PREPARATION TO RESUME WORK AT LAKE

CITY PROJECT

ZHONGXIANG CONSTRUCTION SDN BHD


CONTENT
 NEW NORM COVID - 19 OPERATING PROCEDURE
FOR PELAN PEMULIHAN NEGARA PPN PHASE 1
 ALL WORKERS NEED TO SANITIZE EVERYTIME ENTER SITE FROM OUR
NEW GATE
 ALL OTHER PHASE CONTRACTOR NOT ALLOWED TO ENTER
ZHONGXIANG WORKING AREA. TO AVOID CLOSE CONTACT
 FOLLOWING NEW CIDB SOP DURING FASA PEMULIHAN NEGARA (PPN)
 DECLARATION FORM FOR RTK ANTIGEN AND GATE PASS
 TECHNICAL ISSUE TO RESUME WORK
 AUTHORITIES UPDATE
 TOTAL VACCINATED
NEW NORM COVID - 19 STANDARD OPERATING
PROCEDURE
FOR
1. COVID PELAN
19 RTK PEMULIHAN
ANTIGENT NEGARA
TEST NEED TO CONDUCT PPN
EVERY PHASE 1
14 DAYS.
2. WEARING PERSONAL PROTECTIVE EQUIPMENT SUCH AS SAFETY HELMET, BOOTS,VEST,
RUBBER GLOVE AND MASK.
3. MAINTAIN 1 METER SOCIAL DISTANCE AT THE MAIN GATE DURING MySejahtera SCANNING.
4. DAILY TEMPERATURE RECORD, SANITIZE AND MySejahtera ATTENDANCE RECORD. MUST BE
KEPT FOR ATLEAST 3 MONTH AND SUBMIT COPY TO THE CLIENT.
5. TOOLBOX MEETING INCLUDING A NEW NORM SOP FOR PREVENTIVE COVID 19 SUCH AS SOCIAL
DISTANCE, SANITIZE, USING 3 LAYER FACE MASK ETC.
6. ALWAYS AWARE FOR SOCIAL DISTANCING 1 METER PER PERSON DURING WORKING TIME.
7. DISINFECTION AT SITE OFFICE, GUARD HOUSE AND WORKERS QUARTERS 3 TIMES PER DAY.
8. OFFICE MEETING NEED TO CONDUCT ONLINE.
9. PROVIDE MORE INFORMATION OF COVID 19 SIGNAGE AT THE SAFETY NOTICE BOARD
INCLUDING SAFETY INFO.
10. HOUSEKEEPING AND PROVIDE RUBBER GLOVE, SPECIAL DUSTBIN FOR USE MASK.
COVID-19 CONTROL AND PREVENTION FOR CONSTRUCTION WORKERS

Since our workers are stationed at rented house nearby the project site (herein called House
Centralized Workers Quarters, HCLQ), we will monitor and control their movement from time to
time.

National Recovery Plan SOP before the workers or visitor entering the project site as follows:

1. Provide a copy of RTK Antigen Test Report by MOH Approved Clinic or Hospital.

2. Workers or Visitors always need to scan the MySejahtera QR code, temperature and sanitizer
at the entrance, Safety Team will compile the documents and workers MySejahtera Daily
Check-In History and submit to Client for Record.

3. For control and prevention, Zhongxiang’s have implement to conduct the RTK Antigen
Testing on site through self-testing kit for the workers as a proactive measure to curb the
spread of Covid-19 amongst workers. The schedule of test for the workers are categories as
follow;
Total of Employee
Item Category Description RTK Testing Schedule (Estimation)
1 Construction Management Every 2 eeks 22 persons
2 Worker Stay at HCLQ Every week 20 persons
Twice a week
3 Worker NOT Stay at HCLQ (Monday & Thursday) 21 persons

** 1. All documents and reports to be submit to Client Through Project WeChat Group by 11am (daily)
2. Person In Charge – a) Ch’ng Kheng Hock (Asst. Project Manager, 016-405 4001)
b) Affan Bin Abd Jamil (Safety Officer, 013-207 7768)
COVID-19 CONTROL AND PREVENTION FOR
CONSTRUCTION WORKERS
4. Construction Worker is required to inform his Superior for leaving the project site during
working hours such as grocery, emergency to consult doctor etc. Their movement need to
record down and post in project group chat.

5. Although we are in the National Recovery Plan, but the SOPs are still implement in the
project site. If workers do not comply, action will be taken against them. The penalties as
follow:
Zhongxiang’s Staff and Worker Name List
Construction Management Worker Staying at HCLQ Worker NOT Staying at HCLQ
Item Name List Item Name List Item Name List

