You are on page 1of 1

MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : : COMMISSIONING / TESTING PREREQUISITES : REF : SHEET 1 OF 1 1 X 500 MW UNIT :7

LOCATION:

PLANT NOMENCLATURE: _________________________________________________ MANUFACTURER ___________________ SERIAL NO. __________________________

NO .

ACTIVITY

STATUS REMARKS (YES/NO)

1. 2. 3.

Access to the plant item is adequate Illumination in the plant area is adequate. Any other requisite safety provision is adequate for the immediate commissioning activity. Plant item is in a clear condition. All necessary locks and keys for padlocks, interlocks etc. are available. Hot surfaces lagged or screened or screened sufficiently to provide protection for personnel.

4. 5.

6.

NAME MECH.ERECT. NTPC ELECT.ERECT. COMMNG. C&I BHEL ERECT. COMMNG.

SIGNATURE

DATE

CONTRACTOR