You are on page 1of 5

Field test form LV Power Circuit Breaker

CUSTOMER: MAADEN K.S.A EQUIPMENT TAG NO.: BI/JO NO.: REF. DRAWINGS & DOCUMENTS: TEST COMPLETION DATE:
MAKE TYPE MODEL NO. VL 800 SIEMENS

PROJECT: SUBSTATION-1 DESCRIPTION: L V MCC CIRCUIT BREAKER PLANT NO. / LOCATION: /08/2010
VOLTAGE RATING CURRENT RATING PLUG RATING 480 Volt A

SECTION 1: MECHANICAL CHECK AND VISUAL INSPECTION:

Ite m 1 2 3 4 5 6 7 8 9

Description Inspect for physical damage/defects. Check quality of paintwork. Check nameplate information for correctness. Check tightness of all bolted connections (torque wrench method). Check racking mechanism for alignment and smoothness of operation. Check operation of all mechanical interlocks. Check for correct breaker position indication. Check the arc chutes for damage and correct positioning above the interrupter contacts. Check that all control wiring is correct according to the approved drawings and terminal connections are secure.

Remarks OK N.A OK OK OK N.A OK N.A OK

SECTION 2: ELECTRICAL CHECK:

TESTING ENGINEER
Name Signature Date

NOUR QC

MAADEN WITNESS

Field test form LV Power Circuit Breaker

CUSTOMER: MAADEN K.S.A EQUIPMENT TAG NO.: BI/JO NO.: REF. DRAWINGS & DOCUMENTS: TEST COMPLETION DATE:
Item 1 2 3 Contact Resistance Insulation resistance TRIP TEST

PROJECT: SUBSTATION-1 DESCRIPTION: L V MCC CIRCUIT BREAKER PLANT NO. / LOCATION: /08/2010
Remarks OK OK OK

Description

SECTION 3: TEST VALUES:

1. INSULATION RESISTANCE TEST ( VALUES IN MEGA-OHMS) ( TEST VOLTAGE KV DC)


RESULTS PHASE (BREAKER CLOSED) A To ( B+C+G) A TO B PHASE (BREAKER CLOSED) RESULTS

B to ( A+C+G)

B TO C

TESTING ENGINEER
Name Signature Date

NOUR QC

MAADEN WITNESS

Field test form LV Power Circuit Breaker

CUSTOMER: MAADEN K.S.A EQUIPMENT TAG NO.: BI/JO NO.: REF. DRAWINGS & DOCUMENTS: TEST COMPLETION DATE:
C to (A+B+G)

PROJECT: SUBSTATION-1 DESCRIPTION: L V MCC CIRCUIT BREAKER PLANT NO. / LOCATION: /08/2010
C TO A

2. CONTACT RESISTANCE TEST (VALUES IN MICRO OHMS) : (TEST CURRENT A) PHASE CONTACT RESISTANCE

A
B C

3. TRIP TEST

PHASES

L1

L2

L3

TESTING ENGINEER
Name Signature Date

NOUR QC

MAADEN WITNESS

Field test form LV Power Circuit Breaker

CUSTOMER: MAADEN K.S.A EQUIPMENT TAG NO.: BI/JO NO.: REF. DRAWINGS & DOCUMENTS: TEST COMPLETION DATE:

PROJECT: SUBSTATION-1 DESCRIPTION: L V MCC CIRCUIT BREAKER PLANT NO. / LOCATION: /08/2010

PHASE CHECK TRIP CHECK

SECTION 4: TEST EQUIPMENTS LISTING AND CALIBRATION DATA

DEVICE Insulation Resistance

MAKE

CALIBRATION DATE

CALIBRATION EXP.

TESTING ENGINEER
Name Signature Date

NOUR QC

MAADEN WITNESS

Field test form LV Power Circuit Breaker

CUSTOMER: MAADEN K.S.A EQUIPMENT TAG NO.: BI/JO NO.: REF. DRAWINGS & DOCUMENTS: TEST COMPLETION DATE:
Micro Ohm meter TRIP CHECK

PROJECT: SUBSTATION-1 DESCRIPTION: L V MCC CIRCUIT BREAKER PLANT NO. / LOCATION: /08/2010

TESTING ENGINEER
Name Signature Date

NOUR QC

MAADEN WITNESS

You might also like