Dear Sir,

Height test required for the following workmen at  TG#3(IEL-CPP#1)   of M/s Thermax
Babcock & Wilcox  today.
Kindly Allow for height Test.
 
Regards

Dear Sh.Koom Singh,

As per trailing mail review & approve CV.

आभारी | Regards

Kind attention- RCM M/s PMIL


 
I would like to bring you kind notice M/s PMIL has not deployed a planning engineer at
site since April 2021. Site work is hampered due to non deployment of planning
engineer and same is discussed with you several time  . Today your quality engineer and
HR department person are also not available at site without any intimation . This type of
irregularity and casual work approach is not at all acceptable . Any delay in the project
due to non deployment of manpower shall completely be in account of PMIL, as per GCC
of contract.
 
Due to non deployment of planning Engineer since April 2021 even after several
reminder from PDIL  , a  Financial penalty of Rs.-15000/- is imposed on M/s PMIL as per
SCC Annexure A-XII
 
Regards,
                                                  

Dear Sir,

Attached please find the CV of Mr. RAKESH PRADHAN for the post of Lead Safety of
Composite Mechanical Works at CMU.

Request you to please accord your approval so as to enable us to deploy him to Site at


earliest.

Thanking you.

With Regards.

A.K.Chouny
RCM
POWER MAX INDIA PVT. LTD

Dear All,
It is thereby informed that any erection and shifting of equipments/machineries above
5MT should be supported with proper erection plan with a sketch.
 
This is as instructed by IOCL F&S.

 Non Submission of above document shell lead to imposition of financial penalty.

भवदीया /Regards,

Attention : RCM PMIL


Parking the vehicle only in the designated area inline systematically otherwise it will be
penalized as per SSC norms.
--
Regards,

Attention : All RCM


You are advised to Submit  Covid-19 Emergency Response Plan(Covid ERP) for
CMU Project (As per SOP) as earliest as Possible.
Regard

Attention : RCM-PMIL 
Unsafe activities were stopped at site & advised to resume after necessary correction.
Kindly take necessary action & arrange to liquidate all observations given below & also
revert the one to one compliances of below observations.
Also pl note that a penalty of Rs 1500.00 has  been imposed in course of non compliance
of safety lapses at site. 

This was informed to your site supervisors various times regarding violation of safety
(Electrical safety)in various instances ,where as we as we  understood that you have to
abide by safety rules for safe work at site .
Hope with this you will understand the situation and will maintain site work  with
safety and healthy atmosphere along with progress.

Regards,

Dear All, 
You all are advised for strictly maintaining Guide lines of COVID-19 for all site
staff/Engineers  Deputed at CMU site & also  all are advised to maintain Home
quarantine schedule as per rule in case of outstation leave . Hope all will understand &
co-operate. Home quarantine for 14 days without test & for 7 days with test report from
Covid hospital at panipat.

With Regards

Dear Sir,

The following observations and safety lapses were noted during tommorow evening
visit at CMU site. You are advised to take note of the same and arrange to adhare the
safety norms as per rule, to carry out safe work at CMU site.

1. You were found to work at height using scaffolding without any permit for using the
same. Further, no safety tags were found to be used on the scaffolding. (pics. attached)
2. You were found to carry out welding works without double body earthing, as per
safety standard. (pics. attached)

Kindly arrange to take note of the above observations & rectify the same, at the
earliest. Also, you are advised not to initiate any work at site without proper
permit, such lapses shall attract penalty near future.

भवदीया /Regards,

Dear Sir,

This is to bring it to your kind notice to make proper arrangements for Water Line thru'
running hose pipe from existing fire water line to your fabrication yard. However, till
date you have failed to make the necessary arrangement. You are hereby again
requested to take immediate measures for the same within a week, and adhate the
safety norms.

भवदीया /Regards

Dear Sirs,

In view of the upcoming monsoon & waterlogging, you all are requested to kindly make
proper approach till your fabrication yard/ site office at CMU site, in order to avoid
occurrence of any incident at site.

भवदीया /Regards,

Dear Sir,
Please find herewith attached Harihar Behra CV along with transmittal for the post of
Lead safety officer. So we request you to please review the attached resume and kindly
accord your approval in this regard.
As per your approval, we will deploy him immediately at site.
Please do the needful in this regard.

Regards

Dear Sir,
Checked and  found ok.
original document to be submit.

भवदीया /Regards,

Dear Sir,

We like to inform you at the time of site visit your blasting shed is not properly covered
from the side portion , hose pipe  & curtain is not suitable for blasting. So we have
advised you to comply with all points for blasting activity before you start any site
activity.

Further, kindly arrange to submit the calibration certificate of  pressure gauge & TPI of
blasting hopper, hose pipe.

भवदीया /Regards,

Attention M/s RCM (PMIL)

This is with reference to the above subject; we want to inform you that, in spite of
several reminders verbally you failed to submit HSE report timely to us and next time if
report will not submit timely we will definitely impose penalty as per contract for HSE
Report.

This is for your kind information and necessary action please.

Note-- Immediately submit HSE Report by tomorrow otherwise impose penalty as per
contract.

