BETONSKE KONSTRUKCIJE II

UNIVERZITET U SARAJEVU
GRAEVINSKI FAKULTET
ODSJEK ZA KONSTRUKCIJE
Predmet: Betonske konstrukcije 2

PROGRAM 1

BETONSKE KONSTRUKCIJE II
Sarajevo, juni 2013.

1. Proraun stropne ploe POZ 100


1.1. Optereenje na plou

Minimalna debljina ploe: hmin

husv= 15 cm

STALNO OPTEREENJE:
-

teina slojeva poda ............................................................1,50 kN/m 2


teina ploe .................................................0,15 x 25,00=3,75 kN/ m 2
teina plafona ....................................................................0,65 kN/ m 2
g= 5,90 kN/ m2

KORISNO OPTEREENJE:
RAUNSKO OPTEREENJE (ULS):
gd=1,35 x g=1,35 x 5,90=7,97 kN/ m2
pd=1,5 x p=1,5 x 6,40= 9,60 kN/ m2
qu= gu + pu =7,97+9,60= 17,57 kN/ m2

1.2. Proraun presjenih sila

Proraunski model:

p= 6,40 kN/ m 2

BETONSKE KONSTRUKCIJE II

1.2.1. Sheme optereenja


Shema 1

Shema 2 i 3

Shema 4

1.2.2. Momenti savijanja

BETONSKE KONSTRUKCIJE II

1.2.3. Poprene sile

1.2.4. Redukcija momenta nad osloncem


Pretpostavka je da je veza ploe i grede monolitna .
red

mEd,B= minmEd,B +

x c/2

c=30cm
red

mEd,B= -34,65+ 45,53x0,3/2 = -27,82 kNm/m mjerodavno h

1.3. Dimenzioniranje ploe


hploe=15 cm d1=2,0 cm
d= 13,0 cm
C 25/30 fcd =
B 500 S fyd=500/1,15=435 N/mm2
a) dimenzioniranje na savijanje
Popreni presjek:

N/mm2

BETONSKE KONSTRUKCIJE II

PRESJE
K

MOMENA
T
MEd
(kNm/m)

d
(cm)

Eds

POLJE 1

28,98

13,0

0,121

ARMATURA

pot

aa

(cm /m)

0,1285

5,44

OSLONAC
B

-34,65

13,0

0,145

0,1638

6,14

POLJE 2

16,62

13,0

0,070

0,0728

3,08

POLJE 2

-5,05

13,0

0,021

0,0203

0,86

Razdjelna armatura:
a = 0,20x aa,x= 0,20 x 5,44 =1,08 cm2/m

min a,r

USVOJENO: 6/20cm ; B 500S


stv

as,r = 1,41 cm2/m

Armatura u gornjoj zoni iznad srednjeg oslonca u pravcu y:


a = aa,x,polja = 5,44 cm2/m , polje 1

min a,y

min a,y

= aa,x,polja = 3,08 cm2/m , polje 2

USVOJENO: 10/12,5cm; B 500S


stv

aa,y = 7,85 cm2/m

ODABRAN
O
10/12,5c
m
10/25cm

8/25cm
+
6/25cm

8/12,5cm
10/25cm
iz polja 1

a
/

stv a
2
(cm m)

6,28

6,28

4,02
3,14

BETONSKE KONSTRUKCIJE II

b) dimenzioniranje na poprene sile


Za odnos b/h=100/15=6,67 > 5,0 i h=15 cm < 20 cm (ploa se moe izvesti bez
smiue armature)
Potrebno je ispitati je li ispunjen uslov da je
Redukcija poprene sile:

VRd,ct
=1,0

cd =0;

=25 N/mm2 ; bw =1,0 m; d=0,13m

VRd,ct
VEd = 45,53 kN/m

= 45,53 kN/m< VRd,ct

BETONSKE KONSTRUKCIJE II
Plou nije potrebno armirati smiuom armaturom.

1.4. Raspored armature


Veliina pomjeranja: al = d = 13 cm usvojeno al = 15 cm
Sidrenje armature
C 25/30

a) osnovne duine sidrenja

- za 10 mm

- za 8 mm

- za 6 mm

b) sidrenje armature na krajnjim osloncima (indirektno oslanjanje)

= 6,25 cm2/m (sva armatura iz polja se sidri)

l 0,3 x

min b

= 12 cm
10 x ds= 10 cm

USVOJENO: lb= 15 cm

BETONSKE KONSTRUKCIJE II

c) sidrenje armature na srednjim osloncima (donja zona)


- za ds=10 mm: lb> 6 x ds = 6 x 1,0 = 6 cm
USVOJENO: lb= 10 cm
- za ds=8 mm:

lb> 6 x ds = 6 x 0,8 = 4,8 cm


USVOJENO: lb= 10 cm

- za ds=6 mm:

lb> 6 x ds = 6 x 0,6 = 3,6 cm


USVOJENO: lb= 10 cm

d) sidrenje armature u polju (gornja zona)


