STANDARD CHECKLIST:: SYSTEM COMMISSIONING

STATION: NTPC /RhSTPP-II (2 x 500 Mw) ; UNIT: _____


PLANT ITEM: LUBRICATOR COMPRESSED AIR LINE

SHEET

1 OF 2

Date -

Name of the system: ___________________ Plant area: ________________________


System Drawing No: __________________ Manufacturers Name:__________________
Location :
SN

_____________________ Serial No: ________________________


ACTIVITY

1.

General conditions satisfy the site standing instruction as


listed in the Plant Item Commissioning Essential Pre requisites
(SCL MSI/1).

2.

The name plate legend agrees with the approved NTPC Plant
nomenclature and is clearly visible, securely fixed, durable and
correlates with remote labels.

3.

The installation is complete and correct in accordance with the


latest drawings and specification.

4.

Check that quick opening cap arrangement for oil filling is


provided.

Check that air line connected at inlet and outlet of lubrication are
tested and blown.

Confirm the integrity of the joints at inlet and outlet of lubricator.


Check the oil level in the lubricator.
SCL REF: M/VOL II/SEC F /06

STATUS
Yes / No

NTPC

RIHAND

STATION: NTPC /RhSTPP-II (2 x 500 Mw); UNIT:


SN

SHEET 2 OF 2

ACTIVITY

STATUS
Yes / No

Adjust the drip rate to 1 drop/minute by adjustor mechanism.

Check that the drip rate is clearly visible through transparent


polycarbonate bowl and sight tube.
SCL REF: M/VOL II /SEC F /06

Remarks: -

Name
Agency

Signature

Date

NTPC-Erection
NTPC-Commissioning