Professional Documents
Culture Documents
RNC Installation
ZTE University
Contents
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Installation Flow Chart
Installing cables
Installing cabinet
Installing auxiliary facilities
Installing boards
Inspecting installation
Equipment power-on/power-off Installing cables
Inspecting installation
Equipment power-on/power-off
End
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Installing Cabinet
Start
Base-Mounted Mode
It is suitable for the Base-mounted mode Feet-mounted mode
Feet-Mounted Mode
It is suitable for the Connecting adjacent cabinets
cement floor.
Inspecting installation
Installing boards
End
Positioning cabinet
Positioning
机柜定位 cabinet
Positioning base
Fixing
固定机柜 cabinet
Installing base
Unqualified
Insulation test
End
结束
End
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Installing Boards
Preparations
(1) Wear antistatic wrist strap.
(2) Clean up the shelves to ensure good sanitary conditions.
(3) Check the backplane for bent, missing or broken pins.
(4) Check the jacks on the backplane and the boards for
deformation.
(5) Prepare a 6 mm flathead screwdriver or Philips screwdriver to
tighten the captive screw on the extractor.
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Installing Cabinet Power Cables
There are two types of internal lines: internal cables and internal
optical fibers.
Internal cabinet lines include:
Peripheral environment monitoring cables and power cables
Clock cables
Control plane interconnection cables
User plane interconnection optical fibers
Jacks Description
RS485 There are two RS485 interfaces on the power distribution box. The upper one
connects to the PD485 jack of the ROMB rear board; the lower one connects to
the RS485 jack of the PWRD rear board in other racks.
SENSORS The environment monitoring sensor interfaces that connect with all sensors in
the equipment room
DOOR The outlet of internal access control, working ground, and protective ground
FANBOX1 No. 1 fan subrack signal interface that connects to the set-top fan subrack
FANBOX2 No. 2 fan subrack signal interface that connects to the first fan subrack
FANBOX3 No. 3 fan subrack signal interface that connects to the second fan subrack
FANBOX4 No. 4 fan subrack signal interface that connects to the third fan subrack
INPUT (II) No. 1 -48 V power input that connects to the set-top power filter
INPUT (I) No. 2 -48 V power input that connects to the set-top power filter
Jack Description
Jack Description
-48V
GND
cabinet, and provides six terminal sets. The first set and
GND
PE, and GND from the top down. The first set connects -48V
GND
-48V
PE
supply only for the third fan subrack. The second to fifth GND
Jack Description
The first external standard 8K input interface that connects to the 8KOUT/DEBUG-232 on
8 KIN1
the APBE rear board
The second external standard 8K input interface that connects to the 8KOUT/DEBUG-232
8 KIN2
on the backup APBE rear board
Clock output socket, each of which preferably outputs three sets of (16m, pp2s, 8k) clocks.
CLKOUT Under the full capacity of the socket (that is, each socket connects with six UIM boards), six
sets of clocks are required and are connected to the CLKIN jack on the UIM rear board.
These cables are used for the tandem between the resource shelf
and the control plane of the switching shelf in the system, as well
as between the switching plane of the control shelf and the
CHUB.
PDM PDM
G G
U U
Resource shelf
I Resource shelf
I
M M
U R C C U
I O H L I
Control shelfM M U K Control shelfM
C B B G C
G G
U U
Resource shelf
I Resource shelf
I
M M
U G
I U
Switching shelf M Resource shelf
I
C M
These optical fibers are used to connect the resource shelf and
the switching shelf in the system. The user plane is connected
through optical fiber. The RNC user plane is interconnected
through the GLI board and PSN board of the switching shelf. The
GUIM front board of the resource shelf is connected with the GLI
front board through optical fiber.
The connection rules are as follows:
Connect the two optical interfaces of one GUIM board to the
optical interfaces (with the same interface No.) of two different
adjacent active/standby GLI boards. Start the use of GLI
interfaces from the first one in slot 1. Start the connection of
GUIMs from slot 9 in shelf 1 of rack 1.
SD1
SD2 GLIn
S GUIM#9
SD3
a
m
e SD4
re
so SD5
u
rc SD6
e
sh SD7
e UIM #10
lf SD8
SD1
UIM#9
SD2
S
a
m SD3
e SD4
re
so
u SD5
rc
e Note: Each line
SD6
sh
e stands for a pair SD7 GLIn+1
lf UIM#10 of optical fibers. SD8
Main network
7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x
Ethernet
Ethernet
C C
7 8 9 101112 7 8 9101112
A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x
A B A B
G G
I I 10 network
P P section
I I 139 network
section OMM
139 network
section
R R
O O
7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x
129 network
Ethernet
C
7 8 9101112
section
A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x
M M
A B
B B
129 network
section
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Installing Auxiliary Facilities
HUB HUB
R R
O O
M M
Remote alarm box Local alarm box
B B
Router RNC
Router
End A
Sensor pin
LED
End B
Connect the DB9 connector at the end A to the end B4 of the H-MON-009, which is an external
monitoring cable on the PWRDB.
© ZTE Corporation. All rights reserved
Installing Temperature/Humidity Sensor
44
4
85.6
85.6 30 60
壁挂安装孔
Wall-mounting holes
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Inspecting Installation
Installation Process
Installing Cabinet
Installing Boards
Installing Cables
Installing Auxiliary Facilities
Inspecting Installation
Equipment Power-On/Power-Off
Equipment Power-On/Power-Off
Inspection before Powe-On
Check Items Description
Number of Check the number of boards according to the system
boards configuration list.
Board front Check the indicators on the board front panels for looseness.
panel Make sure the buttons and switches are reliably flexible. Ensure
the board interfaces (network interfaces and optical interfaces)
are secure and reliable. Correct any poor contact.
Board rear Make sure the rear boards that connect boards and backplanes
panel are reliably crimped. Ensure the jacks on the rear boards are
clean and free from blockage. Correct any poor contact.
Jumpers & Check the jumpers and DIP switches (if any) in the boards to see
DIP switches if they are in the right positions. For more information, refer to
on boards the descriptions in the related sections of Chapter III of ZXTR
RNC (V1.30) Radio Network Controller Hardware Manual .
Board Perform visual check on the components on the boards and
components correct any solder skips, solder bridges, and cold solder joints.
Board Check the fasteners on the boards and correct any loose or poor
fasteners contact.
Short circuit Measure the ground resistance of the -48V power input port on
at power the boards with a multimeter to avoid any short circuit.
input port of
boards
Power-On Steps
1. Check the cabinet power supply.
2. Power on the boards for the first time.
3. Power on the boards normally.
Power-Off Steps
1. Disconnect the -48V power supply switches on the filters of all subracks.
2. Disconnect the two-way -48V power supply switch on the panel of the
distribution subrack on the top of the rack.
3. At the DC power distribution cabinet side, shut down the -48V power output
to the cabinet.