Professional Documents
Culture Documents
Management Techniques
By
BRYAN LLOYD C. PALLEGA,REE
IIEE ZAMBASULTA BOD
What is PERT and CPM?
Developed in the late 1950s, Critical Path Method or CPM is an algorithm used
for planning, scheduling, coordination and control of activities in a project.
Here, it is assumed that the activity duration is fixed and certain. CPM is used
to compute the earliest and latest possible start time for each activity.
The process differentiates the critical and non-critical activities to reduce the
time and avoid the queue generation in the process. The reason for the
identification of critical activities is that, if any activity is delayed, it will
cause the whole process to suffer. That is why it is named as Critical Path
Method.
Project Scheduling
B CONDUIT LAYOUT
C WIRING LAYOUT
G CONCRETE FINISH
E F
START A B C I J FINISH
G H
D
Activity A B C D E F G H I J
IMMEDIATE PREDECESSORS -- A B A A C,E A C,G D,F,H I
EXPECTED TIME(WEEKS) 5 1 2 1 2 3 3 1 1 0.1
FORWARD PASS
E 5 7 F 8 11
2 3
12.1
I 11 12 J 12 12.1
START A 0 5 B 5 6 C 6 8
1 0.1 FINISH
5 1 2
G 5 8 H 8 9
3 1
A ES EF
t LS LF D 5 6
1
EF = ES+t
Activity A B C D E F G H I J
IMMEDIATE PREDECESSORS -- A B A A C,E A C,G D,F,H I
EXPECTED TIME(WEEKS) 5 1 2 1 2 3 3 1 1 0.1
BACKWARD PASS
E 5 7 F 8 11
2 6 8 3 8 11
12.1
I 11 12 J 12 12.1
START A 0 5 B 5 6 C 6 8
1 11 12 0.1
12 12.1
FINISH
5 0 5 1 5 6 2 6 8
G 5 8 H 8 9
3 7 10 1 10 11
A ES EF
t LS LF D 5 6
1 10 11
LS = LF-t
Activity A B C D E F G H I J
IMMEDIATE PREDECESSORS -- A B A A C,E A C,G D,F,H I
EXPECTED TIME(WEEKS) 5 1 2 1 2 3 3 1 1 0.1
Slack=2 Slack=0
E 5 7 F 8 11
Slack=0 2 6 8 3 8 11 Slack=0 Slack=0
Slack=0
12.1
I 11 12 J 12 12.1
START A 0 5 B 5 6 C 6 8
Slack=0 1 11 12 0.1
12 12.1
FINISH
5 0 5 1 5 6 2 6 8 Slack=2
G 5 8 H 8 9
3 7 10 1 10 11
A ES EF
t LS LF Slack=2
D 5 6
1 10 11
Slack=2 Slack=0
E 5 7 F 8 11
2 6 8 3 8 11
Slack=0 Slack=0
Slack=0 Slack=0 Slack=0 12.1
I 11 12 J 12 12.1
START A 0 5 B 5 6 C 6 8
1 11 12 0.1
12 12.1
FINISH
5 0 5 1 5 6 2 6 8
Slack=2
Slack=2
G 5 8 H 8 9
3 7 10 1 10 11
A ES EF
t LS LF D 5 6
1 10 11
Slack = 0, is called critical activity Slack=5
Activity A B C D E F G H I J
IMMEDIATE PREDECESSORS -- A B A A C,E A C,G D,F,H I
EXPECTED TIME(WEEKS) 5 1 2 1 2 3 3 1 1 0.1
Slack=2 Slack=0
E 5 7 F 8 11
2 6 8 3 8 11
Slack=0 Slack=0
Slack=0 Slack=0 Slack=0 12.1
I 11 12 J 12 12.1
START A 0 5 B 5 6 C 6 8
1 11 12 0.1
12 12.1
FINISH
5 0 5 1 5 6 2 6 8
Slack=2
Slack=2
G 5 8 H 8 9