1 Ch’ng Kheng Hock 1 Yeayjudin 1 Saiful


2 Alomgr 2 Mandiri
2 Pang Wei Sheng
3 Jakir Hossen 3 Tugang Anak Ngarah
3 Mohd Izzat Fitri bin abdullah
4 Affan bin Abd Jamil 4 Roman Sikdar 4 Tye Khai Chian
5 Saddam Hussein 5 Ahmad Sanawai
5 Imran Rifai bin Othman
6 Shaharib 6 Mohd Fazreem Azuha
6 Mohd taufiq bin Othman
7 Ashraful 7 Muhammad Izzuddin Bin Sedek
7 Mohd Iqbal
8 Guo Jun Qi 8 Salman 8 Abdul Muhaimin Bin Ayub
9 Suruj 9 Mohd Azrim Bin Sulong
9 Fan Jin Ming
10 Ujjal Miah 10 Mohamad Syazwan Bin Mohd Asri
10 Soong William
11 Low Ken Puan 11 Rasel Bepary 11 Muhamad Azanham Bin Md Dris
12 Md Rahmat Ullah 12 Mohd Syakir Bin Hassan
12 Lim Hong Ie
13 Md Lasin Ali Mohamad Khairul Anuar Bin Abdul
13 Li Bing Kang 13
Wahab
14 Sun Feng Li 14 Md Kalam 14 Mohd Salmu Azman Bin Suadin
15 Niu Jin Fu 15 Md Farhad 15 Abd Rashid Bin Samsa
16 Abd Kauym 16 Chuang Tuck Boon
16 Hao Gao Chao
17 Wang Wen bin 17 Samer Ali 17 Chuang Jun Hong
18 Tofajjal 18 Muhamad Azwan Bin Ab Rajid
18 Li Xing Bao
19 Rubel 19 Harun b Abdullah
19 Huang Ai Liang
20 Ruman 20 Omar Bin Kadil
20 Guo Ning Ning
21 21 Jumadil Bin Abdullah
21 Gua ChengCheng
22 22
22 Hao Shu Jian
1. RTK ANTIGEN TEST.

 Action to be taken if the result of RTK Antigen test is positive:

RTK ANTIGEN TESTING


(POSITIVE)
1. Update in mysejahtera self test RTK

2. Issolate and ask them to self quarantine

3. Any other worker in the same workplace who has close contact with +ve worker
consider as CC1 and need to do RTK -Antigen Covid19 test
NEW CONSTRUCTION SOP (PPN PHASE 1)
ACTION EXPLANATION

Approval 1. Getting approval from CIMS MITI and show it


at the construction site.

1. Number of workers need to adjust based on


Workers space.
2. Practice 3W (Wash, wear, warm) wash our hand,
wear a mask and getting a treatment if having fever
or any symptoms.
3. Practice 3C/S (Crowded places, confined spaces,
Close Conversation).
4. All workers need to do a swab test before start
work in construction site.
NEW CONSTRUCTION SOP (PPN PHASE 1)
ACTION EXPLANATION

Movement of Material of construction 1. Movement of material into construction site


must be recorded and the driver must scan
MySejahtera and screening temperature must
not more than 37.5 or any symptoms of covid –
19.

Information of SOP 1. Always spread information for prevention of


infection covid – 19 through poster and awreness.

Management and emergency Respond 2. Bear the cost of cleaning, sanitizing in


construction site
NEW CONSTRUCTION SOP (PPN PHASE 1)
ACTION EXPLANATION
Application MySejahtera 1. All workers need to register Mysejahtera
application to detect close contact
2. Provide Mysejahtera at construction site and
all workers, visitor or driver need to register
before entering site.

Gate of construction site 1. MySejahtera QR scan


2. Copy of RTK antigen report
3. Mysejahtera vaccine certificate
4. Sanitize hands and body spray before
entering site

During working time at construction site 3. Movement control


4. Always aware of 1M distance
NEW CONSTRUCTION SOP (PPN PHASE 1)
ACTION EXPLANATION
Record 1. Keep all the workers record regarding:
- Workers attendance
- Swab test
- Personal information
2. Record all the prove of sanitizing, housekeeping.

1. To make sure workers accommodation are safe


Workers Accommodation and clean.
2. Number of workers need to adjust based on
space.
3. Practice 3W (Wash, wear, warm) wash our hand,
wear a mask and getting a treatment if having fever
or any symptoms.
4. Practice 3C/S (Crowded places, confined spaces,
Close Conversation).
2. WEARING PERSONAL PROTECTIVE EQUIPMENT

 Personal protective equipment PPE include Safety Helmet, Boots, Vest, Rubber Glove
and 3 layer Mask.
 Mask need to wear all the time and change it every day.
 Always give awareness and advice to all workers to wear PPE including face mask
during working time:

Provide Signage Give awareness from time to time


NEW NORM COVID - 19 STANDARD OPERATING PROCEDURE

SWAB TEST FOR COVID 19 WEAR PPE AS STATED AWARE DISTANCE 1M DURING
WORKING ACTIVITY

1 2 3

Must be done before entering site Helmet, boots, Vest, face mask Practice social distancing 1M during working activity

DAILY TEMPERATURE
RECORD MUST BE KEPT
ATLEAST 3 MONTH

TOOLBOX MEETING
4 INCLUDE NEW NORM SOP 5

Must be done by Daily and kept for Toolbox Meeting include new norm
3 month at least SOP
NEW NORM COVID – 19 STANDARD OPERATING PROCEDURE

