Professional Documents
Culture Documents
Build Up Rate Infrastructure Work
Build Up Rate Infrastructure Work
Item a, page 29
Per day
RM
150.00
ii)
1 Day
RM
270.00
Per day
RM
270.00
RM
250.00
Per day
RM
250.00
iv) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 770.00
: : RM
91 770.00
M / 91 = RM 8.51
1 Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
1 Day
RM
38.00
Per day
RM RM
190.00 255.00
: : RM
91 255.00
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged End Wing or Fish Tail (Terminal end Type 1)
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00
Item b i, page 29
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: :
RM
33 250.00
NO /
33
= RM
7.69
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 4 x
Day
RM
38.00
Per day
RM RM
152.00 217.00
: : RM
33 217.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged Terminal Anchorage Unit Type 2)
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: : RM
17 250.00
NO /
17
= RM
14.71
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 4 x
Day
RM
38.00
Per day
RM RM
152.00 217.00
: : RM
17 217.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged 90 degrees Twist Unit Type 3
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: : RM
17 250.00
NO /
17
= RM
14.71
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 4 x
Day
RM
38.00
Per day
RM RM
152.00 217.00
: : RM
17 217.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged Terminal 1 : 6 / Sloping End Unit Type 4
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: : RM
17 250.00
NO /
17
= RM
14.71
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 4 x
Day
RM
38.00
Per day
RM RM
152.00 217.00
: : RM
17 217.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged guardrail post
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00 Backhoe : 1
Item c, page 29
Per day
RM
150.00
ii)
Day
RM
270.00
Per day
RM
270.00
iii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 520.00
: :
RM
27 520.00
NO /
27
= RM
19.40
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 3 x
Day
RM
38.00
Per day
RM RM
114.00 179.00
: :
RM
27 179.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing damaged nose yellow
A) Machinery. I) Backhoe 1
Item d, page 29
Day
RM
270.00
Per day
RM
270.00
ii)
RM
150.00
iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 280.00
Per day
= Total =
RM RM
280.00 700.00
: : RM
6 700.00
NO /
= RM
114.27
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 3 x
Day
RM
38.00
Per day
RM RM
114.00 179.00
: : RM
6 179.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing damaged cartridge
A) Machinery. I) Backhoe 1
Item e, page 29
Day
RM
270.00
Per day
RM
270.00
ii)
RM
150.00
iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
= Total =
RM RM
150.00 570.00
: : RM
3 570.00
NO /
RM
165.46
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 3 x
Day
RM
38.00
Per day
RM RM
114.00 179.00
: : RM
3 179.00
NO /
= = = = Take
RM RM RM RM RM
ADD:
15%
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing beam panel
A) Machinery. I) Backhoe 1
Item f, page 29
Day
RM
270.00
Per day
RM
270.00
ii)
RM
150.00
iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
= Total =
RM RM
150.00 570.00
: : RM
5 570.00
NO /
= RM
109.20
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 3 x
Day
RM
38.00
Per day
RM RM
114.00 179.00
: : RM
5 179.00
NO /
= RM = RM = RM = RM Take RM
ADD:
15%
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Realigning of existing (line & level) Item g, page 29 Realign and straighten the line of existing guardrail including correct the level and verticality position of existing guardrail post.