भवदीया /Regards

Attention : RCM VRC & RCM PMIL & RCM JSM


 
Monthly Safety review meeting on a fortnightly basis has been planned on 17.08.2020 &
31.08.2020 for the month of Aug-20 respectively. The Time slots for different Contracts
are as below;
 
1. M/s VRC - 10:30 AM
2. M/s PMIL - 11:00 AM
3. M/s JSM - 11:15 AM

भवदीया /Regards,

Dear Sir,
 
Please find enclosed herewith the MOM for Safety Review Meeting held today i.e.
17/08/20 at 11:20 AM at CMU site. You are advised to take note of the
observations and take action immediately.

भवदीया /Regards,

Dear Sir,
 
Your Tractor No. HR 06 AH 6851 was found to trochen your Temp No. GJ 06 AX 1944
using a normal rope of 8 mm at CMU site. Further, on asking him to stop the vehicle,
both were trying to escape from the site. This is not at all permissible at site. We have
seized the gate pass and entry permit of both the vehicles at CMU site, till further notice.

भवदीया /Regards,

REMINDER
all are once again advised to comply the Standardization Safety Helmet Colour Code at
CMU site by latest by 31.08.2020. 

as per instructions from IOCL's F&S.  

भवदीया /Regards,

Dear All,
 
Safety inspection of CMU Project area carried out today & safety non compliances
recorded from site are given below. Kindly take necessary action from your end &
arrange to liquidate all observations on priority.

  Please share the liquidation status against each observation given below.  

Dear all,

This is to inform you that, you all are advised to arrange  Fire Retardant Suit (IFR) for
Hot Work and Safety Dangri (Boiler Suit) for all other workmen by  31st  October, as
instructed by IOCL.

It is also informed that, no work permit shall be issued from 1st November onward if
workers are found without Fire Retardant Suit/ safety Dangri (Boiler Suit), at CMU site.
भवदीया /Regard

You have failed to submit the Fire And Safety compliance on time bcoz of which we can
not forward and close the same, which is scheduled to be submitted within 24 Hrs. after
observation.

You are strictly advised to arrange to submit the same by today itself and arrange to
deputy competent person to take care of Safety issues within stipulated time.

Repetition of such casual approach shall result to imposition of financial penalty, near
future.

भवदीया /Regards,

Dear Sir,

Pl find herewith enclosed the approved CV of  Safety Officer " Mr Intekhab Alam " of M/s
PMIL for Mechinical Works.

This is for your kind information.

भवदीया /Regards,

Dear Sir,

This is in continuation to the trailing email against non submission of HSE Report.
Kindly find enclosed herewith the penalty letter.

You are again advised to arrange to submit the HSE Report in order to avoid further
penalty. 

Also, kindly note that your Lead Safety Office is absent from site since more than 15
days. Kindly arrange to deploy the same at the earliest, for ensuring issuance of work
permits at site and avoid further penalty.

  

भवदीया /Regards,

Dear Sir,
Please Review attached JSA document for Equipment Erection of CMU Project.
 

भवदीया /Regards,
Dear Sir,
You are found working without valid Hot work permit hence you are advice stop Hot job
activity.
Also arrange running hose pipe and SFU (Switch Fuse Unit) at site for issuing the above
permit.

भवदीया /Regards,

Dear Sir,
A Financial penalty of Rs.-3000/- is imposed on you for non completion of grass cutting
activity at CMU site.
It was already advised by CGM Sir,for grass cutting to all contractors for their respective
area.
You are again advised to completed the same on priority.
In this context, a financial penalty of Rs. 3,000/- is being imposed on you, as per clause
No.-3.1.13(Point No.-26) for the above non-compliance of safety norms. 

भवदीया /Regards,

Kind attention RCM-M/s PMIL.

This is to bring your kind notice that morning dtd-25.02.21 as per safety siren,it is
observed that neither labour nor any staff from PMIL has been gathered at the assembly
point which is totally unacceptable and violation of safety norms. Please clarify for the
above matter through revert mail by today.

Considered it, as warning & against the safety norms of the contracts.

Further if such violations of safety are found or repeated at the site suitable action to be
taken accorded as per the contracts.

Best Regards,

Dear Sir,
 
This is in reference to the attached file, we would like to request you to kindly allow
for Online renewal gate pass of A Vehicle(HR 02 AK 9149-HYDR) for PNC gate and
battery area.

Thanks & Regards

Dear Sir,

Pl take needful action for renewal gate pass  HR 02 AK 9149-HYDR) for PNC gate and
battery area.

आभारी | Regard

Dear Sir,
It has been reported by our Security personnel that your tractor trailer was parked on
the main road adjacent to CMU Warehouse for the last 2 days. Kindly arrange to remove
the trailer at the earliest, as this is blocking the road and restricting free movement of
vehicles.
However, today on intimation, you have started loading pipes. Plz. don’t make it a
practice, for parking the trailer on the main road.
--
Regards,

Dear sir,
 
I would like to inform you that required material is available in CMU warehouse for
unit-11 as per received drawings; you are advised to lift the material from CMU
warehouse and start fabrication work for unit -11.
 
This is for your information and necessary action please.
 
Regards,

Dear Sir,

I would like to say that we are working on the OSBL site (Front of PP Unit), We are
facing a difficult situation due to production material kept in the work site. so please
contact the production department and remove all material for safe work. and the
second point is that grasses grow near all the working areas under hazardous working
condition, therefore the area must be clear and clean.

we are requested to kindly advice us as soon as possible.


