ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Removal, Dismantle and Replace of Damage Components Removal, dismantle

and dispose the damaged guardrail beam.


A) Machinery. i) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00 Backhoe : 1

Item a, page 29

Per day

RM

150.00

ii)

1 Day

RM

270.00

Per day

RM

270.00

iii) Tipper truck (6-wheeler) : 1 x 1 Day

RM

250.00

Per day

RM

250.00

iv) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 770.00

Productivity Per Day Machinery Cost Per M B) Workmen i) Ganger : 1

: : RM

91 770.00

M / 91 = RM 8.51

1 Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

1 Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per M

: : RM

91 255.00

M / 91 Row cost Per M = RM = RM = RM = RM RM 2.82 11.33 1.70 13.02 13.00

ADD:

P& O Rate Per M

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged End Wing or Fish Tail (Terminal end Type 1)
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00

Item b i, page 29

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: :

RM

33 250.00

NO /

33

= RM

7.69

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 4 x

Day

RM

38.00

Per day

RM RM

152.00 217.00

Productivity Per Day Workmen Cost Per NO

: : RM

33 217.00

NO /

33 Row cost Per NO

= RM = RM = RM = RM RM

6.68 14.37 2.16 16.52 16.50

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged Terminal Anchorage Unit Type 2)
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00

Item b ii, page 29

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

17 250.00

NO /

17

= RM

14.71

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 4 x

Day

RM

38.00

Per day

RM RM

152.00 217.00

Productivity Per Day Workmen Cost Per NO

: : RM

17 217.00

NO /

17 Row cost Per NO

= RM = RM = RM = RM RM

12.76 27.47 4.12 31.59 31.50

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged 90 degrees Twist Unit Type 3
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00

Item b iii, page 29

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

17 250.00

NO /

17

= RM

14.71

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 4 x

Day

RM

38.00

Per day

RM RM

152.00 217.00

Productivity Per Day Workmen Cost Per NO

: : RM

17 217.00

NO /

17 Row cost Per NO

= RM = RM = RM = RM RM

12.76 27.47 4.12 31.59 31.50

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged Terminal 1 : 6 / Sloping End Unit Type 4
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00

Item b iv, page 29

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

17 250.00

NO /

17

= RM

14.71

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 4 x

Day

RM

38.00

Per day

RM RM

152.00 217.00

Productivity Per Day Workmen Cost Per NO

: : RM

17 217.00

NO /

17 Row cost Per NO

= RM = RM = RM = RM RM

12.76 27.47 4.12 31.59 31.50

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Removal, dismantle and dispose the damaged guardrail post
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00 Backhoe : 1

Item c, page 29

Per day

RM

150.00

ii)

Day

RM

270.00

Per day

RM

270.00

iii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 520.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: :

RM

27 520.00

NO /

27

= RM

19.40

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 3 x

Day

RM

38.00

Per day

RM RM

114.00 179.00

Productivity Per Day Workmen Cost Per NO

: :

RM

27 179.00

NO /

27 Row cost Per NO

= RM = RM = RM = RM RM

6.68 26.08 3.91 29.99 30.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing damaged nose yellow
A) Machinery. I) Backhoe 1

Item d, page 29

Day

RM

270.00

Per day

RM

270.00

ii)

Miscellaneous Allow sum (per day)

RM

150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 280.00

Per day

= Total =

RM RM

280.00 700.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

6 700.00

NO /

= RM

114.27

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 3 x

Day

RM

38.00

Per day

RM RM

114.00 179.00

Productivity Per Day Workmen Cost Per NO

: : RM

6 179.00

NO /

6 Row cost Per NO

= RM = RM = RM = RM RM

29.22 143.49 21.52 165.01 165.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing damaged cartridge
A) Machinery. I) Backhoe 1

Item e, page 29

Day

RM

270.00

Per day

RM

270.00

ii)

Miscellaneous Allow sum (per day)

RM

150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00

Per day

= Total =

RM RM

150.00 570.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

3 570.00

NO /

RM

165.46

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 3 x

Day

RM

38.00

Per day

RM RM

114.00 179.00

Productivity Per Day Workmen Cost Per NO

: : RM

3 179.00

NO /

3 Row cost Per NO

= = = = Take

RM RM RM RM RM

51.96 217.42 32.61 250.03 250.00

ADD:

P& O : Rate Per NO.

15%

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Remove, Dismantle and Replace of Damaged Components Dismantle and removed existing beam panel
A) Machinery. I) Backhoe 1

Item f, page 29

Day

RM

270.00

Per day

RM

270.00

ii)

Miscellaneous Allow sum (per day)

RM

150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00

Per day

= Total =

RM RM

150.00 570.00

Productivity Per Day Machinery Cost Per NO B) Workmen I) Ganger : 1

: : RM

5 570.00

NO /

= RM

109.20

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 3 x

Day

RM

38.00

Per day

RM RM

114.00 179.00

Productivity Per Day Workmen Cost Per NO

: : RM

5 179.00

NO /

5 Row cost Per NO

= RM = RM = RM = RM Take RM

34.29 143.49 21.52 165.01 165.00

ADD:

P& O : Rate Per NO.

15%

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Realigning of existing (line & level) Item g, page 29 Realign and straighten the line of existing guardrail including correct the level and verticality position of existing guardrail post.
A) Machinery. I) Pick-up truck (3.0T) for carring,materials, workers and tools : 1 x 1 Day @ RM 150.00 Hydraulic jack 1 x

Per day

RM

150.00

ii)

Day

RM

100.00

Per day

RM

100.00

iii) Backhoe : 1

Day

RM

270.00

Per day

= Total =

RM RM

270.00 520.00

Productivity Per Day Machinery Cost Per M B) Workmen I) Ganger : 1

: :

RM

97 520.00

M /

97

= RM

5.36

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per M

: :

RM

97 255.00

M /

97 Row cost Per M

= RM = RM = RM = RM RM

2.63 7.99 1.20 9.19 9.20

ADD:

P& O : Rate Per M

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Realigning of existing (line & level) Supply and replace missing delinator piece on guardrail
A) Material I) B) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set)

Item h, page 29

= RM

5.00

Machinery I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00

C)

Workmen I) General worker 3 x 1 Day @ RM 38.00 per day Total Productivity Per day Workmen Cost Per No. : : 43 344.00 NO / = RM RM 114 344.00

RM

43 Raw cost per No.

= RM = RM = RM = RM RM

8.06 13.06 1.96 15.01 15.00

ADD :

P&O : Rate Per No.

