CASE STUDY

2.1 INTRODUCTION
Case study involves the construction of a sewerage treatment plant,
which is located on lot 3311 & 3312 Taman Sri Cempaka, Jalan Junid, Mukim
Bandar, daerah Muar, Johor Darul Takzim for Tentuan Sawit Warisan Sdn at
Maharani town. Bhd. This constructions project has been start from 10
August 2008 and fully completed at 22 January 2010. This sewerage
treatment plant is a private project and not a government project that has
been develop by Khidmat Hijau Sdn. Bhd.

MUAR TOWN

SITE
LOCATION

SITE
LOCATION

Overall base area involved in this construction of the sewage plant is


comprised of 2727 square feet and also include a buffer zone of about 2317
square feet including road reserves for the site. The base area is suitable for
construction activities and have a good soil conditions for the construction of
the sewage plant. The person responsible for managing the construction
project are Mr. Mohd Rosdi bin Kasdi acting as site engineer for the
construction. He was assigned by the owner to build a sewage plant as
planned and according to a predetermined plan.
The construction of the sewage plant on the lot Taman Sri Cempaka is
the construction of complete and overall which includes M & E room, toilet,
control room, inspection chamber, coarse screen chamber, influent pump
sump, secondary fine screen chamber, grit chamber, by-pass channel grease
chamber , grease chamber, aeration tanks, sedimentation tanks, sludge
holding tank, chlorodination chamber, 'V' notch measurement chamber, sand
drying bed dry cake and storage area.
For the M & E specification, the equipment included are air blower,
influent pump, fine bubble diffuser, sludge pump and coarse bubble diffuser.
For process and instrumentation, equipment including raw sewage pump, air
blower, sludge pump, air diffuser for aeration tank and air diffuser for sludge
holding tank. The construction site is equipped with compound lighting.
Depth of excavation for the construction of the sewage plant is 4575 mm
equivalent to 4.58m according to plan drawings provided numbered WYE
3006 / SW / 09 / SW-04. According to SMM (Standard Measurement Method)
4.58m depth is located between 4m but not exceeding 6m for excavation
work.

2.2 PARTIES INVOLVE


Every construction project should and must have parties that involved to handle the
construction process. As well as this sewage treatment plant construction, which
have involves many parties such as owner, contractors, project manager and others
to make sure all process run well.