Estimating Earthwork
Earthwork includes: 1. Excavation 2. Grading: Moving earth to change elevation 3. Temporary shoring 4. Back fill or fill: Adding earth to raise grade 5. Compaction: Increasing density 6. Disposal
Productivity Factors
A. Job conditions
Material type Water level and moisture content Job size Length of haul Haul road condition (accessibility and load restrictions)
Units of Measure
Cubic Yard (bank, loose, or compacted)
Bank (BCY): Mat erials in it s nat ural st at e before dist urbance (in-place, in-sit u) Loose (LCY): Mat erial t hat has been compact ed or dist urbed or loaded Compact ed (CCY): Mat erial aft er compact ion
1.25
1.0
0.90
In place
Loose
Compacted
Volume
Bank: VB
Bank cubic yards (BCY) Density B Lb /BCY
Loose: Vl
Loose cubic yards (LCY) Density L Lb/LCY
Compacted: Vc
Compacted cubic yards (CCY) Density C LB/CCY
Prof Awad S. Hanna
Swell:
A soil increase in volume when it is excavated.
Swell (%) =
- 1) x 100
Load factor =
Shrinkage: A soil decreases in volume when it is compacted Bank density Shrinkage (%) = (1 ) Compacted density x 100 Shrinkage factor = 1 - Shrinkage Compacted volume = Bank volume x Shrinkage factor
Prof Awad S. Hanna
Exact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils. Prof Awad S. Hanna
2-0 or more
Prof Awad S. Hanna
Angle of Repose
Stations
E F
80
82
84
86
88
A
100'
B
100'
C
100' 500'
D
100'
E
100'
300'
80
Sec. A- A
78.5 78
76 82
Sec. B- B
80.3
80
78 84
Sec. C- C
82.3
82
80 86
Sec. D- D
84.2
84
88
Sec. E- E
86.2
86
90
Sec. F- F
88.2
88
Cross-Section @ A - A
80
Area =
107 x 1.0 2
= 53.5
79
79.5
78.5
78
76.7
Area =
193 x 1.8
77 = 173.7 76
Section A- A
Cross-Section @ B - B
82
Area =
90 x 1.5 2
81.8
= 67.5
81
80.3
80
76.7
Area =
210 x 1.8
79 = 189.0 78
Section B- B
A
88
87.6
B
89
88.5
C
90
89.3
D
300
E
91
90.3
F
93 94
92
91.5
95.0
A
87.6
B
88.6
C
89.4
D
90.4
E
91.6
F
93.2 94.3
G
87.4
H
88.2
J
89.5
K
90.6
L
91.6
M
92.7 93.5
N
87.2
O
87.7
P
89.0
Q
90.4
R
91.3
S
92.0 93.1
No Scale
Notes: 1. Bring the entire site to elevation 90. 2. All grids are 50x 50 = 2500 sq. ft. 3. Present contours
Need Fill
Need Cut
Quick and Dirty Assume one grid Existing 90.50 Proposed 90.00 Cut 0.50
27
300'
90'
91'
90.5'
150'
Average elevation = 87.6+88.5+87.6+88.6 4 = 88.08 change = 90-88.08 = 1.92 cut = = 177.77 CY and so on.
87.6 87.6
88.6
87.6