AWARE DISTANCE 1M AT THE SANITIZE 3 TIMES PER DAY AS CONDUCT ONLINE MEETING
ENTRANCE WHEN ENTERING MENTION
SITE

6 7 8
Aware distance 1M at the gate entrance Must be done 3 times per day Can be done by zoom or google meet

EXTRA DUSTBIN FOR USE MASK


PROVIDED WITH RUBBER
GLOVE

ADD INFORMATION OF COVID 19


IN SAFETY NOTICE BOARD 9 10
Add all information of covid - 19 update Must be throw into the special dustbin
Because of contamination
NEW GATE LAYOUT AND MANDATORY
DOCUMENT NEED TO PROVIDE BEFORE ENTER SITE

Our New Gate Layout


1. MySEJAHTERA QR scan
2. Copy of RTK antigen report
3. MySejahtera Vaccine Certificate
4. Sanitize hands before entering
5. Spray sanitize before entering
DECLARATION FORM, COVID 19 KIT
CHECKLIST AND GATE PASS

GATE PASS APPROVAL FROM OUR COMPANY


DECLARATION FORM, COVID 19 KIT
CHECKLIST AND GATE PASS
Declaration Form Checklist Form

Declaration Form Checklist Form


DECLARATION FORM, COVID 19 KIT
CHECKLIST AND GATE PASS
Daily Temperature Record Keeping
Form Form

Daily temperature Form Record Keeping Form


COVID 19 SELF TEST KIT APPROVAL

We choose number 10

Twelve Self –test covid – 19 test kit approved by MOH


EXAMPLE OF COVID – 19 SELF TEST KIT CAN BE
USED
TECHNICAL ISSUE AND WORK PLAN ON SITE
 MATERIAL
 Concrete:
 Test cube record from the date of stop work until resume work has been tested and recorded, only pending sign from
RE/COW.
 Test cube for new norm operation is tester must send photo evidence of testing and send to the engineer.The result to be
pickup at their place.
 Rebar:
 Visual inspection for current rebar material on site will be inspected on 25/8/2021 with RE/COW. Rebar test to be done if
necessary.

 MACHINERY
 Cabin for operator has been sanitize before entering the cabin
 Mechanics has checked all the machineries and equipment and all in good condition
TECHNICAL ISSUE AND WORK PLAN ON SITE

 TEST PILE

 MLT: MLT stone will start demobilise on 25/8/2021

 SLT: Sonic logging test will start testing on 25/8/2021

 PDA: Pile head preparation will start on 25/8/2021. Drop hammer calculation pending reply from consultant. Start
test at Tower B (5nos) while Tower C (11nos) after demobilisation of MLT stone finish.
TECHNICAL ISSUE AND WORK PLAN ON SITE

 SHEET PILE WORK

 MOS Remedial Work for Existing Steel Sheet Pile Rev. 1 will be reply by consultant
 Subcontrator will start work on 25/8/2021

 SURVEY WORK
 Surveyor has traverse the TBM level and control point setting out on 24/8/2021. All control point and level
maintain as before and within tolerance +/-25mm.
AUTHORITIES UPDATED

 MITI Approved as ‘Kerja Penyelengaraan & Pembaikian Cerun but we stated in MITI
system that our job scope including Bored pile work as stated below during approval.

MITI

APPROVED PILING WORK


AUTHORITIES UPDATED

 JTK IS IN PROGRESS (JTK OFFICER REVIEW). Once our JTK submission approve we
going to submit new MITI application , sector: Menempatkan Pekerja Di Kuaters pekerja
berpusat (CLQ).

JTK: OFFICER REVIEW


STAFF VACCINATION RATE

Number of People vaccinated as of 3/9/2021


• Total staff: 77 person

• Total vaccinated (1st


dose/2nd dose :

48 staff (62.3%)

Not Vaccinated Yet: • Total not vaccinated yet :


37.7% Vaccinated (1st dose &
2nd dose) : 62.3% 29 staff (37.7%)

Vaccinated Not Vaccinated


STAFF VACCINATION RATE

Demographic of vaccinated staff as of 3/9/2021


• Total staff taken vaccine: 48
person

Complete 1st dose • Complete 1st dose only :


only:
22.9% 11 staff (22.9%)

• Complete 1st dose and 2nd


dose :

37 staff (77.1%)
Complete 1st dose and
2nd dose:
77.1%

Complete 1st dose only Complete 1st dose and 2nd dose
STAFF VACCINATION RATE
• Total staff taken vaccine:
48/77 staff

Percentage of Fully Vaccinated Staff (%)


90 • By 23/8/2021:
8 staff fully vaccinated
80
80.5
70 • By 3/8/2021:
15 staff fully vaccinated
60
61
50
• By 3/9/2021:
32 staff fully vaccinated
40
41.5
30
• By 18/9/2021:
47 staff fully vaccinated
20
19.4 • By 13/10/2021:
10
10 62 staff fully vaccinated
0
23/8/2021 30/8/2021 3/9/2021 18/9/2021 13/10/2021
THANK YOU