15%

Take

Guard Rails

ROAD FURNITURES MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised new guardrail beams
A) Material I) ii) Guardrail (supply price/M) Transportation(per M) : : : = RM RM

Item a, page 30

35.00 10.00 = RM 45.00

iii) Material cost (per M) B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, workers and tools : 1 x 1 Day @ RM 150.00

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day) Total

= =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per M C) Workmen I) Ganger : 1

: :

RM

71 250.00

M /

71

= RM

3.55

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per M

: :

RM

71 255.00

M /

71 Row cost Per M

= RM = RM = RM = RM RM

3.62 52.16 7.82 59.99 60.00

ADD:

P& O : Rate Per M

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised End wing or Fish Tail (Terminal unitType 1)
A) Material I) ii) Terminal End Type l (supply price/No) Transportation(per No) : : = RM = RM

Item b i, page 30

58.00 5.00 = RM 63.00

iii) Material cost (per No) : B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1

: :

RM

29 250.00

NO /

29

= RM

8.68

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per No

: :

RM

29 190.00

NO /

29 Row cost Per No

= RM = RM = RM = RM RM

6.60 78.28 11.74 90.02 90.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised Terminal anchorage unit Type 2
A) Material i) ii) Terminal anchorage unit Type 2 (supply price/No) Transportation(per No) : : = RM = RM

Item b ii, page 30

380.00 5.00 = RM 385.00

iii) Material cost (per No) : B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1

: :

RM

80 250.00

NO /

80

= RM

3.13

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per No

: :

RM

80 255.00

NO /

80 Row cost Per No

= RM = RM = RM = RM RM

3.19 391.31 58.70 450.01 450.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised 90 degrees Twist Unit Type 3
A) Material I) ii) Twist unit type 3 (supply price/No) Transportation(per No) : : = RM RM

Item b iii, page 30

550.00 5.00 = RM 555.00

iii) Material cost (per No) : B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1

: :

RM

9 250.00

NO /

= RM

26.60

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per No

: :

RM

9 255.00

NO /

9 Row cost Per No

= RM = RM = RM = RM RM

27.13 608.72 91.31 700.03 700.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised Terminal section 1:6 / Sloping End Type 4
A) Material I) ii) Terminal Anchorage Type 4 (supply price/No) Transportation(per No) : : = RM RM

Item b iv, page 30

158.00 5.00 = RM 163.00

iii) Material cost (per No) : B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00

Per day

RM

150.00

ii)

Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1

: :

RM

14 250.00

NO /

14

= RM

18.32

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per No

: :

RM

14 255.00

NO /

14 Row cost Per No

= RM = RM = RM = RM RM

18.68 200.00 30.00 230.00 230.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and install galvanised guadrail post complete with packer
A) Material I) ii) Guardrail post (supply price / No) Transportation(per No) : : = RM RM

Item c, page 30

87.00 2.00 = RM 89.00

iii) Material cost (per No) : B) Machinery. I)

Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Arrow Rammer : 1 x

Per day

RM

150.00

ii)

Day

RM

300.00

Per day

RM

300.00

iii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools): Allow sum (per day)

= Total =

RM RM

100.00 550.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1

: :

RM

52 550.00

NO /

52

= RM

10.50

Day

RM

65.00

Per day

RM

65.00

ii)

General Worker : 5 x

Day

RM

38.00

Per day

RM RM

190.00 255.00

Productivity Per Day Workmen Cost Per No

: :

RM

52 255.00

NO /

52 Row cost Per No

= RM = RM = RM = RM RM

4.87 104.36 15.65 120.02 120.00

ADD:

P& O : Rate Per NO.

15%

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Item d, page 30 Supply and replace new yellow nose for the crash cushion inclusive of all necessary preparatory work.
I) Nose Yellow = RM
21,090.00

ADD:

P& O : Rate Per NO.

15%

= RM = RM RM

3,163.50 24,253.50 24,250.00

Take

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Item e, page 30 Supply and replace new cartridge for the crash cushion inclusive of all necessary preparatory work.
A) Material I) Cartridge ADD: P& O : Rate Per NO. Take 15% = RM = RM = RM RM 2,740.00 411.00 3,151.00 3,150.00

Guard Rails

ROAD FURNITURE MAINTENANCE OF GUARDRAIL AND CRASH CUSHION Installation of New Sections Supply and replace new beam panel.
A) Material I) Cartridge ADD: P& O : Rate Per NO. 15%

Item g, page 30

= RM = RM = RM Take RM

2,892.00 433.80 3,325.80 3,325.00

Guard Rails

ROAD FURNITURE MAINTENANCE OF STUDS Reinstallation of existing studs Item a,page 31 To reinstall the missing road stud at existing location with new single - sided Road stud
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 16.20 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total = Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x : : 55 250.00 No /

RM RM

100.00 250.00

RM

55

RM

4.55

Day

RM

65.00

Per day

RM

65.00

ii) General Worker : 2 x 1 iii) Flagman 2 x

Day

RM

38.00

Per day

RM

76.00

Day

RM

35.00

Per day

RM RM

70.00 211.00

Productivity Per Day Workmen Cost Per No

: :

RM

55 211.00

No / 55 Row cost Per No 15%

= = = = Take

RM RM RM RM RM

3.84 26.08 3.91 29.99 30.00

ADD:

P& O : Rate Per NO.

