DPR 28 12 12
DPR 28 12 12
S.No:21
1.
Date 28.12.2012
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
Nil.
2.
Nil.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
Utkal Engineers:
Boiler: Supervisor:01 IB
03; Riger-02;grinder-0 Helper-04(Total=13)
S.N Furnace:
7.
8.
Site status:
Vwta020 BOILER:
Work started time:08-00AM work end time: 7-00PM
1) Hopper to PA line Pad Welding Work U/P.
2) Feed piping Hp welding work U/P.
3) Common Discharge header to WHRB I,ii,iii inlet piping work
U/P.
4) Sporger Header drain piping erection work U/P.
ESP;
1. Current pipe protection piping welding work U/P.
2. Support insulator erection work U/P.
Boiler No.VWH 053
REFRACTORY
1. Furnace Hopper Ash chute refractory work completed.
Prepared by (Name):
M.E.MANIKANDAN
M.E.MANIKANDAN
Signature:
Signature:
Staff No : 2141