You are on page 1of 47

UMTS_RNS_I_07_20090530

RNC Installation
ZTE University
Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Installation Flow Chart

 RNC Installation consists of the following steps:


 Installing cabinet
 Installing boards Start

 Installing cables
Installing cabinet
 Installing auxiliary facilities
Installing boards
 Inspecting installation
 Equipment power-on/power-off Installing cables

Installing auxiliary facilities

Inspecting installation

Equipment power-on/power-off

End

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Installing Cabinet
Start
 Base-Mounted Mode
 It is suitable for the Base-mounted mode Feet-mounted mode

equipment room that has Installing base


Installing feet

antistatic floor. Fixing cabinet and base

 Feet-Mounted Mode
 It is suitable for the Connecting adjacent cabinets

equipment room that has


Installing cabinet accessories

cement floor.
Inspecting installation

Installing boards

End

© ZTE Corporation. All rights reserved


Cabinet Installation Flow Chart

Base-Mounted Mode Feet-Mounted


Mode
Start
Start
开始

Positioning cabinet
Positioning
机柜定位 cabinet
Positioning base

Fixing
固定机柜 cabinet
Installing base

Fixing cabinet Unqualified


不通过
Insulation test
绝缘测试

Unqualified
Insulation test
End
结束

End

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Installing Boards

 Preparations
 (1) Wear antistatic wrist strap.
 (2) Clean up the shelves to ensure good sanitary conditions.
 (3) Check the backplane for bent, missing or broken pins.
 (4) Check the jacks on the backplane and the boards for
deformation.
 (5) Prepare a 6 mm flathead screwdriver or Philips screwdriver to
tighten the captive screw on the extractor.

© ZTE Corporation. All rights reserved


Inserting Board

 1. To insert a board, unlock the extractor ejector lever,


and then release it by pushing it outwards. Push the
board slowly into the intended slot in the standard 8U
subrack along the upper and lower guide rails.
 2. After the board connector contacts with the backplane
connector, turn the extractor ejector lever inwards.
Move the board forwards in place. When the ejector
lever makes a "click" sound, it means the extractor is in
the right position and is engaged with the ejector
lever hook.
 3. Use a flathead screwdriver or Philips screwdriver to
tighten the captive screw on the extractor. The
installation is completed.

© ZTE Corporation. All rights reserved


Extracting Board
1. Use a flathead screwdriver or Philips screwdriver to
loosen the captive screw on the extractor. Press
the unlock button to release the extractor.
2. After the board panel indicator ENUM flashes at a
frequency of 1 Hz, turn the extractor ejector lever
outwards to fully release the extractor from the
subrack beam slot, and then extract the board
slowly.
3. Pull out the board slowly along the upper and
lower guide rails of the standard 8U subrack until
it
is completely extracted.

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Installing Cabinet Power Cables

 External Power Cables


 External power cables provide power supply to the RNC.
 Internal Power Cables
 Internal power cables provide power supply to the modules in
the RNC. There are three main types power cables in the RNC
system.
1 . Power cables for the power distribution subrack
2 . Power cables for the fan shelf/subrack
3 . Power cables for the service subrack

© ZTE Corporation. All rights reserved


Installing Cabinet Grounding Cables

 In an RNC system, there are three types of grounding cables:


shelf grounding bar cable, cabinet door grounding cable, and
protective ground tandem cable in the cabinet.
 Protective Grounding of DC Power Distribution Cabinet
 The protective grounding cable of the DC power distribution
cabinet should be directly connected to the grounding bar in the
equipment room.

© ZTE Corporation. All rights reserved


Installing Cabinet Grounding Cables

 RNC Equipment Grounding


 Cabinet Door Grounding Cable

 It connects cabinet front/rear door with rack ground.


 Protective Ground Tandem Cable in Cabinet

 It connects protective busbar ground with rack ground.


 Shelf Grounding Bar Cable

 It connects subrack and cabinet grounding bar, and ensures


reliable lap joint between subrack and rack.