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Reinstallation of existing studs Item b,page 31 To reinstall the missing road stud at existing location with new double - sided Road stud
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 21.40 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

55 250.00

No /

55

RM

4.56

Day

RM

65.00

Per day

RM

65.00

ii) General Worker : 2 x 1 iii) Flagman 2 x

Day

RM

38.00

Per day

RM

76.00

Day

RM

35.00

Per day

RM RM

70.00 211.00

Productivity Per Day Workmen Cost Per No

: :

RM

55 211.00

No /

55 Row cost Per No

= = = = Take

RM RM RM RM RM

3.85 31.31 4.70 36.01 36.00

ADD:

P& O : Rate Per NO.

15%

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs Item c,page 31 To replace the damaged road stud at existing location with new single - sided Road stud
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = RM RM 16.20 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

39 250.00

No /

39

RM

6.44

Day

RM

65.00

Per day

RM

65.00

ii) General Worker : 2 x 1 iii) Flagman 2 x

Day

RM

38.00

Per day

RM

76.00

Day

RM

35.00

Per day

RM RM

70.00 211.00

Productivity Per Day Workmen Cost Per No

: :

RM

39 211.00

No /

39 Row cost Per No

= = =

RM RM RM

5.44 29.58 4.44 34.02 34.00

ADD:

P& O : Rate Per NO.

15%

= RM Take RM

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs Item d,page 31 To replacel the damaged road stud at existing location with new double - sided Road stud
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = = RM RM 21.40 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

39 250.00

No /

39

RM

6.44

Day

RM

65.00

Per day

RM

65.00

ii) General Worker : 2 x 1 iii) Flagman 2 x

Day

RM

38.00

Per day

RM

76.00

Day

RM

35.00

Per day

RM RM

70.00 211.00

Productivity Per Day Workmen Cost Per No

: :

RM

39 211.00

No /

39 Row cost Per No

= = = = Take

RM RM RM RM RM

5.44 34.78 5.22 40.00 40.00

ADD:

P& O : Rate Per NO.

15%

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Replacement of Existing Studs To remove existing road stud and refix at same position
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =

Item e,page 31

RM RM

16.20 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

55 250.00

No /

55

RM

4.55

Day

RM

65.00

Per day

RM

65.00

ii) General Worker : 2 x 1 iii) Flagman 2 x

Day

RM

38.00

Per day

RM

76.00

Day

RM

35.00

Per day

RM RM

70.00 211.00

Productivity Per Day Workmen Cost Per No

: :

RM

55 211.00

No /

55 Row cost Per No

= = = = Take

RM RM RM RM RM

3.84 26.08 3.91 29.99 30.00

ADD:

P& O : Rate Per NO.

15%

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Installation of New Studs Supply and lay new single -side Road in accordance to specification.
A) Material I) Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =

Item f,page 31

RM RM

16.20 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

42 250.00

No /

42

RM

5.91

Day

RM

65.00

Per day

RM

65.00

ii) Semi-skiller worker : 1 x 1 iii) General Worker : 3 x 1 iv) Flagman 2 x

Day

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

114.00

Day

RM

35.00

Per day

RM RM

70.00 289.00

Productivity Per Day Workmen Cost Per No

: :

RM

42 289.00

No /

42 Row cost Per No

= = =

RM RM RM

6.83 30.44 4.57 35.01 35.00

ADD:

P& O : Rate Per NO.

15%

= RM Take RM

Road Stud

ROAD FURNITURE MAINTENANCE OF STUDS Installation of New Studs Supply and lay new double-side Road stud in accordance to specification.
A) Material I) Prismo II Road stud (Supply price / No) : ii) Epoxy in-fill (per no) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day : = =

Item g,page 31

RM RM

21.40 1.50

RM

150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 250.00

Productivity Per Day Machinery Cost Per No C) Workmen I) Ganger : 1 x

: :

RM

35 250.00

No /

35

RM

7.12

Day

RM

65.00

Per day

RM

65.00

ii) Semi-skiller worker : 1 x 1 iii) General Worker : 3 x 1 iv) Flagman 2 x

Day

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

114.00

Day

RM

35.00

Per day

RM RM

70.00 289.00

Productivity Per Day Workmen Cost Per No

: :

RM

35 289.00

No /

35 Row cost Per No

= = = = Take

RM RM RM RM RM

8.23 38.26 5.74 43.99 44.00

ADD:

P& O : Rate Per NO.

15%

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

Road Stud

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item a,page 32 Prepare and apply white or yellow temporary roadline paint for pavement markings for 150mm wide single continous edge line marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item b,page 32 Prepare and apply white temporary roadline paint for pavement markings for 150mm wide single continous center line and lane markings
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item c,page 32 Prepare and apply white temporary roadline paint for pavement markings for 100mm wide intermittent center line and lane marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item d,page 32 Prepare and apply white temporary roadline paint for pavement markings for 150mm wide yellow edge marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item e,page 32 Prepare and apply white temporary roadline paint for pavement markings 200mm wide intermitent give-way line wide with 300mm length each and at 200mm gap
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

= RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item f, page32 Prepare and apply white temporary roadline paint for pavement markings for 300mm wide continous stop line marking
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item g, page32 Prepare and apply white temporary roadline paint for pavement markings for 300mm wide chevron hatching for merging / diverging traffic and cross hatching
A) Material I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= =

RM RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

124 370.00

M2 /

124

RM

2.98

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

124 262.00

M2 /

124 Row cost Per M2

= RM = RM = RM = RM RM

2.11 6.75 1.01 7.76 7.75

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item h, page32 Prepare and apply white temporary roadline paint for pavement markings for "AWAS" and other pavement lattering marking
A) Material I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= RM = RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