Thanks & Regards

Intekhab Alam

Dear All,

Weekly Review Meeting will be scheduled as below :

DTH: 0300 PM – 0320 PM
 
PMIL: 0320 PM – 0340 PM
 
JSM : 0340 PM – 0400 PM

आभारी | Regards

Reminder - II

Kind Attention - RCM M/s PMIL,

We are regularly asked to deploy the Planning Engineer so that work can be run
smoothly but till now it has not deployed at site.

Further for the store work, the store officer is not available at site. Due to it site work
was also hampered .

You are advised to deploy both persons at the earliest.


आभारी | Regards

Dear Sir,

This is information to you today's morning visit at your site. 


It has been noticed that 01 Nos. of your welder were found engaged in Hot work
without IFR Suit.

Note-As you were interested yesterday morning to use IFR suit while hot job still your
work found without IFR suit for grainding work.

Further, a financial penalty of Rs. 10,000/- is imposed on you, as per clause No.-


3.1.13(Point No.-26) for the above non-compliance of safety norms.

Thanks
Dear Sir,
Today it's found that there is no IFR suit at site as the previous contractor has left the
job and new contractor has not issued any IFR suit. In this concern we told to PMiL RCM
also. 

RCM please look the matter on priority and stop the work till new IFR suit to be
provided the workers for the job.Treat it as warning.

Thanks

Dear Sir,
Please find attached herewith this mail of compliance report of plant safety inspection
report dated on-04.03.2021 has been implemented at site for the  flagman with Jcb.

 Picture  is  attached for your reference.

 With Regards,

Dear Sir,

This is information to you today's morning visit at your site. 


It has been noticed that 01 Nos. of your grainder men were found engaged in Hot work
without IFR Suit.

Note-As you were interested today morning to use IFR suit while hot job still your work
found without IFR suit for grainding work.

Further, a financial penalty of Rs. 5,000/- is imposed on you, as per clause No.-


3.1.13(Point No.-20) for the above non-compliance of safety norms.

भवदीया /Regards,

Dr. Sahab,
Please refer trailing mail & confirm your availability for Vertigo test of enclosed
workers from M/s PMIL workers.

Dear sir,
The electrical hazard is very high due to the Rainy weather, so the entire electrical
systems should be in good condition.

Thanks & Regards

Dear Sir 

We are appreciate you to for your kind information we will do our best for your
satisfaction

Thanking you

Kind Attention - RCM M/s PMIL,

We are regularly asked to deploy the Planning Engineer so that work can be run
smoothly but till now it has not deployed at site.

Further for the store work, the store officer is not available at site. Due to it site work
was also hampered .

You are advised to deploy both persons at the earliest.

आभारी | Regards

Dear All,

As earlier communicated,Monthly Review Meeting (July-21) has  been


scheduled today (08.07.2021)as per  below schedule :
·         VRC   -  14:00 to 14:30 Hrs
·         PMIL  -  14:30 to 15:00 Hrs

Thanks

Dear Sir,

Yesterday we were issued permits necessary for OSBL but it is in the name of M/s.
Shilpi Engineering.

So, request you to please issue fresh permits in the name of Powermax as we are fully
prepared to start work at OSBL today itself.

Thanking you.
Regards.

Kind Attention - RCM M/s PMIL,

This is for your kind information Planning Engineer CV was approved as per the trailing
mail but till date Planning Engineer has not been deployed at site.

Pls look into this matter as a priority.

आभारी | Regards

Dear Sir,

We would like to inform you to, our driver Mr. Diwan Singh will goes to leave from 12-
07-2021 to 31-07-2021 to meet his family.

Herewith, in the absence of Mr. Diwan Singh we need a new driver for temporary basis.

You are requested to kindly accord your approval & advice us as soon as possible.

Thanks & Regards,

Sir,

Please advise all contractors to take vaccine at Panipat Refinery Hospital as per
eligibility. Please refer trailing mail.

Thanks & Regards

Dear Sir,

As already communicated several times, you are once again advised to ensure to submit
the following HSE documents on monthly / daily basis. 

Further, would like to remind you that, you have failed to submit the HSE Report for the
month of November’20 till date, last date of submission of the same is by today evening ,
failing which we will be left with no option other than imposing financial penalty on
you, as per contractual terms & conditions.

You are again reminded to submit the following reports on periodical basis, with out
repeated reminders or mails, as per standard procedure.

S.N. DOCUMENT NAME FREQUENCY


1 SAFETY WALK THROUGH REPORT MONTHLY
2 GAS CUTTING CHECK LIST MONTHLY
3 DAILY CHECK LIST REPORT DAILY
4 HOUSEKEEPING REPORT MONTHLY
5 INSPECTION OF TEMPORARY ELECTRICAL BOOTH MONTHLY
6 INTERNAL- MOM MONTHLY
7 LIST OF VEHICLES AT CMU PROJECT MONTHLY
8 TOOL BOX TALK RECORD DAILY
9 PPE'S ISSUE REPORT MONTHLY
10 FIRE EXTINGUISHER REPORT MONTHLY
11 MONTHLY SAFETY REPORT MONYHLY
12 SAFETY AWARENESS PROGRAM MONTHLY
13 FIRST-AID REPORT MONTHLY
14 WORKERS MEDICAL EXAMINATION REPORT  
15 ELCB CHECKING REPORT MONTHLY
16 JSA REPORT ACCORDING TO JOB
17 PENALTY BOOK UPDATED
18 WELDING MACHINE CHECKING REPORT MONTHLY
19 TPI INSPECTION REPORT MONTHLY
20 CRANE/HYDRA/MEN LIFT CHECK LIST DAILY
21 VEHICLES FITNESS CHECKING REPORT MONTHLY
22 SAFETY INDUCTION REPORT FIRST TIME
23 CLOSED PERMIT BOOK MONTHLY
24 COMPLIANCE & CLOSURE REPORT MAINTAIN
25 LIST OF PERSON WORKING AT HEIGHT MONTHLY
26 PPE'S INSPECTION REPORT MONTHLY
27 LIST ALL LIFTING TOOLS AND TACKLES MONTHLY
28 SAFETY COMMITTEE MEETING SHEET MONTHLY
29 SCAFFOLDING INSPECTION REPORT MONTHLY
30 MAN-HOURS STATISTICS REPORT MONTHLY
31 SAFETY OBSERVATION REGISTER UPDATE
32 EARTH PIT INSPECTION REPORT MONTHLY
33 WORKER COLONY INSPECTION REPORT MONTHLY
34 FLAG MAN MONTHLY