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00 Hydraulic jack 1 x
Per day
RM
150.00
ii)
Day
RM
100.00
Per day
RM
100.00
iii) Backhoe : 1
Day
RM
270.00
Per day
= Total =
RM RM
270.00 520.00
: :
RM
97 520.00
M /
97
= RM
5.36
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
97 255.00
M /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Realigning of existing (line & level) Supply and replace missing delinator piece on guardrail
A) Material I) B) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set)
Item h, page 29
= RM
5.00
Machinery I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00
C)
Workmen I) General worker 3 x 1 Day @ RM 38.00 per day Total Productivity Per day Workmen Cost Per No. : : 43 344.00 NO / = RM RM 114 344.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Guard Rails
ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised new guardrail beams
A) Material I) ii) Guardrail (supply price/M) Transportation(per M) : : : = RM RM
Item a, page 30
Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day) Total
= =
RM RM
100.00 250.00
: :
RM
71 250.00
M /
71
= RM
3.55
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
71 255.00
M /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised End wing or Fish Tail (Terminal unitType 1)
A) Material I) ii) Terminal End Type l (supply price/No) Transportation(per No) : : = RM = RM
Item b i, page 30
Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: :
RM
29 250.00
NO /
29
= RM
8.68
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
29 190.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised Terminal anchorage unit Type 2
A) Material i) ii) Terminal anchorage unit Type 2 (supply price/No) Transportation(per No) : : = RM = RM
Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: :
RM
80 250.00
NO /
80
= RM
3.13
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
80 255.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised 90 degrees Twist Unit Type 3
A) Material I) ii) Twist unit type 3 (supply price/No) Transportation(per No) : : = RM RM
Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: :
RM
9 250.00
NO /
= RM
26.60
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
9 255.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised Terminal section 1:6 / Sloping End Type 4
A) Material I) ii) Terminal Anchorage Type 4 (supply price/No) Transportation(per No) : : = RM RM
Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00
Per day
RM
150.00
ii)
Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 250.00
: :
RM
14 250.00
NO /
14
= RM
18.32
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
14 255.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised guadrail post complete with packer
A) Material I) ii) Guardrail post (supply price / No) Transportation(per No) : : = RM RM
Item c, page 30
Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Arrow Rammer : 1 x
Per day
RM
150.00
ii)
Day
RM
300.00
Per day
RM
300.00
iii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)
= Total =
RM RM
100.00 550.00
: :
RM
52 550.00
NO /
52
= RM
10.50
Day
RM
65.00
Per day
RM
65.00
ii)
General Worker : 5 x
Day
RM
38.00
Per day
RM RM
190.00 255.00
: :
RM
52 255.00
NO /
= RM = RM = RM = RM RM
ADD:
15%
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Item d, page 30 Supply and replace new yellow nose for the crash cushion inclusive of all necessary preparatory work.
I) Nose Yellow = RM
21,090.00
ADD:
15%
= RM = RM RM
Take
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Item e, page 30 Supply and replace new cartridge for the crash cushion inclusive of all necessary preparatory work.
A) Material I) Cartridge ADD: P& O : Rate Per NO. Take 15% = RM = RM = RM RM 2,740.00 411.00 3,151.00 3,150.00
Guard Rails
ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and replace new beam panel.
A) Material I) Cartridge ADD: P& O : Rate Per NO. 15%
Item g, page 30
= RM = RM = RM Take RM
Guard Rails
ROAD FURNITURE MAINTENANCE OF STUDS Reinstallation of existing studs Item a,page 31 To reinstall the missing road stud at existing location with new single - sided Road stud
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 16.20 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total = Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x : : 55 250.00 No /
RM RM
100.00 250.00
RM
55
RM
4.55
Day
RM
65.00
Per day
RM
65.00
Day
RM
38.00
Per day
RM
76.00
Day
RM
35.00
Per day
RM RM
70.00 211.00
: :
RM
55 211.00
= = = = Take
RM RM RM RM RM
ADD:
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Reinstallation of existing studs Item b,page 31 To reinstall the missing road stud at existing location with new double - sided Road stud
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 21.40 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
55 250.00
No /
55
RM
4.56
Day
RM
65.00
Per day
RM
65.00
Day
RM
38.00
Per day
RM
76.00
Day
RM
35.00
Per day
RM RM
70.00 211.00
: :
RM
55 211.00
No /
= = = = Take
RM RM RM RM RM
ADD:
15%
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs Item c,page 31 To replace the damaged road stud at existing location with new single - sided Road stud
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = RM RM 16.20 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