83 370.00

M2 /

83

= RM

4.46

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

83 262.00

M2 /

83 Row cost Per M2

= RM = RM = RM = RM RM

3.16 9.26 1.39 10.65 10.65

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item i, page32 Prepare and apply white temporary roadline paint for pavement markings for pavement directional arrow marking
A) Material I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= RM = RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

83 370.00

M2 /

83

= RM

4.46

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

83 262.00

M2 /

83 Row cost Per M2

= RM = RM = RM = RM RM

3.16 9.26 1.39 10.65 10.65

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Repainting of Existing Marking Item j, page32 Prepare and apply black temporary roadline paint to erase and correct including necessary adjustment of existing pavement markings
A) Material I) Roadline paint (black) - Cost @ Per Drum (20 litres) = RM 300.00 a) Approx. Coverage / Drum : 200 M2 b) Cost (per M2) RM 300.00 / 200 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Setting equipments and Tools (1 set) : 1 x 1 Day @ : 10%

= RM = RM

1.50 0.15 = RM 1.65

RM

150.00

RM

120.00

Per day

RM

120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment): Allow sum Per day = Total =

RM RM

100.00 370.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

102 370.00

M2 /

102

= RM

3.63

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

102 262.00

M2 /

102 Row cost Per M2

= RM = RM = RM = RM RM

2.57 7.85 1.18 9.02 9.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item a,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings or sizes100mm to 150mm wide single continuos edge line marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item b,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of 150mm width single continuos center line and lane marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item c,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for intermittent center line and lane marking of 100mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item d,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement marking for 150mm wide single continuos edge marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item e, page33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for intermittent give-way line 200mm wide, with 300mm length each and 200mm gap
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item f, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for continuos stop line of 300mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item g, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings for 300mm width chevron hatching for merging / diverging tracffic and cross hatching
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

122 620.00

M2 /

122

= RM

5.10

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

122 262.00

M2 /

122 Row cost Per M2

= RM = RM = RM = RM RM

2.16 17.40 2.61 20.02 20.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item h, page 33 Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick 600mm
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 200 M2 b) Cost (per M2) RM 2,200.00 / 200 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

11.00

M2 /

1,250

= RM = RM

2.08 13.08 1.31 = RM 14.39

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

120 620.00

M2 /

120

= RM

5.17

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

120 262.00

M2 /

120 Row cost Per M2

= RM = RM = RM = RM RM

2.18 21.74 3.26 25.00 25.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item i, page 33 Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick and 500mm wide
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 200 M2 b) Cost (per M2) RM 2,200.00 / 200 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

11.00

M2 /

1,250

= RM = RM

2.08 13.08 1.31 = RM 14.39

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

120 620.00

M2 /

120

= RM

5.17

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day Total

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

120 262.00

M2 /

120 Row cost Per M2

= RM = RM = RM = RM RM

2.18 21.74 3.26 25.00 25.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item j,page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of "AWAS" or other lattering on pavement marking
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item k, page 33 Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings of pavement direction arrow
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

160 620.00

M2 /

160

= RM

3.88

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

160 262.00

M2 /

160 Row cost Per M2

= RM = RM = RM = RM RM

1.64 15.66 2.35 18.01 18.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item I,page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of intermittent center line100mm wide and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

43 620.00

M2 /

43

= RM

14.27

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

43 262.00

M2 /

43 Row cost Per M2

= RM = RM = RM = RM RM

6.03 30.44 4.57 35.01 35.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item n, page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of continuos edge line 150mm and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

43 620.00

M2 /

43

= RM

14.27

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

43 262.00

M2 /

43 Row cost Per M2

= RM = RM = RM = RM RM

6.03 30.44 4.57 35.01 35.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF ROAD MARKINGS Painting of New Markings Item o, page 33 Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of double line 100mm wide and 3.0mm thick
A) Material I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00 a) Approx. Coverage / MT 308 M2 b) Cost (per M2) RM 2,200.00 / 308 ii) Glass bead - Cost @ Per Mt RM 2,600.00 a) Approx. Coverage / Mt : 1,250 b) Cost (per M2) RM 2,600.00 ii) ADD : Wastage iii)Material cost (per M2) B) Machinery. I) Pick-up truck (3.0T) for carrying, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Pick-up truck (1T) for carrying Boiler: 1 x 1 Day @ iii)Boiler and heater : 1 x 1 iv)Screeding machine : 1 x 1 : 10%

= RM

7.14

M2 /

1250

= RM = RM

2.08 9.22 0.92 = RM 10.15

RM

150.00

RM

130.00

Per day

RM

130.00

Day

RM

120.00

Per day

RM

120.00

Day

RM

100.00

Per day

RM

100.00

v) Setting equipment and Tools (1 set) 1 x 1 Day @

RM

120.00

Per day Total

= =

RM RM

120.00 620.00

Productivity Per Day Machinery Cost Per M2 C) Workmen

: :

RM

43 620.00

M2 /

43

= RM

14.27

I) Semi-killed worker (for setting) 1 x 1 Day ii) General Worker : 4 x iii)Flagman 2 x

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day

RM RM

70.00 262.00

Productivity Per Day Workmen Cost Per M2

: :

RM

43 262.00

M2 /

43 Row cost Per M2

= RM = RM = RM = RM RM

6.03 30.44 4.57 35.01 35.00

ADD:

P& O : Rate Per M2.

