You are on page 1of 3

NTPC

RIHAND
STANDARD CHECKLIST:: SYSTEM COMMISSIONING

STATION: NTPC /RhSTPP-II (2 x 500 Mw) ; UNIT: _____


PLANT ITEM: WIND BOX ASSEMBLY

SHEET

1 OF 2

Date -

Name of the system: ___________________ Plant area: ________________________


System Drawing No: __________________ Manufacturers Name:__________________
Location :
SN

_____________________ Serial No: ________________________


ACTIVITY

1.

General conditions satisfy the site standing Instructions as listed


in the Plant Item Commissioning Essential Pre-requisites (SCL
MS 1/1).

2.

The installation is complete and correct in accordance with the


latest drawings.
Access for adjustments, maintenance and repairs is satisfactory.

3.
4.

The correct wind box assembly is installed in correct furnace


corner

Burner tilt position indicator with pointer is provided in each


corner.
There is no obstruction to the movement of wind box dampers
when opening and closing and the dampers are free in operation.

The wind box dampers remain 5 deg open in closed condition.

Ensure that the tilting mechanism is properly erected.

Inspect tilt linkages to ensure components are in good condition


and there is no interference with other components, building steel,
platforms etc.
Stipulated clearance from wind box assembly to structural steel is
provided to take care of thermal expansion of the boiler.

10

STATUS
Yes / No

11

Check Burner nozzle tips have stipulated clearance from water


walls.
SCL REF: M/VOL II /SEC F /07

NTPC

RIHAND

STATION: NTPC /RhSTPP-II (2 x 500 Mw); UNIT:


SN

SHEET 2 OF 2

ACTIVITY

12

Check burner tilt mechanism for smooth operation.

13

Set the burner tilt at zero degrees as indicated in the position


indicator and check all the nozzles are herizental.

14

Set the burner tilt at + 30 deg as indicated on position indicator.


Measure actual angle of nozzle tilt at all elevations and check that
they are within (30 + 1

15

Set the burner tilt at-30 deg as indicated on position indicator.


Measure actual angle of nozzle tilt at elevations and check that
they are within (-30+ 1 ) deg.

16

Obtain the Certificate from erection personnel stating that the


assemblies are installed to give a correct firing angle and stating
the actual firing angle.

17
Check all the dampers as per dampers standard check list.
SCL REF: M/VOL II /SEC F /07
Remarks: -

STATUS
Yes / No

Name
Agency
NTPC-Erection
NTPC-Commissioning

Signature

Date