DAILYREPORTFROM SITE

S.No:21

1.

Date 28.12.2012

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Nil.

2.

Details of communications sent to HO


on

Nil.

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


:

MR.M.E.MANIKANDAN(2141)

5.1

Staff (VEESONS)

Mr. DINESH KUMAR.S (1832)

5.2

Contract Workers (Contractor wise)

Utkal Engineers:
Boiler: Supervisor:01 IB
03; Riger-02;grinder-0 Helper-04(Total=13)
S.N Furnace:

Supervisor with Massion -01Nos Massion-03


6.

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

4. Milwright fitter req for rotary equipm

7.

Materials, documents, payments urgently


required from HO with details

1. Utkal engg Contractor payment.

8.

Any urgent / important site complaints

UTKAL Engineering Should be


increasing his manpower./

Site status:

Vwta020 BOILER:
Work started time:08-00AM work end time: 7-00PM
1) Hopper to PA line Pad Welding Work U/P.
2) Feed piping Hp welding work U/P.
3) Common Discharge header to WHRB I,ii,iii inlet piping work
U/P.
4) Sporger Header drain piping erection work U/P.
ESP;
1. Current pipe protection piping welding work U/P.
2. Support insulator erection work U/P.
Boiler No.VWH 053
REFRACTORY
1. Furnace Hopper Ash chute refractory work completed.

Prepared by (Name):

M.E.MANIKANDAN

Checked & Approved by (Name) :

M.E.MANIKANDAN

Signature:

Signature:

Staff No : 2141