भवदीया /Regards,

Attention M/s RCM (PMIL)


This is with reference to the above subject; we want to inform you that, in spite of
several reminders verbally you failed to submit HSE report timely to us and next time if
report will not submit timely we will definitely impose penalty as per contract for HSE
Report.

This is for your kind information and necessary action please.

Note-- Immediately submit HSE Report by tomorrow otherwise impose penalty as per


contract.

भवदीया /Regards,

Dear Sir, 

As per ur trailing mail, i would like to inform you that i already have used ELCB (63 A)
in my distribution panel which you already have seen. But according to PDIL we have to
be used separate ELCB which we know yesterday and i have taken action today and
separate ELCB provided to all welding machine. 

So i don't understand why penalty,when i am able to fulfil the criteria to work with u.... 

Thanking you 

Dear Sir,
As Per trailing mail,
Please find herewith attached fine due to unsafe electrical practice at site.
This is for your ready reference.

Regards

Dear Sir,

This is in continuation to the trailing email against non submission of HSE Report.
Kindly find enclosed herewith the penalty letter.

You are again advised to arrange to submit the HSE Report in order to avoid further
penalty.

Also, kindly note that your Lead Safety Office is absent from site since more than 15
days. Kindly arrange to deploy the same at the earliest, for ensuring issuance of work
permits at site and avoid further penalty.

भवदीया /Regards,
It has been observed that, even after repeated reminder to your Safety Officer and RCM,
your workers were found engaged in Hot Job without IFR Suit. The matter was
communicated to you today on priority but still negligence/noncompliance has been
observed, at the site.

Further, on advising to suspend such Hot work for two days, misbehaving approach
from your staff has been observed. PDIL shall not tolerate such unhealthy behavior at
site.

The matter has been communicated to appropriate level and suitable penalty shall be
imposed on to you, Very Soon, As Per Terms Of Contract.

भवदीया /Regards,

Dear Sir,
As per trailing mail, Mr. Sattar Alam lead Engineer Mechanical asked for leave from 10-
07-2021 to 30-07-2021. After Discussion Mr. Sattar is agree that he will come back from
leave on 25.07.2021 instead of 30.07.2021.

At present no mechanical engineer is available at site rather then Mr. Sattar Alam. We
discuss with our new contractor and he will put his site incharge Mr. Kamlesh Singh to
look after the site in absence of Mr. Sattar Alam.

We don't have planning engineer at site so you are requested to depute one planning
engineer at site on or before 7th July'2021.

Regards,

Dear Mr. Chouni,


 
With reference to our discussion for  last 2-3 days, you are requested to send the
following documents at the earliest.
 
1. Billing Projection for next 2 months.- By 25.06.2021
2. Site mobilization plan of new contractor. – 26.05.2021
3.Dabit note of Venus. By 26.06.2021
4. List of final  out standing  payment of Venus’s vendors. 27.06.2021
 
Regards,

 Dear Mr. Singh,


 
We are sending the WO  within next 4-5 days time. Sorry for the delay.
 
Regards,

Dear sir 
As on previous discussion between you and Mr. Harendra Singh. It had been cleared
that the work order  (CMU unit IOCL Panipat) will  be issued on date 16-june 2021 but
we still did get a work order.it is making an obstruction to make the actual work plan.
So  hereby request to you please issue work order as soon as possible  
 
 
Thanks & Regards 

Dear Sir,

It has been observed that, even after warning to your Tractor No.-HR 10 X0371 without
permission working on site. The matter was communicated to you on priority but still
negligence/noncompliance has been observed, at the site.

We can not tolerate any type of safety violations at any cost.

Further, a financial penalty of Rs.10,000/- is imposed on you, as per clause No.-


3.1.13(Point No.-26) for the above non-compliance of safety norms.

भवदीया /Regards,

Dear Sir,

We are arranging Fire fighting training & First Aid training at our LG ELECTRONICS(I)
Pvt. Ltd. Ranjangaon, Pune. Site. So we are Invite you to for Training program. We
request to you please give us valuable time as early as possible.

If possible please give us following tentatively date 28/06/10 to 29/06/10

Thanking you,

Dear Sir,
As informed earlier, we would request you again please arrange to send us the site
Account Statement along with vouchers and Suppliers and Sub- contractors bills up to
date immediately without fail.

Best Regards,

Dear sir,
I would like to inform that height training will starting at 10:am near gate no 1 safety
training hall please send to staff and workers.