© ZTE Corporation. All rights reserved


Grounding of Other Equipment

 Connection between RNC equipment ground and distribution


frame ground
 Connection between RNC equipment ground and transmission
equipment ground
 Interconnection between RNC cabinet and protective grounds
among RNC cabinets

© ZTE Corporation. All rights reserved


Installing Internal Cabinet Cables

 There are two types of internal lines: internal cables and internal
optical fibers.
 Internal cabinet lines include:
 Peripheral environment monitoring cables and power cables
 Clock cables
 Control plane interconnection cables
 User plane interconnection optical fibers

© ZTE Corporation. All rights reserved


Peripheral Environment Monitoring Cables and
Power Cables
 The peripheral environment monitoring cables and power cables
are used in the following parts:
 Rear boards of power distribution subrack
 Rear boards of ROMB
 Fan subrack
 General subrack
 Busbar

© ZTE Corporation. All rights reserved


Peripheral Environment Monitoring Cables and
Power Cables
 Jacks on Rear Panel of Power Distribution Subrack

Jacks Description

RS485 There are two RS485 interfaces on the power distribution box. The upper one
connects to the PD485 jack of the ROMB rear board; the lower one connects to
the RS485 jack of the PWRD rear board in other racks.
SENSORS The environment monitoring sensor interfaces that connect with all sensors in
the equipment room

DOOR The outlet of internal access control, working ground, and protective ground

FANBOX1 No. 1 fan subrack signal interface that connects to the set-top fan subrack

FANBOX2 No. 2 fan subrack signal interface that connects to the first fan subrack

FANBOX3 No. 3 fan subrack signal interface that connects to the second fan subrack

FANBOX4 No. 4 fan subrack signal interface that connects to the third fan subrack

ARRESTER Internal lightning protection alarm interface

INPUT (II) No. 1 -48 V power input that connects to the set-top power filter

INPUT (I) No. 2 -48 V power input that connects to the set-top power filter

OUTPUT -48 V power output that connects to the power busbar

© ZTE Corporation. All rights reserved


Peripheral Environment Monitoring Cables and
Power Cables
 Cable Connection of Rear Board of ROMB
 PD485 cables are used to connect the ROMB with the cabinet
power distribution subrack in the 485 mode for monitoring
PWRD status.

Jack Description

PD485 An RS485 interface that connects to the RS485


jack on the power distribution subrack.

© ZTE Corporation. All rights reserved


Peripheral Environment Monitoring Cables and
Power Cables
 Rear Board Cables of Fan Subrack

Jack Description

1 A alarm control interface of the fan subrack. It connects to


the FANBOX (1 ~ 4) of the power distribution subrack.
2 A -48 V power output that connects to the power busbar.

© ZTE Corporation. All rights reserved


Peripheral Environment Monitoring Cables and
Power Cables
 General Subrack and Busbar
 The power cable, power distribution cable, and
Detail
放大view
grounding cable of the RNC cabinet are tandemed
through a busbar. -48V

-48V
GND

 The busbar is on the right side of the back of the PE

cabinet, and provides six terminal sets. The first set and
GND

the sixth set each have four terminals: -48V, -48VGND,


-48V

PE, and GND from the top down. The first set connects -48V
GND

with the power distribution subrack to provide power -48V

-48V

supply for the busbar. The sixth set provides power


GND

PE

supply only for the third fan subrack. The second to fifth GND

sets have six terminals: -48V, -48VGND, -48V, -48VGND,


PE, and GND from the top down. These terminal sets
provide power supply for fan subracks and service
subracks.

© ZTE Corporation. All rights reserved


Clock Signal Cables

 Clock signal cables are used in APBE, CLKG, and GUIM.


 APBE board: When the APBE is used at the Iu interface and is set
to get the 8K reference clock from CN, the corresponding rear
board should be RGIM1.

Jack Description

A clock cable interface that outputs clock signals to


the 8 KIN1 jack on the CLKG rear board. If there is a
8KOUT/DEBUG- backup optical fiber that connects with the CN, it is
232 required to connect another clock cable from the
backup APBE rear board to the 8 KIN2 jack on the
CLKG rear board.

© ZTE Corporation. All rights reserved


Clock Signal Cables

 CLKG board: The resource shelves and interface shelves of the


RNC system all require system clock, which is distributed by
connecting RCKG1 and RCKG2 (rear boards of the CLKG) to the
GUIM boards of all resource shelves through cables. The clock is
then distributed by the GUIM boards to the slots of each shelf.
Jack Description

The first external standard 8K input interface that connects to the 8KOUT/DEBUG-232 on
8 KIN1
the APBE rear board

The second external standard 8K input interface that connects to the 8KOUT/DEBUG-232
8 KIN2
on the backup APBE rear board

Clock output socket, each of which preferably outputs three sets of (16m, pp2s, 8k) clocks.
CLKOUT Under the full capacity of the socket (that is, each socket connects with six UIM boards), six
sets of clocks are required and are connected to the CLKIN jack on the UIM rear board.

