SEA-TO-SKY HIGHWAY IMPROVEMENT PROJECT

PAVING
LOCATION:
SEGMENT #:

SECTION #:
Check for Changes
(Yes / No):

DWG # / Rev #:
Course type:

Thickness:

Latest IFC, RFI, FDC checked? Indicate.


Foreman
Check

DESCRIPTION

Engineer
Check

Compliance
(Y/N)

Date

Pre-paving
Asphalt cement and aggregates meet specifications
Plant calibrated
Correct and approved mix designs in place
Base Preperation
Base course prepared to line, grade, and compaction required. Signed off
by QA and survey.
Surface checked for segregation and fixed where necessary?
Tack coat applied and protected
Paving
Approved mix design used.
Existing joints saw-cut or appropriately prepared, attach checklists
Tack coat applied and protected
Material application rate checked/recorded
Survey check line and grade of final lift (survey crew)
Material Testing
Required hot-mix samples obtained (attach reports)
Plant testing in place (attach reports)
Required cores drilled from pavement
Visual check for surface segregation
Placement temperatures meet specifications.Indicate

ADDITIONAL ITEMS:
Weather Condition:

Underlying surface temperature:

Ambient temperature:
Joint layout and placing sequence reviewed

Superintendent:

Signature:

Date:

NOTES, COMMENTS, NCRS:

QC_DBFO_011

Rev. 0

July 2005