Professional Documents
Culture Documents
Country Report
Nepal
(2017 Seminar on Electrification Mode Based on
Clean Energy for Countries along the Belt and
Road)
Team Member
Mr. Hari Ram Shrestha
Ms. Liyan Sharma
Mr. Manoj Kumar Sah
Mr. Roshan Pandey
Tuesday, April 30, 2024
2
Tuesday, April 3
0, 2024
Country Background
• Area: 147,141 sq. km.
• Three ecological regions: Terai, Hills & Mountains
• Population: 26.62 million; 5.66 million households
(CBS, 2012)
Key features of energy sector:
Heavy reliance on traditional sources
Regular power-cuts
100% of petroleum is imported: frequent shortages
Upcoming RE sector
3
Tuesday, April 3
0, 2024
Geographical Location
Tuesday, April 3
0, 2024
Physiographic Division
Terai: 17%
(<330 m)
Hilly Area: 68%
Mountain: 15%
(> 3000 m)
Avg. width: 200km
Avg. Length: 800km
Extends from 60 m to 8,848 m at North(The Mount Everest)
5
Tuesday, April 3
0, 2024
General look
6
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Living Goddess
8
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Important Sites
• Lumbini- Birth Place of Lord Buddha
• Pasupathinath- Lord Shiva
• 7 Cultural Heritage site registered by UNESCO
and 2 National Parks
• Highest Peak- Mount Everest (8848 m)
10
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Incredible Nepal
• Naturally Nepal-Once is not enough.mp4
13
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Wind Potential
16
Tuesday, April 3
0, 2024
Condt….
17
Tuesday, April 3
0, 2024
But……
Energy Consumption Situation
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
• Renewable energy for combating energy crisis (urban solar, solar street lighting, wind
energy)
• "Every household in Nepal will be made Indoor Air Pollution Free Bright Household
in next 3 years (CCLS4ALL)” goal through GoN's Policy & Program (FY 2014/15)
• High targets in periodic plan (13th Plan: 2013/14 - 2015/16) & Budget
Speech (FY 2015/16)
• GoN joined UN’s SE4ALL Initiative: NPC as focal point & 3 thematic
• coordination groups (EA, RE, EE); SDG Goal 7
Present Capacity
Installed Capacity: 1001.0 MW
Tuesday, April 3
0, 2024
ROR 811 MW
Storage 92 MW
IPP 430
NEA 381
21
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Classification of Hydropower in
Nepal
• -Pico Hydro: Up to 10 kW
Tuesday, April 3
0, 2024
RE Installation
Renewable Energy Technology Installations July 2011 Districts Households
Number Capacity Covered* connected
Tuesday, April 3
0, 2024
Transmission Line
Under
Existing Planned
Transmission Lines Construction
(Circuit km) (Circuit km)
(Circuit km)
66kV Voltage Level 511.16 -
132kV Voltage Level 2337.7 1010.0 1320.0
220kV Voltage Level - 659.0 949.8
400kV Voltage Level - 648.0 6495.6
Total 2848.86 2317.0 8765.4
25
Source:
Rajeev Sharma, (at Power Summit), 2016
26
RE Status
Theoretical Potential of Above 100 GW
Hydropower (MW)
Definition of SHP in Your Within 10 MW
Country (MW)
Tuesday, April 3
0, 2024
RE status contd…
Installed Capacity of SHP (MW) 70% of total hydro
Installed Capacity of Solar 20 MW (Grid+ off grid)
Energy (MW)
Installed Capacity of Wind Nearly 1 MW (off grid)
Energy (MW)
Power Price for End Users 8.46 NPR-11.5 NPR (20-251) Unit 1 USD = 103.5 NPR
(US dollar)
Feed-in Tariff of SHP ~ 5.20 NPR by NEA
(US dollar)
Feed-in Tariff of Solar Energy ~9.46 NPR by NEA (recently made in tender)
(US dollar)
Feed-in Tariff of Wind Energy ~9.46 NPR by NEA (recently made in tender) especially for Solar Wind hybrid
(US dollar)
Hydropower Projects to be 2-3 above 1 MW per year and 10 below 1 MW every year and 2 big hydro (greater
Constructed or Refurbished than 50 MW) construction every year.
Main Difficulties in SHP Policy, Training, Maintenance services and technology transfer
development and planning
Future Solar Energy Projects to World bank 20 MW project to be constructed this year
be Constructed
Main Difficulties in Developing Problem for grid penetration due to lack in feed in traffic policy for renewable energy
Solar Energy and due to lack of Grid Impact Study of Nation grid transmission system.
28
Status 04/30/2024
04/30/2024
Problems
• On looking the percentage of failure, it was
obtained that about 50% of the components
manufactured in Nepal have failed. This is
probably because the manufacturers are new to
this process and they have got very low expertise
on the manufacturing of hydropower
components.
• To reduce the dependence and increasing own
capacity, proper seminars and workshops need
to be organized for the local manufacturers.
30
04/30/2024
12
10
0
Electro-mechanical Civil Electrical Mechanical
04/30/2024
0
<1 1 to 5 5 to 10 >10
Preservation and
Modernization of Indigenous
Technologies
Promotion of Research in S
&T
04/30/2024
04/30/2024
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
How it goes??????
40
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Then Now
43
Tuesday, April 3
0, 2024
Group Photo
44
Tuesday, April 3
0, 2024
Nepalese Dress
45
Tuesday, April 3
0, 2024
Tuesday, April 3
0, 2024
Modern Girls
47
Tuesday, April 3
Average Guy
0, 2024
48
04/30/2024