15%

Take

Road Marking

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item a Page 34 Excavate, dismantle and reinstall the existing concrete road kerb for straightening of misaligned kerbs
A) Material i) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & equipments) : Allow sum Per day Total Productivity Per Day Workmen Cost Per M : : 76 478.00 M / M 76

RM

150.00

RM RM

100.00 478.00

RM

= RM Raw cost Per M = RM = RM = RM RM

6.32 11.32 1.70 13.02 13.00

ADD :

P&O

: Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(i) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type I
A) Material i) Kerb Type I (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 30.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 116 478.00 M /

RM RM

100.00 478.00

RM

116 Raw cost Per M

= RM = RM = RM = RM Take RM

4.12 39.12 5.87 44.99 45.00

ADD :

P&O Rate Per M

15%

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(ii) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type II
A) Material i) Kerb Type II (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 27.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 320 478.00 M / M 320

RM RM

100.00 478.00

RM

= RM Raw cost Per M = RM = RM = RM RM

1.49 33.49 5.02 38.52 38.50

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(iii) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type III
A) Material i) Kerb Type III (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 29.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 141 478.00 M /

RM RM

100.00 478.00

RM

141 Raw cost Per M

= RM = RM = RM = RM RM

3.39 37.39 5.61 43.00 43.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(iv) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type IV
A) Material i) Kerb Type IV (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 23.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 128 478.00 M /

RM RM

100.00 478.00

RM

128 Raw cost Per M

= RM = RM = RM = RM RM

3.73 31.73 4.76 36.49 36.50

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Realignment of Existing Kerbs Item b(v) Page 34 Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new concrete kerb Type V
A) Material i) Kerb Type V (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x = RM = RM 28.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 109 478.00 M /

RM RM

100.00 478.00

RM

109 Raw cost Per M

= RM = RM = RM = RM RM

4.39 37.39 5.61 42.99 43.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type I including concrete bedding
A) Material i) Kerb Type I (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(i) Page 34

= RM = RM

30.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 71 478.00 M /

RM RM

100.00 478.00

RM

71 Raw cost Per M

= RM = RM = RM = RM RM

6.75 41.75 6.26 48.01 48.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type II including concrete bedding
A) Material i) Kerb Type II (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(ii) Page 34

= RM = RM

27.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 105 478.00 M /

RM RM

100.00 478.00

RM

105 Raw cost Per M

= RM = RM = RM = RM RM

4.55 36.55 5.48 42.04 42.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type III including concrete bedding
A) Material i) Kerb Type III (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(iii) Page 34

= RM = RM

29.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 93 478.00 M /

RM RM

100.00 478.00

RM

93 Raw cost Per M

= RM = RM = RM = RM RM

5.14 39.14 5.87 45.01 45.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type IV including concrete bedding
A) Material i) Kerb Type IV (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(iv) Page 34

= RM = RM

23.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 95 478.00 M /

RM RM

100.00 478.00

RM

95 Raw cost Per M

= RM = RM = RM = RM RM

5.06 33.06 4.96 38.02 38.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type V including concrete bedding
A) Material i) Kerb Type V (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(v) Page 34

= RM = RM

28.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 99 478.00 M /

RM RM

100.00 478.00

RM

99 Raw cost Per M

= RM = RM = RM = RM RM

4.83 37.83 5.67 43.50 43.50

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VI including concrete bedding
A) Material i) Kerb Type VI (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(vi) Page 34

= RM = RM

20.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 105 478.00 M /

RM RM

100.00 478.00

RM

105 Raw cost Per M

= RM = RM = RM = RM RM

4.55 29.55 4.43 33.99 34.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VII including concrete bedding
A) Material i) Kerb Type VII (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(vii) Page 34

= RM = RM

30.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 40 478.00 M /

RM RM

100.00 478.00

RM

40 Raw cost Per M

= RM = RM = RM = RM RM

11.95 46.95 7.04 53.99 52.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Installation of New Kerbs Supply and install precast concrete road kerb of Type VIII including concrete bedding
A) Material i) Kerb Type VIII (supply price / M) ii) Concrete blinding & haunching (per M) B) Workmen i) General worker : 6 x

Item c(viii) Page 34

= RM = RM

18.00 5.00

Day

RM

38.00

Per day

RM

228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) : Allow sum Per day = Total Productivity Per Day Workmen Cost Per M : : 73 478.00 M / M 73

RM RM

100.00 478.00

RM

= RM Raw cost Per M = RM = RM = RM RM

6.59 29.59 4.44 34.03 34.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Item d Page 34 Supply and apply one coat primer and two coats of approved weatherproof paint to existing concrete kerbs
A) Material i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) a) Approx. Coverage/Ca : 40 b) Cost (per M) : RM 65.00 ii) ADD : Wastage : 10% = M / 40 = = RM RM RM = 65.00 1.63 0.16 RM 1.79

iii) Material cost (per M) B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner) Allow sum Per day C) Workmen i) Semi-skilled worker : 1 x ii) General worker : 4 x iii) Flagman : 2

RM

150.00

RM

100.00

Day

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day Total

RM RM

70.00 512.00

Productivity Per Day Workmen Cost Per M

: :

RM

149 512.00

M /

149 Raw cost Per M

= RM = RM = RM = RM RM

3.44 5.22 0.78 6.01 6.00

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

ROAD FURNITURES MAINTENANCE OF KERBS Repainting of Existing Kerbs Item e Page 34 Scrape, brush, clean, prepare and apply one coat primer and two coats of approved weatherproof paint to existing concrete kerbs
A) Material i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) a) Approx. Coverage/Ca : 40 b) Cost (per M) : RM 65.00 ii) ADD : Wastage : 10% = M / 40 = = RM RM RM = 65.00 1.63 0.16 RM 1.79

iii) Material cost (per M) B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner) Allow sum Per day C) Workmen i) Semi-skilled worker : 1 x ii) General worker : 4 x iii) Flagman : 2

RM

150.00

RM

100.00

Day

RM

40.00

Per day

RM

40.00

Day

RM

38.00

Per day

RM

152.00

Day

RM

35.00

Per day Total

RM RM

70.00 512.00

Productivity Per Day Workmen Cost Per M

: :

RM

132 512.00

M /

132 Raw cost Per M

= RM = RM = RM = RM RM

3.88 5.67 0.85 6.52 6.50

ADD :