Thanks & Regards


Intekhab Alam

Dear sir,
Please provide TPI certificate of all tools and accessories as soon as possible

Thanks & Thanks


intekhab Alam

To,
RCM(PDIL)
CMU, IOCL- Panipat
Date: 22.06.2021
Sub: Request for permission to use lifting tools
Dear Sir,
This is to bring to your kind notice that for Vessel erection we have to use lifting tools
which are newly purchased items by M/s. DSA and they have done the TPI in their
name.
TPI certificates are also attached.

Request you to please allow us to use those materials for lifting purpose for 4 days upto
25.06.2021 and after 4 days all the TPI will be done in the name of Power Max.

Thanking you and assuring our best attention and service at all time.

Regards.

Dear Sir,
Our sub contractor is asking me about the specification of the IFR suits and details of the
approved venders, so please give me details.

Thanks & Regards


Intekhab Alam

Dear Sir
Please provide us specifications and approved vendors details of IFR SUIT. As to we
provide our purchasing department for purchase IFR suits

Thanks & Regard

Dear sir,
Please arrange the details below mention before start hot work activities.
1) IFR Suit
2) Water Hose pipe
3) Valid permit
4) Fire Extinguisher
5) Fire booth
6) Signage & Poster
7) Trained person

Thanks & Regards

Kind Attention RCM M/s PMIL,

Dear Sir,

It is observed that workers (04) & machinery (bearing gate pass of M/s VRC) are used
by M/s PMIL without any permission.

and also observed without TPI certificate and unsafe lifting work being carried out.

Its advice to you kindly look into the above matter & deploy your manpower and
machinery with effective M/s PMIL Gate pass with immediate effect.

Otherwise penalty will be imposed as per contract.

भवदीया /Regards,

Dear Sir,

Non submission of HSE Report month of May-21,


You are again advised to arrange to submit the HSE Report immediately.

Further, a financial penalty of Rs.11,000/- is imposed on you,as per clause No.-


3.1.13(Point No.-15) for the above non-compliance of safety norms.

Dear Sir,
You are requested to please take early action to procure one set of Gas detector
instrument for our site work.
As per IOCL we need one set each at OSBL and OSBL.
Other wise they will not issue permit.
In that case we will not be able to achieve our terget.
With regards,
For Venus Engineering
Debasish Bhattacharya

Dear Sir,

Please arrange Gas detector for cmu project Hot work permit will be not generate
without gas detector as per client instruction.

Thanks & Regards

Intekhab Alam

Dear Sir,
I would like to state that the gas detector must be available on both site. (OSBL & ISBL)
you have only one gas detector on site. Which is issued by client. If you want to work at
both site, Immediately purchase the gas detector to continue work, otherwise stop work
as per client instruction.

This is for your information and necessary action

Thanks & Regards

Dear All,

As per trailing mail (as per instruction of CGM (PJ),In view of rising COVID cases, all are
advised to ensure random COVID-19 testing of at least 10-15 persons of each
contractor's workmen including staff is done per day and report to be submitted to
IOCL.

Further, kindly ensure strict compliance of COVID protocols (including daily


measurement of temperatures, regular sanitisation of workplace etc) as set by IOCL /
government authorities. Also, individuals should get themselves vaccinated as per the
government guidelines.
For compliance & NA please.

Best Regards,

Dear Sir,
In view of rising COVID cases, as per instruction of CGM (PJ), all PMC are advised to
ensure that random COVID-19 testing of at least 10-15 persons of each contractors
workmen including staff is done per day and report to be submitted to IOCL. PMC staff
should also get themselves tested.

Further, kindly insure strict compliance of COVID protocols (including daily


measurement of temperatures, regular sanitisation of workplace etc) as set by IOCL /
government authorities. Also, individuals should get themselves vaccinated as per the
government guidelines.

For compliance please.

Regards,

Kindly provide detail of work, type of permit required and other details necessary for
processing of permit.

Vehicle details, license, driver etc.

Regards,

Dear Sir,

As per trailing mail we need following work permit for OSBL site upto 8 pm from today
along with we are sending you our all vehicle details for vehicle movement permission
purpose. Such as...

1. Hot work

2. cold work
3. Height work

4. Vehicle movement inside plant

Thanks & Regards,

Dear Sir,
A gentle reminder.

Request you to please issue Work permit at OSBL from today onward as we have
mobilized there and are planning to start pipe fit-up and welding job.

So, request you to please issue hot work, cold work, vehicle movement, height permit at
earliest.

Thanking you.

Regards.

Dear sir,
Please issue the permit to powermax i have received the permit shilpi engineering, so
please modify and correct the permitted problems.

Thanks & Regards


Intekhab Alam

Dear Sir,

Request you to please issue work permit to PMIL upto extended hour 8 pm from
28.04.2021.

Thanking you.

Regards.

Dear Mr. Bhattacharya,

This is a second reminder from PDIL as IOCL is under pressure and urging PDIL to
submit a reply closing this issue.

Request you to please do the needful from your end.


Regards.

Avishek Chatterjee.

Reminder - II

In ref to the mail Dated 15.04.2021, no suitable reply / compiled report has been
received yet now from your end .

Reply at the earliest.

Matter is most urgent.

Best Regards,

Dear sir,
We are informed that our client visit on site and checked hydra tyre his not OK. I am
forwarding the failed checklist, Please immediate replace the tyre for ongoing work.

