Professional Documents
Culture Documents
Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)
Air Duct System Unit 1 15-Oct-21 27-Feb-23 08-Oct-21 22-Feb-23 456 450 0 450 6 98.7%
Summary Air Duct #1
Air Duct System Unit 1 22-Nov-21 13-May-23 08-Oct-21 08-May-23 456 266 0 266 190 58.3%
PROGRESS OF PRIMARY HOT AIR DUCT TO MILLS BOILER UNIT #1
Expansion Joint
Damper
Installed Damper
Complete Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
20 0
Joint
Damper 20 16
Joint 78 74
PROGRESS OF SECONDARY AIR DUCT TO WINDBOX UNIT #1
Legend
Expansion Joint
Damper
Installed Expansion
Complete Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
45 0
Joint
Damper 18 0
Joint 96 89
PROGRESS OF TEMPERING AIR DUCT TO MILLS UNIT #1
Legend
Expansion Joint
Damper
Installed Damper
Complete Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
13 0
Joint
Damper 8 6
Joint 32 30
Summary Gas Duct #1
Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)
Gas Duct System 29-Jan-22 20-Jun-23 26-Oct-22 20-Jun-23 155 26 0 26 129 16,8%
Summary Gas Duct #1
Complete Remaining
Percentage Fin-
S/N Duct System Design Total
ish
Ground Assembly Installation Ground Assembly Installation
(48%) (52%)
Air Duct System Unit 2 2-Mar-22 02-Aug-23 08-April-22 28-Jul-23 456 215 15 230 226 50.4%
Summary Air Duct #2
Air Duct System Unit 2 22-April-22 06-Oct-23 24-Jun-22 08-Sep-23 456 130 0 130 326 29,0%
PROGRESS OF TEMPERING AIR DUCT TO MILLS UNIT #2
Legend
Expansion
Joint
Damper
Complete
Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
13 0
Joint
Damper 8 0
Joint 32 28
PROGRESS OF SECONDARY AIR DUCT TO WINDBOX UNIT #2
Legend
Expansion
Joint
Damper
Complete
Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
45 1
Joint
Damper 18 0
Joint 96 46
PROGRESS OF PRIMARY AIR DUCT TO MILLS UNIT #2
Legend
Expansion
Joint
Damper
Complete
Joint
Status
Total Complete
Items Design Arrange
(pcs) (pcs)
Expansion
20 0
Joint
Damper 20 0
Joint 78 59
BOILER – AIR PREHEATER
AIR PREHEATER INSTALLATION SEQUENCE
Installation of The Rotor Lifting Device Installation of Casing Bottom Installation Bearing Pivot & Rotor Core Installation of Casing Top Main Parts Installation of Guide Bearing
Trust Bearing Main Parts Installation of Rotor “CLOSE” Segments Installation of Casing Top Side Parts Installation of Thrust Bearing Set-
Rotor Lifting Device Side Parts Installation of Rotor “OPEN” Segments Installation of Casing Top Completed ting
Completed Parts Installation of Rotor Completed
Installation of Cold Basket Adjustment of Seal Frame, Axial Installation of Water Washing Device Installation of Guide Bearing Protec- Installation of Guide Bearing Plat-
And Interm & Hot Basket Plate and Core Seal Frame (Upper and Lower Side) tion Hood form
Installation of All Piping
Installation of Electrical Conduit,
Wiring and Connection
SCHEDULE AIR PREHEATER #1
"A" "B"
No Description
Start Finish Start Finish Start Finish Start Finish
Dur Dur % Finish Dur Dur % Finish
(Plan) (Plan) (Actual) (Actual) (Plan) (Plan) (Actual) (Actual)
Bearing Compo-
1 23-Sep-22 2-Nov-22 41 23-Sep-22 19-Nov-22 58 100% 17-Oct-22 27-Nov-22 41 23-Sep-22 8-Nov-22 47 100%
nent
2 Bottom Casing 3-Nov-22 12-Dec-22 39 7-Oct-22 98.7% 28-Nov-22 6-Jan-23 39 3-Oct-22 98.7%
Bottom Sealing
3 13-Dec-22 18-Dec-22 5 7-Oct-22 100% 7-Jan-23 12-Jan-23 5 3-Oct-22 100%
Frame
4 APH Rotor 19-Dec-22 23-Jan-23 35 10-Nov-22 56.2% 13-Jan-23 17-Feb-23 35 28-Oct-22 56.2%
Top Sealing
6 10-Feb-23 19-Feb-23 9 7-Mar-23 16-Mar-23 9
Frame
APH Compo-
9 5-May-23 29-Aug-23 116 30-May-23 23-Sep-23 116
nents
SUMMARY AIR PREHEATER #1
Air Preheater 16-Aug-22 23-Sep-23 23-Sep-22 23-Sep-23 1,680 340 15 355 1325 27.2%
SUMMARY PROGRESS AIR PREHEATER #1
SCHEDULE AIR PREHEATER #2
"A" "B"
No Description
Start Finish Start Finish Start Finish Start Finish
Dur Dur % Finish Dur Dur % Finish
(Plan) (Plan) (Actual) (Actual) (Plan) (Plan) (Actual) (Actual)
Bearing Compo-
1 23-Sep-22 2-Nov-22 41 23-Sep-22 19-Nov-22 58 100% 17-Oct-22 27-Nov-22 41 23-Sep-22 8-Nov-22 47 100%
nent
2 Bottom Casing 3-Nov-22 12-Dec-22 39 7-Oct-22 98.7% 28-Nov-22 6-Jan-23 39 3-Oct-22 98.7%
Bottom Sealing
3 13-Dec-22 18-Dec-22 5 7-Oct-22 100% 7-Jan-23 12-Jan-23 5 3-Oct-22 100%
Frame
4 APH Rotor 19-Dec-22 23-Jan-23 35 10-Nov-22 56.2% 13-Jan-23 17-Feb-23 35 28-Oct-22 56.2%
Top Sealing
6 10-Feb-23 19-Feb-23 9 7-Mar-23 16-Mar-23 9
Frame
APH Compo-
9 5-May-23 29-Aug-23 116 30-May-23 23-Sep-23 116
nents
SUMMARY AIR PREHEATER #2
Air Preheater 16-Aug-22 23-Sep-23 23-Sep-22 23-Sep-23 1,680 340 15 355 1325 27.2%
SUMMARY PROGRESS AIR PREHEATER #2