39 250.00
No /
39
RM
6.44
Day
RM
65.00
Per day
RM
65.00
Day
RM
38.00
Per day
RM
76.00
Day
RM
35.00
Per day
RM RM
70.00 211.00
: :
RM
39 211.00
No /
= = =
RM RM RM
ADD:
15%
= RM Take RM
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs Item d,page 31 To replacel the damaged road stud at existing location with new double - sided Road stud
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 21.40 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
39 250.00
No /
39
RM
6.44
Day
RM
65.00
Per day
RM
65.00
Day
RM
38.00
Per day
RM
76.00
Day
RM
35.00
Per day
RM RM
70.00 211.00
: :
RM
39 211.00
No /
= = = = Take
RM RM RM RM RM
ADD:
15%
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs To remove existing road stud and refix at same position
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =
Item e,page 31
RM RM
16.20 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
55 250.00
No /
55
RM
4.55
Day
RM
65.00
Per day
RM
65.00
Day
RM
38.00
Per day
RM
76.00
Day
RM
35.00
Per day
RM RM
70.00 211.00
: :
RM
55 211.00
No /
= = = = Take
RM RM RM RM RM
ADD:
15%
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Installation of New Studs Supply and lay new single -side Road in accordance to specification.
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =
Item f,page 31
RM RM
16.20 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
42 250.00
No /
42
RM
5.91
Day
RM
65.00
Per day
RM
65.00
Day
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
114.00
Day
RM
35.00
Per day
RM RM
70.00 289.00
: :
RM
42 289.00
No /
= = =
RM RM RM
ADD:
15%
= RM Take RM
Road Stud
ROAD FURNITURE MAINTENANCE OF STUDS Installation of New Studs Supply and lay new double-side Road stud in accordance to specification.
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =
Item g,page 31
RM RM
21.40 1.50
RM
150.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 250.00
: :
RM
35 250.00
No /
35
RM
7.12
Day
RM
65.00
Per day
RM
65.00
Day
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
114.00
Day
RM
35.00
Per day
RM RM
70.00 289.00
: :
RM
35 289.00
No /
= = = = Take
RM RM RM RM RM
ADD:
15%
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item a,page 32 Prepare and apply white or yellow temporary roadline paint for pavement markings for 150mm wide single continous edge line marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item b,page 32 Prepare and apply white temporary roadline paint for pavement markings for 150mm wide single continous center line and lane markings
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item c,page 32 Prepare and apply white temporary roadline paint for pavement markings for 100mm wide intermittent center line and lane marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item d,page 32 Prepare and apply white temporary roadline paint for pavement markings for 150mm wide yellow edge marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item e,page 32 Prepare and apply white temporary roadline paint for pavement markings 200mm wide intermitent give-way line wide with 300mm length each and at 200mm gap
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
= RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item f, page32 Prepare and apply white temporary roadline paint for pavement markings for 300mm wide continous stop line marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item g, page32 Prepare and apply white temporary roadline paint for pavement markings for 300mm wide chevron hatching for merging / diverging traffic and cross hatching
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= =
RM RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
124 370.00
M2 /
124
RM
2.98
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
124 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item h, page32 Prepare and apply white temporary roadline paint for pavement markings for "AWAS" and other pavement lattering marking
A) Material I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= RM = RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
83 370.00
M2 /
83
= RM
4.46
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
83 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item i, page32 Prepare and apply white temporary roadline paint for pavement markings for pavement directional arrow marking
A) Material I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= RM = RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
83 370.00
M2 /
83
= RM
4.46
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
83 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item j, page32 Prepare and apply black temporary roadline paint to erase and correct including necessary adjustment of existing pavement markings
A) Material I) Roadline paint (black) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%
= RM = RM
RM
150.00
RM
120.00
Per day
RM
120.00
ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =
RM RM
100.00 370.00
: :
RM
102 370.00
M2 /
102
= RM
3.63
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