P&O Rate Per M

15%

Take

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

Road Kerbs

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item a Page35 Supply, erect and install 76 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting, concrete footing and excavation
A) Material i) M.S. post (supply price) : : : x : 1.50 x 0.75 @ RM 7.35 = RM RM = 6.20 236.89 RM 59.22 0.75 @ RM ### = RM 182.69 RM RM 12.00 12.00 / M x

4.00 M

RM

48.00

ii) Concrete footing 0.75 x 1.50 iii) Excavation 0.75 x

iv) Cost (per M) B) Machinery i)

RM

236.89

4.00 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 52 250.00 M /

100.00 250.00

RM

52

RM

4.81

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

52 287.00

M /

52 Raw cost Per M

= = = = Take

RM RM RM RM RM

5.52 69.55 10.43 79.98 80.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item b Page35 Supply, erect and install 89 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 1.80 x 0.75 @ RM 7.35 = RM RM = 7.44 296.67 RM 59.33 0.75 @ RM ### = RM 219.23 RM RM 14.00 14.00 / M x

5.00 M

RM

70.00

ii) Concrete footing 0.75 x 1.80 iii) Excavation 0.75 x

iv) Cost (per M) B) Machinery i)

RM

296.67

5.00 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 53 250.00 M /

100.00 250.00

RM

53

RM

4.76

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

53 287.00

M /

53 Raw cost Per M

= = = = Take

RM RM RM RM RM

5.47 69.56 10.43 80.00 80.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item c Page35 Supply, erect and install 114 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting, and concrete footing
A) Material i) M.S. post (supply price) : : : x : 1.80 x 0.75 @ RM 7.35 = RM RM = 7.94 321.78 RM 64.36 0.75 @ RM ### = RM 233.84 RM RM 16.00 16.00 / M x

5.00 M

RM

80.00

ii) Concrete footing 0.80 x 1.80 iii) Excavation 0.80 x

iv) Cost (per M) B) Machinery i)

RM

321.78

5.00 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 56 250.00 M /

100.00 250.00

RM

56

RM

4.44

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

56 287.00

M /

56 Raw cost Per M

= = = = Take

RM RM RM RM RM

5.10 73.89 11.08 84.98 85.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item d Page35 Supply, erect and install 140 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.75 @ RM 7.35 = RM RM = 8.82 394.64 RM 62.64 0.75 @ RM ### = RM 259.82 RM RM 20.00 20.00 / M x

6.30 M

RM

126.00

ii) Concrete footing 0.80 x 2.00 iii) Excavation 0.80 x

iv) Cost (per M) B) Machinery i)

RM

394.64

6.30 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 48 250.00 M /

100.00 250.00

RM

48

RM

5.25

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

48 287.00

M /

48 Raw cost Per M

= = = = Take

RM RM RM RM RM

6.03 73.92 11.09 85.01 85.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item e Page35 Supply, erect and install 168 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.75 @ RM 7.35 = RM RM = 8.82 413.54 RM 65.64 0.75 @ RM ### = RM 259.82 RM RM 23.00 23.00 / M x

6.30 M

RM

144.90

ii) Concrete footing 0.80 x 2.00 iii) Excavation 0.80 x

iv) Cost (per M) B) Machinery i)

RM

413.54

6.30 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 43 250.00 M /

100.00 250.00

RM

43

RM

5.88

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

43 287.00

M /

43 Raw cost Per M

= = = = Take

RM RM RM RM RM

6.75 78.28 11.74 90.02 90.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item f Page35 Supply, erect and install 194 mm external diameter mild steel post complete with mounting frames, clips, bolts and nuts, ledge angle, U-bolts, painting and concrete footing
A) Material i) M.S. post (supply price) : : : x : 2.00 x 0.90 @ RM 7.35 = RM RM = 11.91 562.67 RM 70.33 0.90 @ RM ### = RM 350.76 RM RM 25.00 25.00 / M x

8.00 M

RM

200.00

ii) Concrete footing 0.90 x 2.00 iii) Excavation 0.90 x

iv) Cost (per M) B) Machinery i)

RM

562.67

8.00 M

Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day Machinery Cost Per M C) Workmen i) Ganger : 1 x : : 44 250.00 M /

100.00 250.00

RM

44

RM

5.72

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 4 x 1 iii) General worker : 2 x 1

Day @

RM

38.00

Per day

RM

152.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 287.00

Productivity Per Day Workmen Cost Per M

: :

RM

44 287.00

M /

44 Raw cost Per M

= = = = Take

RM RM RM RM RM

6.57 82.62 12.39 95.02 95.00

ADD :

P&O Rate Per M

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign

Item g(I) Page35

Supply and install 600 mm aluminium Ragulatory and Warning sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting
A) Material i) Sign plate (supply price / No.) : = RM 300.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per No. : C) Workmen i) Ganger : 1 x 5 250.00 Nos /

100.00 250.00

RM

RM

51.02

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

190.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 325.00

Productivity Per Day Workmen Cost Per No.

: :

RM

5 325.00

Nos. /

5 Raw cost Per No.

= = = = Take

RM RM RM RM RM

66.33 417.35 62.60 479.95 480.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign

Item g(ii) Page35

Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting
A) Material i) Sign plate (supply price / M2) : = RM 539.50

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Backhoe : 1 x

Day @

RM

270.00

Per day

RM

270.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per M2 : C) Workmen i) Ganger : 1 x 12 520.00 M2 /

100.00 520.00

RM

12

RM

42.62

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

190.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 325.00

Productivity Per Day Workmen Cost Per M2

: :

RM

12 325.00

M2 /

12 Raw cost Per M2

= = = = Take

RM RM RM RM RM

26.64 608.76 91.31 700.08 700.00

ADD :

P&O Rate Per M2

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item h(I) Page35 Supply and install 600 mm aluminium Warning and Regulatory sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting
A) Material i) Sign plate (supply price / No.) : = RM 250.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per No. : C) Workmen i) Ganger : 1 x 7 250.00 Nos. /

100.00 250.00

RM

RM

34.97

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

190.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 325.00

Productivity Per Day Workmen Cost Per No.

