2

L3 BASELINE CURRENT QUANTITY

AREA Accum. Progress Progress


START FINISH START FINISH Total Last This (A) + (B) Remaining
Week (A) Week (B)

Air Preheater 16-Aug-22 23-Sep-23 23-Sep-22 23-Sep-23 1,680 340 15 355 1325 27.2%
SUMMARY PROGRESS AIR PREHEATER #2