102 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item a,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings or sizes100mm to 150mm wide single continuos edge line marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item b,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of 150mm width single continuos center line and lane marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item c,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for intermittent center line and lane marking of 100mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item d,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement marking for 150mm wide single continuos edge marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item e, page33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for intermittent give-way line 200mm wide, with 300mm length each and 200mm gap
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item f, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for continuos stop line of 300mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item g, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for 300mm width chevron hatching for merging / diverging tracffic and cross hatching
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
122 620.00
M2 /
122
= RM
5.10
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
122 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item h, page 33 Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick 600mm
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 200 M2 b) Cost (per M2) RM 2,200.00 / 200 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
11.00
M2 /
1,250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
120 620.00
M2 /
120
= RM
5.17
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
120 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item i, page 33 Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick and 500mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 200 M2 b) Cost (per M2) RM 2,200.00 / 200 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
11.00
M2 /
1,250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
120 620.00
M2 /
120
= RM
5.17
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
RM RM
70.00 262.00
: :
RM
120 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item j,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of "AWAS" or other lattering on pavement marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item k, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of pavement direction arrow
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
160 620.00
M2 /
160
= RM
3.88
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
160 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item I,page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of intermittent center line100mm wide and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
43 620.00
M2 /
43
= RM
14.27
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
43 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item n, page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of continuos edge line 150mm and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
43 620.00
M2 /
43
= RM
14.27
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
43 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item o, page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of double line 100mm wide and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%
= RM
7.14
M2 /
1250
= RM = RM
RM
150.00
RM
130.00
Per day
RM
130.00
Day
RM
120.00
Per day
RM
120.00
Day
RM
100.00
Per day
RM
100.00
RM
120.00
= =
RM RM
120.00 620.00
: :
RM
43 620.00
M2 /
43
= RM
14.27
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
Per day
RM RM
70.00 262.00
: :
RM
43 262.00
M2 /
= RM = RM = RM = RM RM
ADD:
15%
Take
Road Marking
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item a Page 34 Excavate, dismantle and reinstall the existing concrete road kerb for straightening of misaligned kerbs
A) Material i) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & equipments) : Allow sum Per day Total Productivity Per Day Workmen Cost Per M : : 76 478.00 M / M 76
RM
150.00
RM RM
100.00 478.00
RM
ADD :
P&O
: Rate Per M
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(i) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type I
A) Material i) Kerb Type I (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 30.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 116 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM Take RM
ADD :
15%
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(ii) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type II
A) Material i) Kerb Type II (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 27.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 320 478.00 M / M 320
RM RM
100.00 478.00
RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(iii) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type III
A) Material i) Kerb Type III (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 29.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 141 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(iv) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type IV
A) Material i) Kerb Type IV (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 23.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 128 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(v) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type V