- za ds=6 mm:

=24 cm
USVOJENO: l b= 25 cm

- za ds=8 mm:

=32 cm
USVOJENO: lb= 35 cm

- za ds=10 mm:

=40 cm
USVOJENO: lb= 40cm

e) sidrenje armature u gornjoj zoni polja 2

= 1,13 cm2/m (sva armatura iz polja se sidri)

l 0,3 x

min b

= 13,92 cm
10 x ds= 8 cm

USVOJENO: lb= 40 cm

BETONSKE KONSTRUKCIJE II

1.5. Dimenzioniranje ploe za sluaj armiranja zavarenim armaturnim mreama


N/mm2

C 25/30 fcd =
B 500 M fyd=500/1,15=435 N/mm2

MOMENAT
MEd
(kNm/m)

d
(cm)

POLJE 1

28,98

13,0

OSLONAC
B

-34,65

13,0

POLJE 2

16,62

13,0

PRESJEK

POLJE 2

-5,05

13,0

ARMATURA
Eds

0,12
1
0,14
5
0,07
0

0,128
5
0,163
8
0,072
8

0,02
1

0,020
3

potaa
(cm2/m)

USVOJENO

stv aa
(cm2/m)

5,44

R335+R257

5,92

6,14

2x R 335

6,70

3,08

R 335

3,35

0,86

R 335
Prekopljena
mree od
oslonca B

3,35

Armatura u gornjoj zoni iznad oslonca u pravcu y


aa,y= aa,x,polja= 5,44 cm2/m
USVOJENO: R335+R257 , aa,y=5,92 cm2/m
1.5.1. Sidrenje armature
a) sidrenje mrea na krajnjim osloncima

BETONSKE KONSTRUKCIJE II
= 3,35 cm2/m (vodimo do kraja R 335)

l 0,3 x

min b

= 6,73 cm
10 x ds= 8 cm

USVOJENO: lb= 10 cm

b) sidrenje mrea u polju


Za mree u gornjoj zoni usvojeno: lb=32 cm
Za mree u donjoj zoni usvojeno:

lb=32 cm.

Usvojene duine preklopa:


Za mree u gornjoj zoni: lp=29 cm
Za mree u donjoj zoni: lp=29 cm

2. Proraun grede POS 102 (103)


Minimalna debljina grede: hmin
2.1. Analiza optereenja grede
Optereenje od ploe POS 100:
a) stalno optereenje

gd=qd=7,97kN/m gd / qd=1,0

husv= 70 cm

BETONSKE KONSTRUKCIJE II

b) korisno optereenje pd=qd=8,64 kN/m gd / qd=0

c) vlastita teina grede (h=70cm)


ggrede=bw x (h- hpl) x 25 x 1,35= 0,3 x 0,55 x 25 x 1,35= 5,57 kN/m

STALNO OPTEREENJE GREDE: ........................ gd = 37,22 + 5,57= 42,80 kN/m


KORISNO OPTEREENJE GREDE: ....................... pd = 48,96 kN/m
UKUPNO OPTEREENJE GREDE: ........................ qd = gd + pd = 91,76 kN/m

Potrebna statika visina (d):

BETONSKE KONSTRUKCIJE II

; sy
-relativna visina pritisnute zone:

-koeficijent punoe:

-koeficijent poloaja sile pritiska u betonu:

-relativni krak unutranjih sila:


=
Iz uslova:
MEds MRds =
1010,24 0,8095
1010,24

BETONSKE KONSTRUKCIJE II
h = potd + d1 = 80 + 5 = 85 cm

pot

USVOJENO: h=85 cm
Stvarna vlastita teina grede (h=85cm)
ggrede=bw x (h- hpl) x 25 x 1,35= 0,3 x 0,70 x 25 x 1,35= 7,10 kN/m

STALNO OPTEREENJE GREDE: ........................ gd = 37,22 + 7,10= 44,32 kN/m


KORISNO OPTEREENJE GREDE: ....................... pd = 48,96 kN/m
UKUPNO OPTEREENJE GREDE: ........................ qd = gd + pd = 93,28 kN/m

2.2. Proraun presjenih sila

Vrijede iste sheme optereenja kao i kod prorauna ploe.

