Overview of NTPC
NTPC Badarpur station has also bagged ISO 9001/ ISO 14001
certification.
Overview of NTPC
Second Outline
Level
Third Outline
Level
Fourth Outline
Level
Fifth
Outline
Level
NTPC Badarpur
Overview of BTPS
NTPC Badarpur
5th unit
Basic Principle
There are basically three main units of a thermal power plant:
1. Steam Generator or Boiler
2. Steam Turbine
3. Electric Generator
generate electricity.
Water Walls
Reheater
Superheater
Economizer
Air pre-heater
Pulvariser
Power= 210 MW
Number of stages= 12 in HP, 11 in IP and 8 in LP.
Type of governing: Nozzle governing
Vacuum Systems
Condensers: 2 for 210 MW at exhaust of LP Turbine.