Thanks & Regards


Intekhab Alam

Dear Sir,
I want to point out that your panel No #1 was not able to function because The SFU was
withdrawn from the panel. Even the submersible pump does not operate due to electric
supply. Please implement safety culture on the site. Otherwise the job will be impeded.

Kindly resolve the issue and reply at the earliest.

Thanks & Regards


Intekhab Alam

Dear sir,

It has been observed that even after repeated reminder to your hydra back tyre not
replace. the matter was communicated to you on priority but still
negligence/noncompliance has been observed at the site. so immediate replace tyre for
continues work.

This is for your information and necessary action

Thanks & Regards


Dear Sir,.
The matter is discussed with the owner of Hydra and he assured us to replace with the
new tyre tomorrow.
So please allow us to work at ISBL till the replacement is done.
With regards,
For Venus Engineering
Debasish Bhattacharya

Kind Attention- RCM M/s PMIL

In ref to the above subject, it is noticed that the site work is badly hampered from the
last two months due to site issues. Site issues like non payment of wages of manpower
deployed at site / wages of the machineries / contractors .it is time to time informed to
you . These site issues are generated since Feb-2021 and onwards In every month, site
labor / contractors asked these concerns (concern of non payment of wages) and site
work suffered. .

On Dated 15.04.2021, some labor complained about non payment of full wages of the
respective months , intimated through email also & we have asked for its reply . But as
on date, no reply has come from your end of our mail 15.04.2021.

Note that due to above stated site issues, work is not running smoothly. & the resulting
outcome did not achieved as required from the last two months on account of PMIL. We
have provided the sufficient works to you for the work and availability of materials.

Pl look at the matter on priority and reply to our email dated 15.04.2021 at the earliest.

Also to resolve these site issues at the earliest.

Best Regards,

All concerned please note:

Color coding of safety helmets to be strictly followed as per the guideline issued from
IOCL RHQ. we have given sufficient time to all agencies to comply said color coding
norms; but still color coding non-compliances being observed at project sites.

This is last and final reminder to all concerned to use safety helmet as per color coding
issued from IOCL. Deviation from IOCL issued guidelines shall not be acceptable at any
cost.
For needful action to all concerned please.

Thanks & Regards,

Dear Bikash,
Equipment colour coding system is not following on site. Please implement on the site
according to the instruction of our client April month colour code is Green

Thanks & Regards


Intekhab Alam

Dear Bikash,
The colour coding system for equipment does not follow at site. Please implement on
the site according to the instruction of our client April month colour code is Green

Thanks & Regards


Intekhab Alam

Dear Sir,
I would like to say that Hydra was operating with Flag men and guide rope during
material shifting. I am sending my observation photo while m going to visit site one
guide man available with guide rope and second man is preparation guide rope because
huge material stacking near warehouse. A flag man is standing behind hydra.

So our humble request you to not impose fine, your consideration will be highly
appreciation in this regards.

Thanks

Dear Sir,
This is to inform you that during today's visit at your site.

It has been noticed that your Hydra was operating without Flag men and any guide rope
during material shifting.

In this context, a financial penalty of Rs. 5,000/- is being imposed on you, as per clause
No.-3.1.13(Point No.-20) for the above non-compliance of safety norms.

Thanks
Dear Intekhab Alem,
There was no Flag man during my Visit.Kindly go thru' the attached pic.The Flag man
have been standing after my visit.

Note-Kindly attention to the safety officer & Safety supervisor will be on site during
material shifting.Today two pumps have been shifted from Hydra.You have been
warned earlier that you do not have to marching with material from Hydra.

Please use a tractor trolley otherwise impose penalty as per contract.

Thanks

Kind Attention RCM-M/s PMIL, M/s VRC,M/s DTH

Pl refer the trailing mail from our F&S on their compliance

Pl compile at CMU Site on priority basis.

Thanks

Dear Sir,

Please find attached the letter regarding the present site condition. Please ignore the
mail dated 31.03.2021

Regards,

A.Sengupta

Dear All ,

It is hereby informed that Weekly Review Meeting has been arranged as per schedule
1) VRC : 15:00 – 15:30 Hrs

2) PMIL : 15:30-16:00 Hrs

3) JSM: 16:00-16:30 Hrs

Sir,
Weekly review meeting of CMU project is planned tomorrow 02.04.2021 as per below
schedule

Online meeting time is as below

PDIL : 14:30 – 15:00 HRS

VRC : 15:00 – 15:30 Hrs

PMIL : 15:30-16:00 Hrs

JSM: 16:00-16:30 Hrs

Thanks & Regards

Dear Sir,

This is bring your notice that, after discussion with you. We already have removed sub-
standard quality scaffolding and stopped hot work job inside tank 1, today we have
prepared scaffolding platform which will be approved by you and we continue our hot
work inside Tank 1, in scaffolding platform.

We are also attaching herewith new standard scaffolding platform photo for your ready
reference.

So our humble request you to not impose fine, your consideration will be highly
appreciation in this regards.

Thanks

Dear Sir,

This is to inform you that during yesterday evening visit at your site.

It has been noticed that work at height tank No. - 01 sub-standard quality scaffolding is
being used (Height work violation).

Substandard scaffolding was already forbidden from use. However, you failed to
change/rectify the same, even after so many warnings.
In this context, a financial penalty of Rs. 10,000/- is being imposed on you, as per clause
No.-3.1.13(Point No.-5) for the above non-compliance of safety norms.

