Based on the MRP run with respect to Project wbs element: 111.00001.

17 (MD51) requirement is generated for finished material and raw material. Stock and requirement List MD04:

Converting the Plan order to Production order:

As there are no ROW materials in Stock system not allowing to release the order .

Missing part list is shown below

Refresh the Stock and requirement list planed order will change to Production order

Production order 000000500032 is created with respect to planed order.

Production order assigned to WBS by default.

After materials are procured from PR stock is in Quality.

Do the result recording and user decision in QA32.

Now do the usage decision

Here we can see the quantity in quality and how much is accepted and sent to unrestricted.

Stock is shifted to unrestricted.

Follow the same process for all the other remaining material to move the stock from quality to unrestricted.

Now we see the stock in unrestricted.

Now as the raw material in stock we can issue the material to production order 500032.

Confirm the production order after completion of the activity CO11N.

After Confirmation Do the Goods receipt for finished material.

After the GR finished material is in quality

Result recording and usage decision has to give and move the stock from quality to project.

Result recording

Usage desicion

Now we can check the planed / Actual cost of production

Do the actual overhead calculation for the order 500032

After this overhead will be flow in actual cost.

After completion of the production do the TECO