Lot 12

Walkabout Defect List (19


th
August 2014)

Guard House

Guard House
Crack glass Silicon on wall & uneven wall paint at joint

Guard House

Guard House
Wall & slab joint not straight 90 Remove the unused material

Guard House

Bin Centre
Rough wall surface Touch-up paint at Batu Angin

Lot 12
Walkabout Defect List (19
th
August 2014)

Bin Centre

Production (ext)
Rough wall surface Rough wall surface & driveway slab joint

Production (overall)

Production (ext. rear)
Window panel out of alignment Provide slope cement mortar to cover the bolt

Production (ext. rear)

Fencing wall beside Lot 68
Wall plug for lightning arrester cable Uneven wall plaster
Lot 12
Walkabout Defect List (19
th
August 2014)

Driveway (right)

Air-cond ledge (ground floor)
Cut square box around gully trap & touch-up
cement mortar
Floor trap pipe need to bracket to wall

Landscape area

Lobby Canopy
Wall paint need to apply until earth level Protusion pipe sleeve for rain water flow

Lobby Canopy (front)

Tempered Glass Frame
Uneven plaster: control by wall painting Paint using same color with wall (grey)
Lot 12
Walkabout Defect List (19
th
August 2014)

Lobby

Lobby
1
st
step riser need to do straight Water seepage mark: apply white paint

Lobby Toilet

Lobby
Dented maica door frame Uneven wall plaster at fire alarm pipe

Staircase 2

1
st
Floor Office
Rough wall plaster around MS handrail Tile not fully cover the floor
Lot 12
Walkabout Defect List (19
th
August 2014)

1
st
Floor Office

1
st
Floor Office
Cement stain on alum frame Uneven paint at door frame

Lobby Staircase

Lobby Staircase
Excess concrete need to hack Wavy skim coat soffit staircase

External Building (front)


Drain-off pipe location not suitable