Proraunski model:

2.2.1. Momenti savijanja

BETONSKE KONSTRUKCIJE II

2.2.2. Poprene sile

2.3. Dimenzioniranje grede


a) sudjelujua irina grede
beff,i=0,2
bi
beff= beff,i + bw

BETONSKE KONSTRUKCIJE II
- krajnje polje: beff,i=0,2
1,97 m
beff= beff,i + bw = 2
- srednje polje: beff,i=0,2
1,97 m
beff= beff,i + bw = 2

USVOJENO: bs=250 cm

2.3.1. Dimenzioniranje na savijanje

Polje 1 i 3:
max

MEd,1= 854.95 kNm

pretp

d1=5 cm

beff = 250 cm; bw = 30 cm

Iz tabela: =0,0410; =0,066; =0,976

BETONSKE KONSTRUKCIJE II
(presjek je pravougaoni)

USVOJENO: 9 20 ; B 500 S
2
2
stv As= 28,3 cm pot As=26,71 cm
Polje 2 (donja zona):
max

MEd,2= 479,71 kNm

pretp

d1=5 cm

beff = 250 cm; bw = 30 cm

Iz tabela: =0,0213; =0,0451


(presjek je pravougaoni)

USVOJENO: 520 ; B 500 S


2
2
stv As= 15,70 cm pot As=13,87 cm

Polje 2 (gornja zona):


min

MEd,2= -145,43 kNm

pretp

d1=5 cm

BETONSKE KONSTRUKCIJE II
beff = 250 cm; bw = 30 cm

Iz tabela: =0,0547

USVOJENO: 2 20 ; B 500 S
2
2
stv As= 6,28 cm pot As=4,30 cm

Oslonac B i C:
max

MEd,1= -1023,85 kNm

Redukcija oslonakog momenta:


Pretpostavka da veza grede i oslonakog elementa nije monolitna.
red

MEd,B = min Med,b + RB,d x cosl / 8 = -1023,85 + 1080.02 x 0,30/8= -983.35 kNm

pretp

d1=5 cm

beff = 250 cm; bw = 30 cm

Iz tabela: =0,4768

USVOJENO: 9 20 (28,26 cm2) + 2


stv

As= 36,30 cm2 > pot As=36,17 cm2

; B 500 S

BETONSKE KONSTRUKCIJE II
2.3.2. Dimenzioniranje na poprene sile

Oslonac A:
VEd,A = 399,60 kN
-redukcija poprene sile, za dio optereenja koji ide u oslonac:
VEd,Amj.=399,60 93,28 (0,10+0,80) = 315,65 kN
-poloaj nulte take:
x0= VEd,A/qd = 399,60/93,28 = 4,40 m
-Proraun poprene armature:
Granine vrijednosti nagiba pritisnutih dijagonala:

VRd,c

Otpornost betonskih pritisnutih dijagonala(=90 :

BETONSKE KONSTRUKCIJE II

Potrebna poprena armatura:

pot

-minimalna poprena armatura: (Za C 25/30 w=0,83 )

min

USVOJENO:
Na dijelu nosaa duine 210 cm od ruba oslonca, usvojeno:
DVOSJENE VILICE: 6/12,5 cm B 500S
stv

asw =4,40 cm2/m > pot asw =4,30 cm2/m

Na preostalom dijelu nosaa duine 220 cm, usvojeno:


DVOSJENE VILICE: 6/20 cm B 500S
stv

asw =2,83 cm2/m > pot asw =2,49 cm2/m

BETONSKE KONSTRUKCIJE II

Oslonac B (lijevo):
VlEd,B = 571,62 kN <
-redukcija poprene sile, za dio optereenja koji ide u oslonac:
VEd,Bmj,l.=571,61 93,28 (0,15+0,80) = 482,0 kN
-poloaj nulte take:
x0= VEd,B/qd = 571,61/93,28 = 6,12 m
-Proraun poprene armature:

pot

(usvojit emo kombinaciju vilica i kosih ipki)

USVOJENE DVOSJENE VILICE: 6/20 cm B 500S


stv

asw =2,83 cm2/m > pot asw =2,49 cm2/m

Potrebna povrina koso povijenih ipki (=45):

BETONSKE KONSTRUKCIJE II

USVOJENO: 3 20 B 500S
stv

As,K. =9,42 cm2 > pot As,K. =8,46 cm2

Oslonac B (desno):
VdEd,B = 508,40 kN <
-redukcija poprene sile, za dio optereenja koji ide u oslonac:
VEd,Bmj,d.=508,40 93,28 (0,15+0,80) = 419,78 kN
-poloaj nulte take:
x0= VEd,Bd/qd = 508,40/93,28 = 5,47 m
-Proraun poprene armature:

pot

(usvojit emo kombinaciju vilica i kosih ipki)

BETONSKE KONSTRUKCIJE II

USVOJENE DVOSJENE VILICE: 6/20 cm B 500S


stv

asw =2,83 cm2/m > pot asw =2,49 cm2/m

Potrebna povrina koso povijenih ipki (=45):