A) Material i) Kerb Type V (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 28.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 109 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type I including concrete bedding
A) Material i) Kerb Type I (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
30.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 71 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type II including concrete bedding
A) Material i) Kerb Type II (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
27.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 105 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type III including concrete bedding
A) Material i) Kerb Type III (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
29.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 93 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type IV including concrete bedding
A) Material i) Kerb Type IV (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
23.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 95 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type V including concrete bedding
A) Material i) Kerb Type V (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
28.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 99 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VI including concrete bedding
A) Material i) Kerb Type VI (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
20.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 105 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VII including concrete bedding
A) Material i) Kerb Type VII (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
30.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 40 478.00 M /
RM RM
100.00 478.00
RM
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VIII including concrete bedding
A) Material i) Kerb Type VIII (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x
= RM = RM
18.00 5.00
Day
RM
38.00
Per day
RM
228.00
ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 73 478.00 M / M 73
RM RM
100.00 478.00
RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Item d Page 34 Supply and apply one coat primer and two coats of approved weatherproof paint to existing concrete kerbs
A) Material i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) a) Approx. Coverage/Ca : 40 b) Cost (per M) : RM 65.00 ii) ADD : Wastage : 10% = M / 40 = = RM RM RM = 65.00 1.63 0.16 RM 1.79
iii) Material cost (per M) B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner) Allow sum Per day C) Workmen i) Semi-skilled worker : 1 x ii) General worker : 4 x iii) Flagman : 2
RM
150.00
RM
100.00
Day
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
RM RM
70.00 512.00
: :
RM
149 512.00
M /
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
ROAD FURNITURES MAINTENANCE OF KERBS Repainting of Existing Kerbs Item e Page 34 Scrape, brush, clean, prepare and apply one coat primer and two coats of approved weatherproof paint to existing concrete kerbs
A) Material i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) a) Approx. Coverage/Ca : 40 b) Cost (per M) : RM 65.00 ii) ADD : Wastage : 10% = M / 40 = = RM RM RM = 65.00 1.63 0.16 RM 1.79
iii) Material cost (per M) B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner) Allow sum Per day C) Workmen i) Semi-skilled worker : 1 x ii) General worker : 4 x iii) Flagman : 2
RM
150.00
RM
100.00
Day
RM
40.00
Per day
RM
40.00
Day
RM
38.00
Per day
RM
152.00
Day
RM
35.00
RM RM
70.00 512.00
: :
RM
132 512.00
M /
= RM = RM = RM = RM RM
ADD :
15%
Take
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item a Page35 Supply, erect and install 76 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting, concrete footing and excavation
A) Material i) M.S. post (supply price) : : : x : 1.50 x 0.75 @ RM 7.35 = RM RM = 6.20 236.89 RM 59.22 0.75 @ RM ### = RM 182.69 RM RM 12.00 12.00 / M x
4.00 M
RM
48.00
RM
236.89
4.00 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 52 250.00 M /
100.00 250.00
RM
52
RM
4.81
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
52 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item b Page35 Supply, erect and install 89 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 1.80 x 0.75 @ RM 7.35 = RM RM = 7.44 296.67 RM 59.33 0.75 @ RM ### = RM 219.23 RM RM 14.00 14.00 / M x
5.00 M
RM
70.00
RM
296.67
5.00 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 53 250.00 M /
100.00 250.00
RM
53
RM
4.76
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
53 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item c Page35 Supply, erect and install 114 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting, and concrete footing
A) Material i) M.S. post (supply price) : : : x : 1.80 x 0.75 @ RM 7.35 = RM RM = 7.94 321.78 RM 64.36 0.75 @ RM ### = RM 233.84 RM RM 16.00 16.00 / M x
5.00 M
RM
80.00
RM
321.78
5.00 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 56 250.00 M /
100.00 250.00
RM
56
RM
4.44
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
56 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item d Page35 Supply, erect and install 140 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.75 @ RM 7.35 = RM RM = 8.82 394.64 RM 62.64 0.75 @ RM ### = RM 259.82 RM RM 20.00 20.00 / M x
