Professional Documents
Culture Documents
Activity Relationship Types Activity Relationship Types: X Y X Y
Activity Relationship Types Activity Relationship Types: X Y X Y
FINISH-TO-START START-TO-START
X Y X Y
FINISH-TO-FINISH START-TO-FINISH
X Y X Y
Logic Diagram (PERT)
Forward Pass: calculates the earliest time each
activity in the network can start and finish. 3 3 5
Calculates the overall minimum network duration
B E G
5 8 11
4 1 2 4 2
Duration Float A C F H I
1 5 8 11 16
110
ACTIVITY TITLE 3
Early Start = Early Finish of
D Predecessor + Duration (If
there are multiple
EarlySTart LateFTinish 5
4 1 2 4 2
Duration Float A C F H I
1 5 5 10 8 12 11 16 16 18
110
ACTIVITY TITLE 3
Late Finish = Successor
D Late Finish – Duration (If
there are multiple
EarlySTart LateFTinish 5 10
B E G
5 8 8 11 11 16
4 0 1 4 2 2 4 1 2 0
Duration Float A C F H I
1 5 5 10 8 12 11 16 16 18
110
ACTIVITY TITLE 3 2
D
Float = Late Finish –
EarlySTart LateFTinish 5 10
Duration – Early Start
Logic Diagram (PERT)
Finding Critical Path 3 0 3 0 5 0
B E G
5 8 8 11 11 16
4 0 1 4 2 2 4 1 2 0
Duration Float A C F H I
1 5 5 10 8 12 11 16 16 18
110
ACTIVITY TITLE 3 2
D
Critical Path Activities have
EarlySTart LateFTinish 5 10
0 Float