© ZTE Corporation. All rights reserved


Clock Signal Cables

 Clock Connections among RNC Racks

Resource shelf Resource shelf

Control shelf Control shelf

Resource shelf Resource shelf

Switching shelf Resource shelf

© ZTE Corporation. All rights reserved


Control Plane Interconnection Cables

 These cables are used for the tandem between the resource shelf
and the control plane of the switching shelf in the system, as well
as between the switching plane of the control shelf and the
CHUB.
PDM PDM

G G
U U
Resource shelf
I Resource shelf
I
M M

U R C C U
I O H L I
Control shelfM M U K Control shelfM
C B B G C

G G
U U
Resource shelf
I Resource shelf
I
M M

U G
I U
Switching shelf M Resource shelf
I
C M

© ZTE Corporation. All rights reserved


User Plane Interconnection Optical Fibers

 These optical fibers are used to connect the resource shelf and
the switching shelf in the system. The user plane is connected
through optical fiber. The RNC user plane is interconnected
through the GLI board and PSN board of the switching shelf. The
GUIM front board of the resource shelf is connected with the GLI
front board through optical fiber.
 The connection rules are as follows:
 Connect the two optical interfaces of one GUIM board to the
optical interfaces (with the same interface No.) of two different
adjacent active/standby GLI boards. Start the use of GLI
interfaces from the first one in slot 1. Start the connection of
GUIMs from slot 9 in shelf 1 of rack 1.

© ZTE Corporation. All rights reserved


User Plane Interconnection Optical Fibers

SD1
SD2 GLIn
S GUIM#9
SD3
a
m
e SD4
re
so SD5
u
rc SD6
e
sh SD7
e UIM #10
lf SD8

SD1
UIM#9
SD2
S
a
m SD3
e SD4
re
so
u SD5
rc
e Note: Each line
SD6
sh
e stands for a pair SD7 GLIn+1
lf UIM#10 of optical fibers. SD8

© ZTE Corporation. All rights reserved


Installing External Cabinet Cables

 The following external cables are required:


 Monitoring system cables
 Background maintenance cables
 External optical fibers

© ZTE Corporation. All rights reserved


Monitoring System Cables

 Monitoring system cables include:


 Fan subrack monitoring cable
 Environment monitoring transit cable
 Access control monitoring cable
 Infrared monitoring cable
 Humidity monitoring cable
 Smoke monitoring cable

© ZTE Corporation. All rights reserved


Background Maintenance Cables

 Connections of background O&M cables, including connections


between RNC foreground and OMCR as well as between OMCB
and MINOS.
To NetNumen To NetNumen

Main network
7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x

Ethernet

Ethernet
C C
7 8 9 101112 7 8 9101112

A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x
A B A B

G G
I I 10 network
P P section
I I 139 network
section OMM
139 network
section
R R
O O
7x 8x 9x 10x 11x 12x 7x 8x 9x 10x 11x 12x
129 network
Ethernet

C
7 8 9101112

section
A 12 34 56 1x 2x 3x 4x 5x 6x 1x 2x 3x 4x 5x 6x

M M
A B

B B
129 network
section

Blue lines: External networks


S 129 network Black lines: Internal networks
B section
C
X

© ZTE Corporation. All rights reserved


Laying External Optical Fibers
 Optical fibers connect MGW and SGSN of the CN, with routes as
follows:
1. CS-domain and PS-domain interfaces use the ATM bearer mode:

APBE (RNC) → ODF → APBE (MGW) optical fiber

APBE (RNC) → ODF → SIUP (SGSN) optical fiber
2. CS-domain interfaces use the ATM bearer mode; PS-domain interfaces use the
IP bearer mode:

APBE (RNC) → ODF → APBE (MGW) optical fiber

GIPI (RNC) → ODF → SIUP (SGSN) optical fiber

Note: For commercial offices, optical fibers must be routed on the ODF. Test
environments and demo offices are not required to meet this requirement.