Thanks

dear Sir,

This is to bring to your kind notice that we would like to carry out Radiography work on
Tank-01 & PIPE from 24-03-2021 to 31-03-2021(Including Sunday & Holiday after 2
PM.) after 9 PM.

Request you to please issue us the permit after 9 pm (Including Sunday & Holiday after
2 PM.) after all the other work at Site get closed as at night time.

Thanking you.
Dear All,

Kind Attention- RCM

Schedule of the Project review meeting of this week is as follows:

CMU ; Date : 26/02/21

VRC : 14:30 – 15:00 HRS

PMIL : 15:00 – 15:30 Hrs

JSM: 15:30-16:00 Hrs

With regards

Rajesh Verma

Dear all,
On the occasion of 4th March,National Safety Day, we are celebrating at CMU
plant.National Safety Day Program is scheduled on 04th March' 21 at 10:30 Am at Cmu
Site.

All are requested to participate in the programs & solicit your presence to celebrate this
auspicious occasion.

Attention : RCM VRC & RCM PMIL & RCM JSM & RCM DTH

Monthly HSE  Activity Plan  has been planned for the month of March-21. The subject
for different date are as below;

Sunda
y  Monday   Tuesday  Wednesday  Thursday  Frida
   1 2 3 4 5
    Daily check list report Hydra inspection Inspection of Safety walk Monthly
inspection.  lifting tools temporary through report report we
inspection PPE,s electrical grinding & welding repo
inspection booth M/C inspection submissio
Hydra/JCB/tract housekee
or /trolley  First aid
inspection
7 8 9 10 11 12
   Welders & Grinders  (Trade Hand Safety Hot work Fire extinguisher  Weekly R
validation)Site safe work training Safety training.Cutti report, Vehicle submissio
Inspection.  Harness ng set Inspection.Docume Housekeep
Inspection Inspection.  nt Inspection. st Aid
Permit/JSA Inspection
Inspection. 
14 15 16 17 18 19
   Gas Cutter (Trade Scaffolding ELCB Excavation Pit Confined
validation)                                    Erection / Inspection Inspection PPE's training
CPR Training  Dismantling Safety Leads Inspection tools Insp
(Training).  meeting              Poster D
Height work   Inspect
inspection   
21 22 23 24 25 26
   Scaffolder  (Trade validation) Excavation Inter Hot work Weekly R
Site Safety Inspection           Safety training contractor Inspection submissio
Safety awareness Site HSE Audit Electrical cabal & Housekee
test.  (Internal)   Connection
Inspection 
28 29 30 31     
   Height work (Trade Store Inspection Height Work    
validation) Electrical DB Fire Point Safety
Inspection   Inspection Training
Scaffold
Inspection.
Monthly Safety
Review Meeting  

Dear sir,

Dear sir,

Please implement safety culture on the site I have observed new workers working hot
work without IFR suit, This is a big violating of the rules and regulations of the company
procedures. Must be the job systematically

I have observed following points in site.

1) No IFR suit

2) No Fire extinguisher

3) No SFU

4) No water hose pipe

5) No Fire booth

6) No signage & poster

We are also attaching herewith observation photo


Regards
Dear Bikash
Please implement safety culture on the site I have observed new workers working
without gat pass. paint work is going on without special training. This is a big violating
of the rules and regulations of the company procedures. Must be the job systematically

Remember and stay safe

1) No supervisor No work
2) No gat pass No work
3) No special Training No work
4) No Permit No work

Thanks & Regards

Intekhab Alam

Dear Sir,

Request you to please extend our both cold work and vehicle movement permit for
OSBL area for next one week.

Thanking you.

Regards.
Dear Bikash,
Work is carried out Under hazardous conditions at the pipeline frame, and there is no
suitable access within the work area. Ladder support without the appropriate platform.
ensure that workers have secure access. and please plan safely before starting the job
activities

Thanks & Regards

Dear Sir,
We are inform that our client (IOCL) visit in site and observe Fire house pipe use
without male and female cuplock. already we have informed your engineer and
supervisor for arrange cuplock but not any implement in site As per our client
instruction if not fixed male and female cuplock within 2 days then client will stop hot
work activity and not issue permit so immediate provide for continues work
 
 
This is for your information and necessary action
 
Thanks & Regards
 
Intekhab Alam

Sir,

CMU Offsite area jobs being executed in PNC needs attention for below points
Dear Sir,

Attached please find the following JSA for OSBL duly signed by IOCL.
1. Piping Erection.
2. Excavation Work.

This is for your information and records.

Regards.

Dear All,

Compliance the trailing mail points immediately at site.

Best Regards,

Dear Sir,
We are inform that our clinte(IOCL) visit in site and observe Fire house pipe using
without male and fimale cuplock. already we have informed your engineer and
supervisor for arrange cuplock but not any impliment in site As per our clint instruction
if not arrange male and female cuplock within 2 days then clinte will stop hot work
activity and not issue permit so imidiate provide for continues work
 
 
This is for your information and necessary action
 
Thanks & Regards

Dear Bikash

I would like to say that you do not have enough safety belts according to the working
condition at the site. I can not permit the work without safety belt.so please arrange
safety belt before stopping the work at height.

As per your commitment, you will have safety belt available within two days,
Wednesday, January 27, 2021
 

Dear Sir

I would like to say that the work permit booklet is not available on-site so it will be
printed as soon as possible

Thanks & Regards


Dear Bikash

Please provide a scrapyard because the scrap scattered here and there please pick up
the scrap and send it to the designated area. and please take out scrap near the DG area.