6.30 M
RM
126.00
RM
394.64
6.30 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 48 250.00 M /
100.00 250.00
RM
48
RM
5.25
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
48 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item e Page35 Supply, erect and install 168 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.75 @ RM 7.35 = RM RM = 8.82 413.54 RM 65.64 0.75 @ RM ### = RM 259.82 RM RM 23.00 23.00 / M x
6.30 M
RM
144.90
RM
413.54
6.30 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 43 250.00 M /
100.00 250.00
RM
43
RM
5.88
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
43 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item f Page35 Supply, erect and install 194 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.90 @ RM 7.35 = RM RM = 11.91 562.67 RM 70.33 0.90 @ RM ### = RM 350.76 RM RM 25.00 25.00 / M x
8.00 M
RM
200.00
RM
562.67
8.00 M
Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 44 250.00 M /
100.00 250.00
RM
44
RM
5.72
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
152.00
Day @
RM
35.00
= =
RM RM
70.00 287.00
: :
RM
44 287.00
M /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
Supply and install 600 mm aluminium Ragulatory and Warning sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting
A) Material i) Sign plate (supply price / No.) : = RM 300.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per No. : C) Workmen i) Ganger : 1 x 5 250.00 Nos /
100.00 250.00
RM
RM
51.02
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
190.00
Day @
RM
35.00
= =
RM RM
70.00 325.00
: :
RM
5 325.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting
A) Material i) Sign plate (supply price / M2) : = RM 539.50
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Backhoe : 1 x
Day @
RM
270.00
Per day
RM
270.00
iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per M2 : C) Workmen i) Ganger : 1 x 12 520.00 M2 /
100.00 520.00
RM
12
RM
42.62
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
190.00
Day @
RM
35.00
= =
RM RM
70.00 325.00
: :
RM
12 325.00
M2 /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item h(I) Page35 Supply and install 600 mm aluminium Warning and Regulatory sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting
A) Material i) Sign plate (supply price / No.) : = RM 250.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per No. : C) Workmen i) Ganger : 1 x 7 250.00 Nos. /
100.00 250.00
RM
RM
34.97
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
190.00
Day @
RM
35.00
= =
RM RM
70.00 325.00
: :
RM
7 325.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item h(ii) Page35 Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting
A) Material i) Sign plate (supply price / M2) : = RM 479.50
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Backhoe : 1 x
Day @
RM
270.00
Per day
RM
270.00
iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per M2 : C) Workmen i) Ganger : 1 x 9 520.00 M2 /
100.00 520.00
RM
RM
58.10
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
Per day
RM
190.00
Day @
RM
35.00
= =
RM RM
70.00 325.00
: :
RM
9 325.00
M2 /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item a Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing warning and regulatory signboard panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 19.30
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
190.00 505.00
: :
RM
10 505.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item b Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Warning and Regulatory signboard panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
190.00 505.00
: :
RM
5 505.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair andand Adjustment of dented Existing Sign of sign panel, and reinstall existing Directional Item c Page36 Dismantle repair the portion and Information signboard panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 20.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
190.00 505.00
: :
RM
8 505.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item d Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
266.00 581.00
: :
RM
4 581.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item e Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 3.0 m2 but not exceeding 6.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 50.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
266.00 581.00
: :
RM
3 581.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item f Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 6.0 m2 but not exceeding 9.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 70.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
266.00 581.00
: :
RM
2 581.00
Nos. /
= = = = Take
RM RM RM RM RM
ADD :
15%
Road Sign
ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item g Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 9.0 m2 but not exceeding 12.0 m2 inclusive of new mounting, clips, Ubolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 90.00
B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day
RM
150.00
ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x
RM
100.00
Day @
RM
65.00
Per day
RM
65.00
Day @
RM
38.00
RM RM
266.00 581.00
: :
RM
2 581.00
Nos. /
= = = = Take
RM RM RM RM RM .
