You are on page 1of 3

NTPC

RIHAND
STANDARD CHECKLIST:: SYSTEM COMMISSIONING

STATION: NTPC /RhSTPP-II (2 x 500 Mw) ; UNIT: _____

SHEET

1 OF 2

PLANT ITEM: ELECTROSTATIC PRECIPITATOR


(MECHANICAL)
COLLECTING ELECTRODE RAPPING MECHANISM

Date -

Name of the system: ___________________ Plant area: ________________________


System Drawing No: __________________ Manufacturers Name:__________________
Location :
SN

_____________________ Serial No: ________________________


ACTIVITY

1.

General conditions satisfy the site Standing Instructions as listed


in the Plant Item Commissioning Testing Essential Pre-requisites
(SCL MS 1/1)

2.

The name plate legend agroes with the approved NTPC Plant
Nomenclature, is clearly visible, securely fixed, is durable and
correlates with any remote labels.

3.

Installation is correct and complete as per the latest approved


drawings.

4.

Ensure that there is no foreign material inside the ESP and check
the cleanliness of hoppers and walls.

Check the disposition and tightness of inner arms on rapping


shaft set at proper phase angle.

Check the support bracket provided in the middle of two hammers.

Check the distance between centre line of rapping shaft to center


line of shock bar.

STATUS
Yes / No

Ensure that the shock pad face and shaft axis are in the same
vertical plane.

Check the lateral shift to hammers with reference to shock pad


centre.
SCL REF: M/VOL II /SEC F /04

NTPC

RIHAND

STATION: NTPC /RhSTPP-II (2 x 500 Mw); UNIT:


SN

SHEET 2 OF 2

ACTIVITY

10

Check the proper sealing of the rapping shaft in the bearing.

11

Check the set rings position and their welding.

12

Check the clearance between collecting electrode and gas screen.

13
Check the radial & axial alignment of clutch & coupling

STATUS
Yes / No

SCL REF: M/VOL II /SEC F /04


Remarks: -

Name
Agency
NTPC-Erection
NTPC-Commissioning

Signature

Date