Dear Sir

I would like to say that We are going to arrange the motivation program1st January
2021 but the motivating banner is not available on-site so it will be printed as soon as
possible. I am sending a sample please find attached copy of banner.

Thanks & Regards

Dear Sir,

Kindly provide the budget for 46 National Safety Day/Week Celebration-2017 as per
below detail.

Dear Abhay

Please arrange to remove the scrap w.r.t your material , for the coming senior
management visit .

It is the strict instruction given by MSIL.

Please do the needful.

Regards.

Sanjeev.

RB

Photographs of meeting is attached below for your reference.

-- Dear Sir,
Kindly allow M/s RBIPL to work for in late hours for wall dismantling in production hall
of TM Plant till 12:00AM on20.09.16. The activity is ground based and is well ventilated
& illuminated.

The urgency arises following machine installation by ETE-MPT.

Regards,

H M SUNIL KUMAR

98110 30636

Dear Sir,

This is to inform you, we have observed that JCB vehicle no.HR-55U-0503 have no valid
insurance. We have already instructed dileep Supervisors of gautam-contractors to
ensure valid insurance but their are no any responses and work is going on so please
hardly instruct to dileep for valid insurance .

Mr.Salim worker of Vartika engineers contractors. Work in fabrication yard I told to him
yesterday use only exit door surrounding fabrication yard for material shifting but their
are no response and avoid my instruction and open hard barricade area continues
shifting work . This is big violating of the rules and regulation of the company
procedures. BreakDear Sir,

 
We are waiting for your valuable reply please against our trailing  mail.
 
Thanks & Regard

Dear Sir,
It has been observed that, even after repeated reminder to your Main electrical panel
SFU (Switch Fuse Unit) not install and even in January month ELCB Earth leakage
testing not done. The matter was communicated to you on priority but still
negligence/noncompliance has been observed, at the site. 
Further, on advising to suspend such electric work for two days.
After receiving compliance reports Permits will be issued.

Dear Bikash,
As discussed above subject matter we request you to kindly arrange to calibration of
Elcb Tester on Site.

Thanks & Regards

Intekhab Alam

Dear Sir,

We would like to inform you that 62.5 KVA DG Calibration will be expired Nov-20

Hence we request you to kindly accord your @ 3500/ Calibration charges

Bank Details.

AC: 20081030973

IFSC: SBIN0008706

Branch : SBI Bahubali IOCL

Account Holder : Vishva Mohan

Please Make the payment after received the Calibration Certificates.

Regards,

Dear Bikash,

I would like to say that you do not have enough halogen light according to the working
condition at the site. You have just four lights on site. Therefore please enough light
must be available before sundown.
Dear sir,

With reference to above subject , Today there is no work activity at M/s PMIL site. All
workers are sitting on strike at site . the workers are striking every month at your site
due to delay in payment at M/s PMIL end . Further the work progress of M/s PMIL is
already slow .

Kindly resolve the issue and reply at the earliest.

Regards,

In Reference to trailing mail, the CV of Mr Naveenkumar C is being approved as per


annexure -A- XII (Contract Requirement) for the Post of Lead QA/QC Engineer of
Composite Mechanical works at CMU Project.

This is for your kind information and records plz.

Regards,
JEETENDRA KUMAR DEWANGAN

QA/QC ENGINEER (MECHANICAL)

Projects & Development India Limited.

CMU, Project.

Panipat- Haryana.

On Sat, Jun 19, 2021 at 2:41 PM PDIL PRPC <pdilpr@gmail.com> wrote:

Pl review and approve the same.

आभारी | Regards

राजेश वर्मा | Rajesh Verma

Resident Construction Manager

प्रोजेक्ट्स एंड डेवलपमें ट इंडिया लिमिटे ड | Projects & Development India Limited

(भारत सरकार का उपक्रम)| (A Govt. of India Undertaking)


सीएमयू,परियोजना।

पानीपत-हरियाणा.

मोबाईल । 7836965210

Wear a mask. Help slow the spread of COVID-19.

---------- Forwarded message ---------

From: PMIL IOCL Panipat Project <projectpanipat@powermaxgroup.net>

Date: Wed, 16 Jun 2021 at 15:02

Subject: Fwd: CV of QA/QC engineer

To: pdilpr <pdilpr@gmail.com>

Cc: jkdewangan21 <jkdewangan21@gmail.com>, deepak1988c


<deepak1988c@gmail.com>, akcunitech <akcunitech@yahoo.com>

Dear Sir,

Please find attached the CV along with credentials of our new QA/QC Lead for your
review and approval please.

You are requested to please review the CV and accord your approval.
Thanking you and assuring our best attention and service at all times.

Regards.

Amiya Kumar Chouny.

RCM.

From: "AMITABHA SENGUPTA" <asengupta@powermaxgroup.net>

To: "PMIL IOCL Panipat Project" <projectpanipat@powermaxgroup.net>

Cc: "Arunava Roy" <arunavaroy@powermaxgroup.net>, "ARUNAVA ROY"


<aruproy1952@gmail.com>, mksengupta@powermxgroup.net

Sent: Tuesday, June 15, 2021 6:58:03 AM

Subject: CV of QA/QC engineer

Dear Mr. Chouny.

Please find attached the CV of QA/QC engineer. Please take approval from client and
forward to us.

Regards,