3 7 10 1 10 11
A ES EF
t LS LF D 5 6
1 10 11
Critical path is A,B,C,I and J Slack=5
Slack=1 Slack=0
E 5 7 F 8 11
2 6 8 3 8 11
Slack=0 Slack=0
Slack=0 Slack=0 Slack=0
I 11 12 J 12 12.1
A 0 5 B 5 6 C 6 8
0.1
0 5 1 11 12 12 12.1
5 1 5 6 2 6 8
Slack=2 Slack=2
G 5 8 H 8 9
3 7 10 1 10 11
ACTIVITY DURATION
1 2 3 4 5 6 7 8 9 10 11 12 12.1
FINANCIAL FLOW
PERSONNEL REQUIRED
ACTIVITY RME/REE/PEE SKILLED HELPER DURATION
(SUPERVISION) ELECTRICIAN
A N/A N/A N/A 5
B 1 3 2 1
C 1 3 2 2
D 1 3 2 1
E N/A N/A N/A 2
F 1 2 2 3
G N/A N/A N/A 3
H 1 1 1 1
I 1 1 1 1
J 1 1 1 .10
Personnel Salary
Personnel Daily Salary
Licensed Electrical Supervisor (PEE/REE/RME) 800
Electrician 500
Laborer/Helper 350
ACTIVITY RME/REE/PEE SKILLED HELPER DURATION Cost
(SUPERVISION) ELECTRICIAN (WEEK)
A N/A N/A N/A 5
B 800 1500 700 1 21,000.00
C 800 1500 700 2 42,000.00
D 800 1500 700 1 21,000.00
E N/A N/A N/A 2
F 800 1000 700 3 52,500.00
G N/A N/A N/A 3
H 800 500 350 1 11,550.00
I 800 500 350 1 11,550.00
J 800 500 350 0.10 1,155.00
S-Curve
%WA=Cumulative Sum of Weekly Accomplishments
%WA=∑ %𝑊𝑊 + 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 %𝑊𝑊𝑊𝑊
%WA7=13.06% + 26.13% = 39.13%
WEIGHTED
ITEM PARTICULAR AMOUNT WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13
PERCENTAGE
1 Activity A ₱ - 0
2 Activity B ₱ 21,000.00 13.06% 13.06%
3 Activity C ₱ 42,000.00 26.13% 13.06% 13.06%
4 Activity D ₱ 21,000.00 13.06% 13.06%
5 Activity E ₱ - 0.00%
6 Activity F ₱ 52,500.00 32.66% 10.89% 10.89% 10.89%
7 Activity G ₱ - 0.00%
8 Activity H ₱ 11,550.00 7.18% 7.18%
9 Activity I ₱ 11,550.00 7.18% 7.18%
9 Activity J ₱ 1,155.00 0.72% 0.72%
TOTAL AMOUNT ₱ 160,755.00 100.00% 0 0 0 0 0 26.13% 39.19% 52.25% 70.32% 81.21% 92.10% 99.28% 100.00%
WEEKLY BILLING
WEEK 1 = PHP 0.00
WEEK 2 = PHP 0.00
WEEK 3 = PHP 0.00
WEEK 4 = PHP 0.00
WEEK 5 = PHP 0.00
WEEK 6 = PHP 42,000.00
WEEK 7 = PHP 21,000.00
WEEK 8 = PHP 21,000.00
WEEK 9 = PHP 29,050.00
WEEK 10 = PHP 17,500.00
WEEK 11 = PHP 17,500.00
WEEK 12= PHP 11,550.00
WEEK 13= PHP 1,155.00
TOTAL COST PHP 160,755.00
Construction Methodology
Construction Methodology refers to the planned method of
construction, taking into account all contractual and legal
requirements, construction constraints, risks, and
opportunities.
Example
Chapter 1. Project Description
This chapter describes the construction methodology of the Electrical power system
installation of a 420sqm two-story bank located at XXXX st., Brgy xxxx, Zamboanga City.
- J. Sins
Any questions ?