You are on page 1of 1

M

cKenneys implemented a
broad-based energy-savings
initiative at an educational insti-
tution in suburban Georgia. The retrot focused
on four of the universitys largest buildings.
THE CHALLENGE
The McKenneys team upgraded lighting in
two gymnasiums, replaced 16 HVAC systems,
added four air-side economizers, and
designed and installed a Tridium

Niagara
AX

web-based control system to integrate with
an existing Siemens

control system. Much


of the work took place in less than a month,
resulting in a compressed schedule. Financing
options were provided but the university opted
for self-funding.
THE SOLUTION
To meet the timeline, McKenneys pre-planned
the entire project and prefabricated compo-
nents for the HVAC installation. Materials and
equipment were also staged on-site to save
time. The web-based controls included
McKenneys bdoc

Validate
TM
online energy
management application to measure energy
cost, consumption and carbon footprint.
THE RESULTS
The retrot, installation and controls implemen-
tation were completed on time and on budget.
Going forward, the university will be able to
track its energy savings through bdoc Validate.
Fast Track to Energy Savings
PROJECT NAME

Private University
PROJECT LOCATION

Marietta, Georgia
PROJECT TEAM

Owner: University

Engineer: McKenneys, Inc.
SPECIALIZATIONS
Design/Build
bdoc
Energy Management
Sheet Metal Shop Prefab
MARKETS

Education
The content of this document is not intended as an endorsement.
www.mckenneys.com
2014 McKenneys, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.
McKenneys, Inc. and the McKenneys, Inc. logo are registered trademarks of McKenneys, Inc. All other trademarks are the property of their respective owners.
404-622-5000
info@mckenneys.com
1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
704-357-1200
info@mckenneys.com
3601 Performance Road
Charlotte, North Carolina 28214

You might also like