Professional Documents
Culture Documents
App Peer Rev Australia-India Perspective 23 June
App Peer Rev Australia-India Perspective 23 June
NTPC Delegates :
I.K.Rajdeva,
A.Nagasundaram, Dy. Gen. Manager, NTPC Ltd. Saju K Sebastian, Dy. Gen. Manager, NTPC Ltd. P.S.Chatterjee, Chief Design Engineer, NTPC Ltd.
CESC Delegates :
Souvik Dutta, Station Manager, Southern generating Station, CESC Ltd .
Kushal Bhowmick, Senior Manager ( Environment), CESC Ltd.
TOTAL
144,773 100.0%
PLF (%)
48 1985-86 1986-87 1987-88 1988-89 1989-90 1990-91
53 .9 55 .3 57 .1 61 60 63 64 .4 64 .7 64 .6 67 .3 69 56 .5 55 53 .2 56 .5 52 .4
53
58
63
68
73
78
Y EARS
1996-97 1997-98 1998-99 1999-2000 2000-01 2000-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
69 .9 72 .7 74 .3
72 .2
74 .8
77 . 03 78 . 61
Energy Shortage
9.8%
750 REQUIREMENT 700 650 600 550 500 450 467 2001 483 2002 498 2003 2004 2005 2006 2007 2008 546 507 7.8% 523 7.5% 519 591 631 AVAILABILITY 691 737
9.6%
8.3%
665 624
7.3%
579
8.8%
559
7.1%
548
665 618 1 ,4 6 5 1 ,6 8 4 2 ,3 4 0
In 2006
NATIONAL ELECTRICITY POLICY TARGETS PER CAPITA AVAILABILITY OF 1000 KWH BY 2012
6 ,4 2 5 7 ,4 4 2 8 ,4 5 9 1 4 ,2 4 0
2 ,7 0 1
Figures in kwh
Source: UNDP Human Development Report 2007-08 Data for 2004
778 GW
2007
2012
2022
2032
Source: Integrated Energy Policy GOI
Thermal 59,513MW ( Coal 51,890 MW, Gas- 5343 MW, Lignite- 2280 MW) Additional capacity expected : New Renewables 14,000 MW : Captive 12,000 MW
9,263 MW capacity already commissioned 60,214 MW (77%) under construction 10,950 MW - Letter of awards yet to be placed Fuel Availability for 96% of coal based stations tied up 88% hydro capacity under construction /commissioned All gas based projects under execution or gas tied up from local sources
Installed Capacity (as on 31.03.2008)- 11125 MW 11th Plan target- 14,000 MW consisting of Wind Power 10,500 MW Biomass Power Baggasse Co-generation Small Hydro (up to 25 MW) -
2,100 MW 1,400 MW
PLAN
NUCLEAR
(MW)
XIITH 82200
Energy Efficiency NATIONAL THERMAL GOVERNMENTS STRAGTEGY / POWER CORPORATION INITIATIVE FOR EFFICIENCY LTD. IMPROVEMENT
- A PROFILE
Setting the Scene today for a futureoriented Sustainable Energy production
INDIAs ENERGY PROGRAMS AND POLICIES Improving energy efficiency Promoting Hydro and renewable energy Power sector Reforms Promotion of Clean coal technology Energy infrastructure Development Coal Washing Environmental Quality Management
Demand of power is set to grow with growing economy Large capacity needs to be added to meet the projected growth in demand With Electricity Act 2003 coming into vogue, the power market is set to attract a lot of investors and competition With tariff based bidding becoming a norm, utilities have to bring down their cost of generation to remain competitive Increased emphasis on Environmental considerations for clean technology CDM opportunities arising out of global warming concerns Fuel, Land & Water availability becoming more and more difficult Efficiency enhancement feasible in future plants as well as existing plants
Major Initiatives
Promotion of Renewable Energy Sources 15,627 MW Capacity of Hydro Power planned in XIth Plan 30,000 MW Capacity of Hydro Power planned in XIIth Plan Retiring 5000 MW old capacity with low efficiency in 11th Plan
Major Initiatives ..
Appoint Energy Manager Get Energy Audits conducted by Accredited Energy Auditors Implement techno-economic viable recommendations given by Accredited Energy Auditor Comply with norms of specific energy consumption fixed Submit report on steps taken
Major Initiatives
Presently Working to develop a Demonstration Project for IGCC along with suitable Partner, development of core technologies for gasifier & Gas cleaning systems suitable for High Ash Indian Coal.
Major Initiatives ..
Ultra Mega Power Projects(4000MW capacity) based on Supercritical Technology at various pithead and coastal locations. Envisaging Mandatory Higher size thermal units (660/800 MW) with Supercritical Parameters.