© ZTE Corporation. All rights reserved


Laying External Optical Fibers

 Connection with Optical Fibers at Node B Side


 If optical fibers are used to connect with NODE B NEs, the route
is:
 APBI → ODF → Transmission equipment → BIIP (NODE B)
 Connection with E1 cables at Node B Side
 If channelized SDTB boards are used to connect with NODE B
NEs, E1 cables should be used to connect RNC and NODE B.
 SDTB → ODF → Transmission equipment → DDF in NODE B
equipment room → BET (E1 lightning protection module of
NODE B)

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Installing Auxiliary Facilities

 Installing Alarm Box


 Installing Smoke Sensor
 Installing Temperature/Humidity Sensor
 Installing Infrared Sensor
 Installing Access Control Sensor

© ZTE Corporation. All rights reserved


Installing Alarm Box

 The alarm box is an audio and visual alarming device that is


installed independently. It can be directly installed in the
equipment monitoring room, or installed and monitored
remotely through a remote network.

HUB HUB

R R
O O
M M
Remote alarm box Local alarm box
B B

Router RNC
Router

Background server Local networking


Transmission
network
Network cables
Remote networking Transmission cables

© ZTE Corporation. All rights reserved


Installing Sensors

 It is required to install environment monitoring sensors in the


equipment room after RNC installation is completed. All
environment monitoring sensors must be connected to the
PWRDB of the power distribution subrack in the RNC cabinet to
monitor the environment and report to the ROMB through the
RS485 interface.

© ZTE Corporation. All rights reserved


Installing Smoke Sensor

 The smoke sensor should be mounted on the ceiling, being


above the rack as possible as it can.
C
Sensor
Tag Tag

End A
Sensor pin
LED

End B

Connect the DB9 connector at the end A to the end B4 of the H-MON-009, which is an external
monitoring cable on the PWRDB.
© ZTE Corporation. All rights reserved
Installing Temperature/Humidity Sensor

 The temperature/humidity sensor should be mounted on the


wall. Drill two holes (Φ6) at a proper location on the wall and put
rubber plugs into them. Tighten the tapping screws, and then
mount the sensor on the wall by using both gourd-like holes.

44
4
85.6

85.6 30 60
壁挂安装孔
Wall-mounting holes

© ZTE Corporation. All rights reserved


Installing Infrared Sensor

 The infrared sensor should be mounted on the upper corner of


the wall, so that it can detect anyone who enters the equipment
room through windows or doors.

© ZTE Corporation. All rights reserved


Installing Access Control Sensor

 The access control sensor can monitor five equipment room


doors at most. Its number depends on actual needs.
 Connect the end A of the access control sensor cable to the end
B1 of the external monitoring cable on the PWRDB. Connect the
end B to the corresponding door status switch.

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Inspecting Installation

 Inspecting Cabinet Installation Workmanship


 Inspecting Cabling
 Inspecting Auxiliary Equipment

© ZTE Corporation. All rights reserved


Contents

 Installation Process
 Installing Cabinet
 Installing Boards
 Installing Cables
 Installing Auxiliary Facilities
 Inspecting Installation
 Equipment Power-On/Power-Off
Equipment Power-On/Power-Off
 Inspection before Powe-On
Check Items Description
Number of Check the number of boards according to the system
boards configuration list.
Board front Check the indicators on the board front panels for looseness.
panel Make sure the buttons and switches are reliably flexible. Ensure
the board interfaces (network interfaces and optical interfaces)
are secure and reliable. Correct any poor contact.
Board rear Make sure the rear boards that connect boards and backplanes
panel are reliably crimped. Ensure the jacks on the rear boards are
clean and free from blockage. Correct any poor contact.

Jumpers & Check the jumpers and DIP switches (if any) in the boards to see
DIP switches if they are in the right positions. For more information, refer to
on boards the descriptions in the related sections of Chapter III of ZXTR
RNC (V1.30) Radio Network Controller Hardware Manual .
Board Perform visual check on the components on the boards and
components correct any solder skips, solder bridges, and cold solder joints.

Board Check the fasteners on the boards and correct any loose or poor
fasteners contact.
Short circuit Measure the ground resistance of the -48V power input port on
at power the boards with a multimeter to avoid any short circuit.
input port of
boards

© ZTE Corporation. All rights reserved


Equipment Power-On/Power-Off

 Power-On Steps
 1. Check the cabinet power supply.
 2. Power on the boards for the first time.
 3. Power on the boards normally.

© ZTE Corporation. All rights reserved


Equipment Power-On/Power-Off

 Power-Off Steps
1. Disconnect the -48V power supply switches on the filters of all subracks.
2. Disconnect the two-way -48V power supply switch on the panel of the
distribution subrack on the top of the rack.
3. At the DC power distribution cabinet side, shut down the -48V power output
to the cabinet.

© ZTE Corporation. All rights reserved

You might also like