Hasan Juma Backer Trading & PRE- WORK RISK ASSESSMENT Contracting Co.

LLC HJB Project Name REFURBISHMENT AND BITUMINOUS PAVING OF ROADS IN MAF 1120
Project No

REFINERY

S.No 1 2 3

Activity job stages Diesel filling to vehicles from tank Excavation Compressor

Hazard-what can go wrong Fire Falling Noise Pollution Oil spillage Slippery/fire Tool breaking Material flying at a distance Burn Sticking Pollution Incident

Risk Potential High Medium Medium

Controls Fire Extinguisher No smoking Barricade the area Display board Periodic maintenance Barricade the area

Action party Supervisor/ Operator Supervisor/ foreman Supervisor/ Operator

Contingency Evacuate area Blanket the fire First aid/clinic Keep distance Use ear plugs Use nose mask Clean oil spillage Stop work First aid/clinic Keep a distance First aid/clinic

Remark

Breaker

High

Guard for tool Barricade the area Use of PPE Barricade the area Attention while material spreading Operator with license Barricade the area Attention Operator with license Barricade the area Operator with license Barricade the area Working men maintain distance Skilled Operator Use PPE

Supervisor/ Operator Supervisor/ Foreman/ Operator Supervisor/ operator Supervisor/ operator Supervisor/ operator

Asphalt

Medium

Paver

Medium

Keep a distance First aid/clinic First aid/clinic

JCB Excavator

Incident

Medium

Rollers

Incident

Medium

First aid/clinic

Compactor

Incident Noise

Medium

Supervisor/ operator

First aid/clinic

Hasan Juma Backer Trading & PRE- WORK RISK ASSESSMENT Contracting Co. LLC HJB Project Name REFURBISHMENT AND BITUMINOUS PAVING OF ROADS IN MAF 1120
Project No

REFINERY

10 11

Grader Spray Tanker

Physical Stress Incident Incident Material spillage Incident Accumulation of material Incident Water spillage Environment aspects/ impacts Exhaustion

Medium Medium

Pause Operator with license Barricade the area Operator with license Barricade the area Operator with license Barricade the area Frequent removal of material Operator with license Barricade the area Controlling water flow Dispose off at the allotted area Provide shade to the extent possible Drink water at frequent intervals Rest time Facility at resting place

Supervisor/ operator Supervisor/ operator Supervisor/ operator

First aid/clinic First aid/clinic

12

Shovel

Medium

First aid/clinic

13

Water Tanker

Medium

Supervisor/ operator Supervisor/ operator Supervisor/ Foreman/ operators

First aid/clinic Stop the water flow First aid/clinic

14

Waste material disposal Working in Open Environment

Medium

15

Medium

First aid/clinic Take rest for some time

Risk Analysis Carried out by: Name S SIVAJI Designation Quality Assurance Coordinator Signature Date 07/07/2010 Rev.No 00 No of pages 2