: :

RM

7 325.00

Nos. /

7 Raw cost Per No.

= = = = Take

RM RM RM RM RM

45.45 330.42 49.56 379.98 380.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Installation of New Sign Item h(ii) Page35 Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames, clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting
A) Material i) Sign plate (supply price / M2) : = RM 479.50

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Backhoe : 1 x

Day @

RM

270.00

Per day

RM

270.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) : Allow sum Per day = RM RM Productivity Per Day : Machinery Cost Per M2 : C) Workmen i) Ganger : 1 x 9 520.00 M2 /

100.00 520.00

RM

RM

58.10

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1 iii) Flagman : 2 x

Day @

RM

38.00

Per day

RM

190.00

Day @

RM

35.00

Per day Total

= =

RM RM

70.00 325.00

Productivity Per Day Workmen Cost Per M2

: :

RM

9 325.00

M2 /

9 Raw cost Per M2

= = = = Take

RM RM RM RM RM

36.31 573.91 86.09 660.00 660.00

ADD :

P&O Rate Per M2

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item a Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing warning and regulatory signboard panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 19.30

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1

Day @

RM

38.00

Per day Total

RM RM

190.00 505.00

Productivity Per Day Workmen Cost Per No.

: :

RM

10 505.00

Nos. /

10 Raw cost Per No.

= = = = Take

RM RM RM RM RM

51.17 70.47 10.57 81.03 81.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item b Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Warning and Regulatory signboard panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1

Day @

RM

38.00

Per day Total

RM RM

190.00 505.00

Productivity Per Day Workmen Cost Per No.

: :

RM

5 505.00

Nos. /

5 Raw cost Per No.

= = = = Take

RM RM RM RM RM

109.31 139.31 20.90 160.20 160.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair andand Adjustment of dented Existing Sign of sign panel, and reinstall existing Directional Item c Page36 Dismantle repair the portion and Information signboard panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 20.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 5 x 1

Day @

RM

38.00

Per day Total

RM RM

190.00 505.00

Productivity Per Day Workmen Cost Per No.

: :

RM

8 505.00

Nos. /

8 Raw cost Per No.

= = = = Take

RM RM RM RM RM

66.98 86.98 13.05 100.02 100.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item d Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 7 x 1

Day @

RM

38.00

Per day Total

RM RM

266.00 581.00

Productivity Per Day Workmen Cost Per No.

: :

RM

4 581.00

Nos. /

4 Raw cost Per No.

= = = = Take

RM RM RM RM RM

144.17 174.17 26.13 200.29 200.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item e Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 3.0 m2 but not exceeding 6.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 50.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 7 x 1

Day @

RM

38.00

Per day Total

RM RM

266.00 581.00

Productivity Per Day Workmen Cost Per No.

: :

RM

3 581.00

Nos. /

3 Raw cost Per No.

= = = = Take

RM RM RM RM RM

211.27 261.27 39.19 300.46 300.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item f Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 6.0 m2 but not exceeding 9.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 70.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 7 x 1

Day @

RM

38.00

Per day Total

RM RM

266.00 581.00

Productivity Per Day Workmen Cost Per No.

: :

RM

2 581.00

Nos. /

2 Raw cost Per No.

= = = = Take

RM RM RM RM RM

234.27 304.27 45.64 349.92 350.00

ADD :

P&O Rate Per No.

15%

Road Sign

ROAD FURNITURES MAINTENANCE OF SIGNS Repair and Adjustment of Existing Sign Item g Page36 Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information signboard panels of size exceeding 9.0 m2 but not exceeding 12.0 m2 inclusive of new mounting, clips, Ubolts and other incidentals necessary
A) Material i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 90.00

B) Machinery i) Pick-up truck (3T) for carrying workers, materials, tools and equipments : 1 x 1 Day @ RM 150.00 Per day

RM

150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) : Allow sum Per day = C) Workmen i) Ganger : 1 x

RM

100.00

Day @

RM

65.00

Per day

RM

65.00

ii) General worker : 7 x 1

Day @

RM

38.00

Per day Total

RM RM

266.00 581.00

Productivity Per Day Workmen Cost Per No.

: :

RM

2 581.00

Nos. /

2 Raw cost Per No.

= = = = Take

RM RM RM RM RM .

284.80 374.80 56.22 431.02 431.00

ADD :

P&O Rate Per No.

15%

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;; ;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

Road Sign

ROAD FURNITURES MAINTENANCE OF KILOMETER POSTS Replacement / Install of Kilometer Posts Item a Page 37 Provide everything necessary for dismantle, remove and dispose the damaged existing Kilometre and replace with new Kilometre post Type "A"
A) Material I) Precast r.c. Kilometre post (supply price / No.) B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 x 1 Day @ RM 150.00 per day = RM 150.00 = RM 300.00

ii) Jackhammer : 1 x 1 Day @ RM 100.00 per day = RM 100.00

iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : C) Workmen i) Ganger : 1 x 1 Day @ RM 65.00 per day = RM 65.00 per day = RM 100.00

ii) General worker 5 x 1 Day @ RM 38.00 per day = RM RM 190.00 605.00

Productivity Per day : Workmen Cost Per No. :

RM

2 Nos 605.00 /

2 Raw cost per No.

= RM = RM = RM = RM RM

273.76 573.76 86.06 659.82 660.00

ADD :

P&O

15%

Rate Per No. Take

Kilometer Post

ROAD FURNITURES MAINTENANCE OF KILOMETER POSTS Replacement / Install of Kilometer Posts Item b Page 37 Provide everything necessary for dismantle, remove and dispose the damaged existing Kilometre and replace with new Kilometre post Type "B"
A) Material I) Precast r.c. Kilometre post (supply price / No.) B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 x 1 Day @ RM 150.00 per day = RM 150.00 = RM 200.00

ii) Jackhammer : 1 x 1 Day @ RM 100.00 per day = RM 100.00

iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : C) Workmen I) Ganger : 1 x 1 Day @ RM 65.00 per day = RM 65.00 per day = RM 100.00

ii) General worker 5 x 1 Day @ RM 38.00 per day = RM RM 190.00 605.00

Productivity Per day : Workmen Cost Per No. :

