Weekly Meeting Minutes of Meeting


__________________________________________________________________________
Ref No

: QCON/C-002/802/IWM/01

Subject

: RFS-128 - LNG ROAD TANKER FACILITY PROJECT TO SUPPLY LNG


TO RLESC (RGCP-475)

QCON Job no

: C02-802

Date

: April 30, 2015

Time

: 01:00PM ~ 02:30PM

Location

: Qcon Head Office-C ring Road

Participants

:
QCON

MR.WAEL EL BANNA PROJECT COORDINATOR


MR.ESMAIL DADAN PROJECT MANAGER
MR.JAZHEEL YOOSUFF-PLANNING ENGR
MR.FHAKRUDDIN MOHAMMAD-SR QC ENGR
MR.FERDINAND MARK SAFETY LEAD

SN

Distribution

: All Attendees

Prepared by

: Jazheel Mohamed Yoosuff

Description

Action by

Due

Mr. Mark

3 May
Conformed

Medical and RG Training


1

Conform the medical clinic center and Medical check list


from CAEL
(As discussed with civil department manager, Qcon prefer
to go with Premium care)
As conformed by Mr. Mark
1. Contractors are free to contact any SCH approved
medical center for fitness certificate.
2. Specific test for drivers.
3. Regardless of the location, if you have work/contract
with RG, need to undergo for defensive driving training.
1.

1/2

SN
2
3

Description

Action by

Due

Inform the approved medical center to sub-contractors to


get medical test/clearance to apply RG Induction training
and Defensive driving training.
Provide Qcon Manpower list to Mr. humlal pande/Kulchandra
Poudel to arrange medical test/clearance to apply RG
induction, Confined space, Defensive driving training

Mr.Wael/
Mr.Esmail

3 May

Mr.Esmail

5 May

Site Facilities and Food Arrangements


4

5.

Arrangement of Site Facilities (Air conditioned cabin,


Rest shelters, Drinking water shelter etc...) on site
immediately after receiving ECPW.
Mr.Esmail will list out the above requirements and
manpower list to discuss with Civil department manager to
finalize.
Request Administration manager to arrange lunch for Qcon
manpower with Amwaj Catering.
After list out the manpower list, Mr.Esmail will provide
the list to Mr. Kulchandra Poudel to get approval prior
to request Amwaj.

Mr.Esmail

4 May
Kulchandra
Poudel/
Mr.Esmail

5 May

Mr.Esmail

6 may

Mr. Mark

3-May

3 may

PPE
6.

Immediately after short out the manpower list,


procurement of Nomex coverall, toxic clip, water bottles,
safety shoes etc... for Qcon manpower
Sub-contractors will do their own arrangements

Dumping Permit
7.

Mr. Mark will contact Mr. Willy Rabe (Qcon environmental


engineer) to arrange the dumping permit

Precast works
8

Collect the Gate shop drawing from Mr.Wael and Submit for
approval

Mr.Wael/
Mr.Esmail

Manpower Mobilization for Concrete precast works

Mr.Esmail

2/2