ADD :
15%
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;; ;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
ROAD FURNITURES MAINTENANCE OF KILOMETER POSTS Replacement / Install of Kilometer Posts Item a Page 37 Provide everything necessary for dismantle, remove and dispose the damaged existing Kilometre and replace with new Kilometre post Type "A"
A) Material I) Precast r.c. Kilometre post (supply price / No.) B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 x 1 Day @ RM 150.00 per day = RM 150.00 = RM 300.00
iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : C) Workmen i) Ganger : 1 x 1 Day @ RM 65.00 per day = RM 65.00 per day = RM 100.00
RM
2 Nos 605.00 /
= RM = RM = RM = RM RM
ADD :
P&O
15%
Kilometer Post
ROAD FURNITURES MAINTENANCE OF KILOMETER POSTS Replacement / Install of Kilometer Posts Item b Page 37 Provide everything necessary for dismantle, remove and dispose the damaged existing Kilometre and replace with new Kilometre post Type "B"
A) Material I) Precast r.c. Kilometre post (supply price / No.) B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 x 1 Day @ RM 150.00 per day = RM 150.00 = RM 200.00
iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : C) Workmen I) Ganger : 1 x 1 Day @ RM 65.00 per day = RM 65.00 per day = RM 100.00
RM
3 Nos 605.00 /
= RM = RM = RM = RM RM
ADD :
P&O
15%
Kilometer Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Remove, dismantle and dispose the damaged delineator post
A) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Item a Page 38
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00
B) Workmen I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM 152.00 382.00
RM
55 Nos 382.00 /
= RM = RM = RM RM Take RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Item b Page 38 Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor to replace the existing damaged or missing post
A) Material I) Flexible delineator post (supply price / No.) = RM 125.00
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 100.00
C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 467.00 x 1 Day @ RM 65.00 per day = RM 65.00
RM
33 Nos 467.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Supply and install new reflector strips complete with bolts and nuts to replace the missing and damaged existing delinator strips
A) Material I) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set) =
Item c Page 38
RM
5.00
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00
C) Workmen I) General worker 3 x 1 Day @ RM 38.00 per day Total = = RM RM 114.00 344.00
RM
58 Nos 344.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units
Item d Page 38
Remove, dismantle, disposed and install new timber post to replace the existing damaged or missing post
A) Material I) Delineator post (supply price / No) = RM 18.20
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00
C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 447.00 x 1 Day @ RM 65.00 per day = RM 65.00
RM
51 Nos 447.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Supply and install new delineator timber post
A) Material I) Delineator post (supply price / No)
Item e Page 38
= RM
18.20
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00
C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 447.00 x 1 Day @ RM 65.00 per day = RM 65.00
RM
51 Nos 447.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Item f Page 38 Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor soil anchor
A) Material I) Delineator post (supply price / No) = RM 125.00
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 100.00
C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 467.00 x 1 Day @ RM 65.00 per day = RM 65.00
RM
52 Nos 467.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Supply and install new delineator strips complete with bolts, nuts and fittings
A) Material I) G.I. Strip, c/w. clip, washer, bolt and nuts (supply price/Set)
Item g Page 38
= RM
5.00
B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00
Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00
C) Workmen I) Ganger : 1 I) General worker 3 x 1 Day @ RM 38.00 per day Total = = RM RM 114.00 409.00 x 1 Day @ RM 65.00 per day = RM 65.00
RM
75 Nos 409.00 /
= = = = Take
RM RM RM RM RM
ADD :
P&O
15%
Delineator Post
ROAD FURNITURES MISCELLANEOUS Hidro Cell Item a Page39 Supply and install Hidro Cell Cluster containing 37 tubes complete with safety belt, bolts, washers, nuts, support legs and hidro cells and all neceassary fittings
A) Material I) Hidro Cell ADD : P&O : Rate Per No. Take 15% = = RM = RM = RM RM 22,851.00 3,427.65 26,278.65 26,278.00
Misc
ROAD FURNITURES MISCELLANEOUS Hidro Cell Provide everything necessary for refilling fluid in the Hidro cell cluster
A) Machinery I) Water pump (3" dia.) 1 x ii) Miscellaneous Allow sum : iii) Pick-up truck c/w water tank 1 x 1 Day Productivity Per Day Machinery Cost Per No B) Workmen I) Ganger 1 ii) General worker 2 x 1 Day @ RM 38.00 per day =RM Total =RM 76.00 141.00 x 1 Day @ RM 65.00 per day =RM 65.00 : :
Item b Page39
1 Day
RM
100.00
RM
50.00
RM
RM
1 No 300.00 /
: :
RM
1 Nos 141.00 /
= RM = RM = RM = RM Take RM
ADD :
15%
Misc