You are on page 1of 3

NTPC

RIHAND
STANDARD CHECKLIST:: SYSTEM COMMISSIONING

STATION: NTPC /RhSTPP-II (2 x 500 Mw) ; UNIT: _____


PLANT ITEM: DAMPER/GATE ELECTRICALLY OPERATED`

SHEET

1 OF 2

Date -

Name of the system: ___________________ Plant area: ________________________


System Drawing No: __________________ Manufacturers Name:__________________
Location :

SN

_____________________ Serial No: ________________________

ACTIVITY

1.

General conditions satisfy the site Standing Instructions as listed


in the Plant Item Commissioning Testing Essential Prerequisites
(SCL MS 1/1).

2.

The nameplate legend agrees with the approved NTPC Plant


Nomenclature, is clearly visible, securely fixed, is durable and
correlates with any remote labels.

3.

Installation correct and complete to latest drawings. Heavy valves


are supported properly and independent of the pipeline. Damper
should not carry the load of the pipeline.

4.
5

Direction of flow marked and correct.


Check duct damper connection

Check mounting of damper/gate actuator

Access adequate for adjustments, maintenance and repairs and


check mechanical completion.

Adequate locking facility exists.

Lubrication suitable and satisfactory.

STATUS
Yes / No

10

Freedom of operation fully open to fully closed. Physically check.

11

Check stuffing boxes/seals


SCL REF: M/VOL I/SEC H /03

NTPC

RIHAND

STATION: NTPC /RhSTPP-II (2 x 500 Mw); UNIT:


SN

SHEET 2 OF 2

ACTIVITY

12

Check direction of opening and closing

13

Check Position indicator visible and indicating correctly and set


correctly (if appropriate)

14

Remote indication limit switch mounted securely and set correctly


(if appropriate)
Verify the torque and limit switches are properly set.

15

Adequate clearance to wall / steelwork around hand wheel for


operation.

16

Check damper behavior for smooth operation under operating


condition and over entire range

17
18

Check the gate entry seal ,undamaged.


Check blowers at gate /damper mounting and functioning. (SCL
for blower to be filled separately.)
Check the blower outlet pneumatic gate for its proper operation.
SCL REF: M/VOL I/SEC H /03

19

Remarks: -

STATUS
Yes / No

Name
AgencyNTPC-Erection
NTPC-Commissioning

Signature

Date