Laffan Refinery Company Limited 2

LR2 Refinery project


Mailing Address

Telephone
Fax

:
:

P.O. Box 22666


Doha Qatar
(+974) 4484-3677
(+974) 4484-3649

6 January 2015

[]
Subject:

Concrete Mix - Curing time

Originator: M.

Initials:

K. Belbouche/ M Ravichandran/ J Dhedin/ H Numan/ J Shukla/ A Ahmed

Initial Page

Laffan Refinery Company Limited 2


LR2 Refinery project
Mailing Address

Telephone
Fax

:
:

P.O. Box 22666


Doha Qatar
(+974) 4484-3677
(+974) 4484-3649

Date

: 6 January 2015

CHIYODA CTCI JOINT


VENTURE
89, Sec. 6 Zhongshan N. Rd.,
Taipei 111, Taiwan, R.O.C

Our Ref.

: []

Your Ref.

Other Reference

Attention:

Mr. Hikaru Morita


Project Manager - CCJV

Answer Rqrd. By

: N/A

Contract No.:

LTC/LRN/1834/12

Contract Title:

Engineering, Procurement, Supply, Construction, and Commissioning (EPSCC)


for LR2 Project

Subject:

Concrete Mix - Curing time

Address:

Dear Morita San


In response to CONTRACTOR request to COMPANY to review the concrete curing time to help in the
catch up schedule on Dec xx/xx, COMPANY reviewed the curing period developed by CONTRACTOR
in sec 9 in the project specs 256-82-00-CI-TS-NA-000009 Job Specification For Supply Concrete
Materials Mix And Construction based on sec 2.9.1 in ACI308R code. As per the code, when the
development of a given strength or durability is critical to the performance of the concrete, the minimum
duration of curing period should be established on the basis of tests of the required properties
performed with the concrete mixture.
COMPANY reviewed the durability test results received after 42 days and the compression strength test
results at 7 days, all results shows very good results for both durability and strength compare to the
project requirements. Accordingly, COMPANY suggest to reduce the curing time to minimum 7 days for
GGBS concrete or until 70% of the specified compressive strength is obtained, whichever is longer, that
would help the CONTRACTOR to catch up the schedule.
CONTRACTOR can adopt this immediately and respond to the CRS and revise the project specs
accordingly.

Ref:

Page 1 of 2

Laffan Refinery Company Limited 2


LR2 Refinery project

Yours Sincerely,

__________________
Eric Guillotin
Project Director LR2 Refinery project
Attachments: None