Earned Value Analysis PDF
Earned Value Analysis PDF
Presented by:
Shuja Ali
IPECC Consultants
Project Management, Training & Contract
Workforce
Todays Situation
Need for accurate and consistent status
information
Numerous complex (and interrelated)
projects
Shuja Ali:wbsproject@yahoo.com
% of
% of
% of
subjective, incomplete
draws false
conclusions
Shuja Ali:wbsproject@yahoo.com
Shuja Ali:wbsproject@yahoo.com
Shuja Ali:wbsproject@yahoo.com
Shuja Ali:wbsproject@yahoo.com
Shuja Ali:wbsproject@yahoo.com
10
?
Shuja Ali:wbsproject@yahoo.com
11
Shuja Ali:wbsproject@yahoo.com
12
Shuja Ali:wbsproject@yahoo.com
13
100000
80000
Projected
60000
Actual
40000
20000
0
Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Shuja Ali:wbsproject@yahoo.com
Dec-03
14
15
Obviously in small
bites.
Shuja Ali:wbsproject@yahoo.com
16
Shuja Ali:wbsproject@yahoo.com
17
Cook the
Food
Cook the
Sauce
Serve
Customers
(Others)
Shuja Ali:wbsproject@yahoo.com
18
Shuja Ali:wbsproject@yahoo.com
19
20
21
Shuja Ali:wbsproject@yahoo.com
22
Shuja Ali:wbsproject@yahoo.com
23
BCWS
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Shuja Ali:wbsproject@yahoo.com
24
Shuja Ali:wbsproject@yahoo.com
25
60000
BCWP
ACWP
49000
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Shuja Ali:wbsproject@yahoo.com
26
Shuja Ali:wbsproject@yahoo.com
27
55000
60000
BCWS
49000
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Shuja Ali:wbsproject@yahoo.com
28
BCWS
56000
60000
BCWP
55000
49000
40000
ACWP
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Shuja Ali:wbsproject@yahoo.com
29
Shuja Ali:wbsproject@yahoo.com
30
= BCWP-ACWP
$49,000
56,000
CV = - $7,000
Shuja Ali:wbsproject@yahoo.com
31
SPI<1
CPI<1
Shuja Ali:wbsproject@yahoo.com
32
Performance Metrics
SPI: BCWP/BCWS
49,000/55,000 = 0.891
CPI: BCWP/ACWP
49,000/56000 = 0.875
CSI: SPI x CPI
.891 x .875 = 0.780
Shuja Ali:wbsproject@yahoo.com
33
Making Projections
Once a project is 10% complete, the
overrun at completion will not be less
than the current overrun.
Once a project is 20% complete,
the CPI does not vary from its current
value by more
than 10%.
The CPI and SPI are statistically accurate
indicators of final cost results.
Source: Defense Acquisition University
Shuja Ali:wbsproject@yahoo.com
34
Making Projections
120000
103865
102000
90882
100000
80000
BCWS
Today
60000
BCWP
ACWP
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Shuja Ali:wbsproject@yahoo.com
35
Estimate to Complete
140000
120000
116,571
100000
102000
80000
BCWS
Today
BCWP
60000
ACWP
40000
20000
Ja
n04
M
ar
-0
4
Ja
n03
M
ar
-0
3
M
ay
-0
3
Ju
l-0
3
Se
p03
No
v03
Shuja Ali:wbsproject@yahoo.com
36
A New Criteria
Activities earn value as they are completed.
The value earned is the WBS budgeted cost of
the activity completed to date.
Shuja Ali:wbsproject@yahoo.com
37
Shuja Ali:wbsproject@yahoo.com
38
39
Shuja Ali:wbsproject@yahoo.com
40
Shuja Ali:wbsproject@yahoo.com
41
Shuja Ali:wbsproject@yahoo.com
42
Shuja Ali:wbsproject@yahoo.com
43
Shuja Ali:wbsproject@yahoo.com
44
Shuja Ali:wbsproject@yahoo.com
45
Requirements of Earned
Value
Proper WBS Design
Baseline Budget Control Accounts
Baseline Schedule
Work measurement by Control
Account
46
Shuja Ali:wbsproject@yahoo.com
47
Summary
EVA & EVMS will help reduce guesswork in:
Measuring performance
forecasting
Shuja Ali:wbsproject@yahoo.com
48
Shuja Ali:wbsproject@yahoo.com
49