MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : STRAINER ROTARY LOW PRESSURE

REF : SHEET 1 of 2

1 X 500 MW

UNIT

:7

LOCATION:

PLANT NOMENCLATURE___________________________________________________ MANUFACTURER______________________SRL.NO._____________________________


NO. ACTIVITY STATUS (YES/NO) REMARKS

1.

General conditions satisfy the site Standing Instructions as listed in the Plant Item Commissioning Essential Pre-requisites (SCL MS1/1). The nameplate legend agrees with the approved NTPC Plant Nomenclature is clearly visible, securely fixed, durable and correlates with remote labels. The installation is complete and correct in accordance with the latest drwings and specification. Access for adjustments maintenance and repairs is satisfactory. Lubricating oils and greases have been applied and are satisfactory.
NAME MECH.ERECT. SIGNATURE DATE

2.

3.

4.

5.

NTPC

ELECT.ERECT. COMMNG. C&I

BHEL

ERECT. COMMNG.

CONTRACTOR

MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : STRAINER ROTARY LOW PRESSURE
REF : M/5/2 NO. ACTIVITY SHEET 2 of 2 STATUS (YES/NO) REMARKS

1 X 500 MW

UNIT

:7

LOCATION:

6. 7.

Strainer drum shaft seals satisfactory. Drum correct. shaft/gearbox alignement

8. 9.

Scraper plate mounting satisfactory. Circumferential strainer drum seals satisfactory. Drum alignment to casing correct. Access manhole appropriate). covers fitted (if

10. 11.

12.

All pipework to and from strainer terminated correctly.

NAME MECH.ERECT. NTPC ELECT.ERECT. COMMNG. C&I BHEL ERECT. COMMNG.

SIGNATURE

DATE