USVOJENO: 2 20 B 500S
stv

As,K. =6,28 cm2 > pot As,K. =4,45 cm2

2.4. Raspored armature


2.4.1. Veliina pomjeranja

2.4.2. Sidrenje armature


lIb=40 ds ; lIIb=58 ds

BETONSKE KONSTRUKCIJE II

a) osnovne mjere duine sidrenja


- za ds =16 mm lIb = 40x1,6= 64,0 cm ; lIIb =58 x 1,6= 92,8 cm
- za ds=20 mm lIb = 40x2,0= 80,0 cm ; lIIb =58 x 2,0= 116 cm
b) sidrenje armature na krajnjim osloncima (direktno oslanjanje)

= 24,12 cm2 (12 16)

min b

0,3 x

= 12,80 cm
10 x ds= 10,67 cm

USVOJENO: lb= 20

cm

c) sidrenje armature na srednjem osloncu u donjoj zoni:


Iz prvog polja vodimo 4 16
Iz drugog polja vodimo 2 16
lb 6 ds =9,6 cm

USVOJENO: l b= 15 cm

d) sidrenje armature iznad srednjeg oslonca u gornjoj zoni


Za 16:

lIb = 58 ds= 92,80 cm


USVOJENO: lb= 95 cm

Za 14:

lIIb = 58 ds= 116 cm


USVOJENO: lb=120 cm

BETONSKE KONSTRUKCIJE II

3. Proraun stuba
- dimenzije stuba: b/b=30/30 cm
- duina stuba: lcol=335 cm
Materijali:
-

Beton: C 25/30
Armatura: B 500 S

3.1 Optereenje:
NEd=1080,02 kN (imamo samo normalnu silu)
3.2 Duina izvijanja i vitkost stuba:

- vitkost stuba:

- granina vitkost stuba:


25

25

BETONSKE KONSTRUKCIJE II

3.3 Ukupni ekscentricitet:

Usvojeno:

BETONSKE KONSTRUKCIJE II

pretp. d1=3 cm d=b- d1=30-3=27 cm

3.4 Proraunske sile po teoriji II reda:


NEd=1080,02 kN
MEd=

kNm

- Dimenzioniranje presjeka:

Iz tabela za:

Usvojit emo minimalnu armaturu:

- minimalni prenik podune armature


USVOJENO: 4 12 B 500S

min

dsl12 mm

BETONSKE KONSTRUKCIJE II
stv

Asl =4,52 cm2 > pot Asl =3,67 cm2

Poprena armatura:
- minimalna prenik poprene armature:

min

dsq 6 mm
0,25 max dsl = 0,25 12 = 3 mm

- najvei razmak poprene armature: sw 12 min dsl = 144 mm


hmin = 300 mm
300 mm
USVOJENE VILICE:
8/12,5 ; 7,5 cm

B 500S

4. Proraun temelja:
Materijali:
-

Beton: C 25/30
Armatura: B 500 S

Optereenje:
g=5,90 kN/ m2
p=6,40 kN/ m2
qu= gu + pu =12,30 kN/ m2
-optereenje sa ploe na gredu:

ggrede=bw x (h- hpl) x 25 x 1,35= 0,3 x 0,70 x 25 = 5,25 kN/m


gu=27,55 + 5,25=32,80 kN/m

BETONSKE KONSTRUKCIJE II
pu=32,64 kN/m
qu= 32,80 + 32,64 = 65,44 kN/m

Nk = 756,52
NEd=1080,02 kN ULS
Doputeni napon u tlu: dop tla =260 kN/m2
4.1 Proraun dimenzija temelja:
- pretpostavljene dimenzije temelja samca: b x/by/h = 1,80/1,80/0,60 m

USVOJENO: bx/by/h = 1,80/1,80/0,60 m

4.2 Presjene sile (Gtemelja se zanemaruje):


- redukcija momenta ispod stuba (pretpostavlja se monolitna veza stuba i temelja):

BETONSKE KONSTRUKCIJE II

4.3 Dimenzioniranje na savijanje:


- zatitni sloj: cv =5,0 cm
- statika visina: (pretp. 10)

Usvojeno:
Odreivanje potrebne armature (finija raspodjela):
Najnapregnutija traka 4:

BETONSKE KONSTRUKCIJE II

Iz tabela

Ukupna armatura: As =1,37/0,19 = 7,23 cm2


4.4 Raspored armature (po gruboj emi):
- Traka 1 i 2:
pot

As = 0,167 7,23 = 1,21 cm2 (2 10) ili

USVOJENO: 10/25 cm B 500S


stv

as = 3,14 cm2/m >

pot

as =2,68 cm2/m

- Traka 3 i 4:
pot

As = 0,33 7,23 = 2,38 cm2 (4 10) ili

USVOJENO: 10/12,5 cm B 500S


stv

as = 6,28 cm2/m >

pot

as =5,30 cm2/m