It is estimated to commission
10 Nos. units of 660MW (XIth Plan) 2 Nos. units of 800MW (XIth Plan) 12 Nos. units of 660MW (XIIth Plan) 31 Nos. units of 800MW (XIIth Plan)
Major Initiatives ..
Supercritical Units of 660 MW Rating under construction Supercritical Units of 800 MW Rating with higher steam temperature conditions under consideration
Parameter Main Steam Pressure Kg/cm2 Main Steam Temperature oC Reheat Temperature oC
43%
42% 320/600/620 41% 247/565/593 40% (660/800 MW) 247/537/565 (660 MW) 39% 170/537/537 (500 MW) 38% 280/600/620 (800-1000 MW) (800-1000 MW)
00
02
Xth Plan
07
XIth Plan
12
XIIth Plan
17
XIIIth Plan
22
Poorer condenser vacuum due to hot climatic conditions Higher unburnt carbon losses in boiler due to low grade high ash Indian coal Efficiency is reported on HHV basis of coal (same as the practice followed in USA) as against LHV used elsewhere.
Typical variation due to above = 3.0 to 4.0 % points (Approx.)
P=1 0a 7 ta M =5 7 ST 3 RH =5 7 T 3
P=1 0a 7 ta M =5 7 ST 3 RH =5 5 T 6
P =2 7 a 4 ta M =5 7 ST 3 RH =5 5 T 6
P=2 7a 4 ta M =5 5 ST 6 RH =5 3 T 9
Member of Carbon Sequestration Leadership Forum (CSLF) Participating in FutureGen Project of USA
275 MW coal fired Zero Emission power plant India contributing US$10 Million
Participating in Asia Pacific Partnership (APP) for Clean Development and Climate
The Indian Project Proposals in the TF Action plan Inputs like case studies & contact details of experts in areas of Indias interest.
Work on Efficiency improvement of two thermal power plants namely Ropar and Kolaghat thermal Power station already started with support of USAID.
Major Initiatives ..
Energy Conservation Awards National Award for improving performance of Thermal Power Stations Awards for reducing T & D losses.
A COST EFFECTIVE APPROACH CONTINUE GETTING THE BEST OUT OF EXISTING FLEET
Improvement in performance parameters PLF, Availability, heat rate/efficiency, auxiliary power consumption, partial loading & forced outage. Restore derated capacity Extension of economic life. Obsolescence & non availability of spares (eg C&I) Environmental requirements. issues/other statutory
Safety requirements.
A large number of 200/250 MW & some 500 MW Units are in operation for more than 15/20 years and have considerable potential for life extension & efficiency improvement Total No. of Units Age 200/210 MW Units (LMZ design) 200/210 MW units (KWU design) 500 MW units 53 88 35 Nos. of Units as potential Candidate >15 years -37 12 >20 years 53 12 2
Shift in focus from Generation Maximization to Plant Performance Optimization Older units have many more opportunities to reduce heat rate than newer units. Retirement of very old small size low efficiency units and replacement with higher efficiency units. Use of high end technology solutions for efficiency enhancement to manage rising costs & reduce carbon, foot prints, e.g.,
Steam flow path modification Steam turbine and boiler upgrades Improved plant control
Additionality in efficiency improvement Efficiency improvement as a result of normal R&M, aims at to minimising losses ( to approach design values) Efficiency improvement through technology intervention/enhanced R&M, targeting efficiency enhancement even beyond design value.
Unit Heat Rate Unit Auxiliary Power consumption Unit Specific secondary fuel oil consumption Unit Specific coal consumption Plant Load Factor (PLF) Planned Maintenance, Forced outage and Operating availability
1 2 3 4 5 6 7 8
Best Practices for Power Generation Activity Plan Best Practices for Transmission and Distribution Activity Plan Best Practices for Demand Side Management Activity Plan Energy Regulatory & Market Development Forum Trade Exhibitions/Conferences and Trade Missions Hydroelectric Generation Best Practices Combustion Optimization in Coal Based Power Plants Implementation of Artificial Intelligent Soot Blowing System for Improving the Steam Generator Efficiency by Increasing the Effectiveness of Soot Blowers. SOx Reduction Technologies in Flue Gas Risk Evaluation and Prioritization (REAP) for Maintenance and Renovation & Modernization (R&M) of Power Plants Life Extension & Remaining Life Assessment Of Power
USA, JAPAN, KOREA USA USA AUSTRALIA USA USA INDIA INDIA
9 10
INDIA INDIA
11
INDIA
20
15
12.7
7.5
2003-04
2004-05 2005-06
2006-07