RM

3 Nos 605.00 /

3 Raw cost per No.

= RM = RM = RM = RM RM

182.78 382.78 57.42 440.20 440.00

ADD :

P&O

15%

Rate Per No. Take

Kilometer Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Remove, dismantle and dispose the damaged delineator post
A) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Item a Page 38

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00

B) Workmen I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM 152.00 382.00

Productivity Per day : Workmen Cost Per No. :

RM

55 Nos 382.00 /

55 Raw cost per No.

= RM = RM = RM RM Take RM

6.95 6.95 1.04 7.99 8.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Item b Page 38 Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor to replace the existing damaged or missing post
A) Material I) Flexible delineator post (supply price / No.) = RM 125.00

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 100.00

C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 467.00 x 1 Day @ RM 65.00 per day = RM 65.00

Productivity Per day : Workmen Cost Per No. :

RM

33 Nos 467.00 /

33 Raw cost per No.

= = = = Take

RM RM RM RM RM

14.15 139.15 20.87 160.02 160.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Replacement of Existing Delinator Posts Supply and install new reflector strips complete with bolts and nuts to replace the missing and damaged existing delinator strips
A) Material I) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set) =

Item c Page 38

RM

5.00

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : = RM 80.00

C) Workmen I) General worker 3 x 1 Day @ RM 38.00 per day Total = = RM RM 114.00 344.00

Productivity Per day : Workmen Cost Per No. :

RM

58 Nos 344.00 /

58 Raw cost per No.

= = = = Take

RM RM RM RM RM

5.96 10.96 1.64 12.61 12.60

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units

Item d Page 38

Remove, dismantle, disposed and install new timber post to replace the existing damaged or missing post
A) Material I) Delineator post (supply price / No) = RM 18.20

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00

C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 447.00 x 1 Day @ RM 65.00 per day = RM 65.00

Productivity Per day : Workmen Cost Per No. :

RM

51 Nos 447.00 /

51 Raw cost per No.

= = = = Take

RM RM RM RM RM

8.78 26.98 4.05 31.03 31.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Supply and install new delineator timber post
A) Material I) Delineator post (supply price / No)

Item e Page 38

= RM

18.20

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00

C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 447.00 x 1 Day @ RM 65.00 per day = RM 65.00

Productivity Per day : Workmen Cost Per No. :

RM

51 Nos 447.00 /

51 Raw cost per No.

= = = = Take

RM RM RM RM RM

8.78 26.98 4.05 31.03 31.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Item f Page 38 Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor soil anchor
A) Material I) Delineator post (supply price / No) = RM 125.00

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 100.00

C) Workmen I) Ganger : 1 I) General worker 4 x 1 Day @ RM 38.00 per day Total = = RM RM 152.00 467.00 x 1 Day @ RM 65.00 per day = RM 65.00

Productivity Per day : Workmen Cost Per No. :

RM

52 Nos 467.00 /

52 Raw cost per No.

= = = = Take

RM RM RM RM RM

8.93 133.93 20.09 154.02 154.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MAINTENANCE OF DELINATOR POSTS Installation of New Posts and Reflector Units Supply and install new delineator strips complete with bolts, nuts and fittings
A) Material I) G.I. Strip, c/w. clip, washer, bolt and nuts (supply price/Set)

Item g Page 38

= RM

5.00

B) Machinery I) Pick-up truck (3.0T) for carrying materials, workers and tools : 1 ii) x 1 Day @ RM 150.00 per day = RM 150.00

Miscellaneous items (Temporary traffic signs, cleaning tools and equipments) Allow sum : Per day = RM 80.00

C) Workmen I) Ganger : 1 I) General worker 3 x 1 Day @ RM 38.00 per day Total = = RM RM 114.00 409.00 x 1 Day @ RM 65.00 per day = RM 65.00

Productivity Per day : Workmen Cost Per No. :

RM

75 Nos 409.00 /

75 Raw cost per No.

= = = = Take

RM RM RM RM RM

5.45 10.45 1.57 12.02 12.00

ADD :

P&O

15%

Rate Per No.

Delineator Post

ROAD FURNITURES MISCELLANEOUS Hidro Cell Item a Page39 Supply and install Hidro Cell Cluster containing 37 tubes complete with safety belt, bolts, washers, nuts, support legs and hidro cells and all neceassary fittings
A) Material I) Hidro Cell ADD : P&O : Rate Per No. Take 15% = = RM = RM = RM RM 22,851.00 3,427.65 26,278.65 26,278.00

Misc

ROAD FURNITURES MISCELLANEOUS Hidro Cell Provide everything necessary for refilling fluid in the Hidro cell cluster
A) Machinery I) Water pump (3" dia.) 1 x ii) Miscellaneous Allow sum : iii) Pick-up truck c/w water tank 1 x 1 Day Productivity Per Day Machinery Cost Per No B) Workmen I) Ganger 1 ii) General worker 2 x 1 Day @ RM 38.00 per day =RM Total =RM 76.00 141.00 x 1 Day @ RM 65.00 per day =RM 65.00 : :

Item b Page39

1 Day

RM

100.00 per day = RM

100.00

RM

50.00

RM

150.00 per day = RM RM 1

150.00 300.00 RM 352.94

RM

1 No 300.00 /

Productivity Per day Workmen Cost Per No.

: :

RM

1 Nos 141.00 /

1 Raw cost per No.

= RM = RM = RM = RM Take RM

131.90 484.84 72.73 557.57 557.00

ADD :

P&O : Rate Per No.

15%

Misc