Professional Documents
Culture Documents
Piled Foundation Design & Construction
Piled Foundation Design & Construction
Contents
z Overview
z Preliminary
Study
z Site
z Pile
Design
z Pile
Installation Methods
z Types
of Piles
Contents (Contd)
z Piling
z Pile
Supervision
Damage
z Piling
Problems
z Typical
z Myths
z Case
in Piling
Histories
z Conclusions
Overview
PILE CLASSIFICATION
z Friction
Pile
Bearing Pile
from base
Friction Pile
Overburden Soil
Preliminary Study
Preliminary Study
z Type
z Proposed
z Geology
of Area
z Previous
z Subsurface
z Selection
Investigation Planning
Proposed
Development
Existing
Development
B
SELECTION OF PILES
Factors Influencing Pile Selection
Types of Piles Available in Market (see Fig. 1)
Installation Method
Contractual Requirements
Ground Conditions (eg Limestone, etc)
Site Conditions & Constraints (eg Accessibility)
Type and Magnitude of Loading
Development Program & Cost
etc
TYPE OF PILES
DISPLACEMENT PILES
Hollow
Small displacement
Steel Pipe
Precast R.C.
piles
Bored piles
Micro piles
Solid
Concrete
NON-DISPLACEMENT PILES
Steel H-piles
(small displacement)
Concrete Tube
Closed ended
tube concreted
with tube left in
position
Bakau piles
Treated timber pile
Precast prestressed
piles
Steel Tube
PREFORMED PILES
<100 KN
300-600
a
?
SCALE OF LOAD
(STRUCTURAL)
100-300
BEARING TYPE
?
?
AUGERED PILES
MICROPILES
BORED PILES
STEEL H PILES
SPUN PILES
PSC PILES
600-1100
a
?
a
?
1100-2000
2000-5000
5000-10000
a
?
a
?
a
?
<5m
a
?
a
?
>10000
a
?
5-10m
a
?
a
?
10-20m
20-30m
30-60m
MAINLY FRICTION
a
?
a
?
a
?
a
?
a
?
a
?
a
?
a
?
a
?
a
?
a
?
a
?
LIMESTON FORMATION
a
?
a
?
M. STIFF SPT = 4 - 15
V. STIFF SPT = 15 - 32
a
?
a
?
M. DENSE SPT = 10 - 30
a
?
DENSE SPT = 30 - 50
a
?
a
?
a
?
?
a
a
?
TYPE OF
BEARING
LAYER
GEOTECHNICAL
RC PILES
BAKAU PILES
DESIGN
CONSIDERATIONS
COHESIVE SOIL
COHESIVELESS SOIL
S < 100 mm
100-1000mm
a
?
a
?
a
?
1000-3000mm
>3000mm
a
x
TIMPER PILES
TYPE OF PILE
JACKED PILES
LEGEND :
a
?
a
?
0.5-2.5
0.3-2.0
a
a
a
?
1-2
0.5-2
1.5-3
1-2.5
1.0-3.5
a
?
Site Visit
Things To Look For
z Accessibility & Constraints of Site
z Adjacent
Structures/Slopes, Rivers,
Boulders, etc
z Adjacent
z Confirm
z Any
Ground Level
Hard Material Level
CROSS SECTION
BH
BH
BH
Seepage
Water Table
EXISTING
GROUND
LEVEL
C1, 1
2
,
2
er C
T
y
W
a
d
he
yL
c
e
r
y
e
P
Cla
C3, 3
Pile Design
PILE DESIGN
Allowable Pile Capacity is the minimum of :
1) Allowable Structural Capacity
2) Allowable Geotechnical Capacity
a. Negative Skin Friction
b. Settlement Control
PILE DESIGN
Structural consideration
Durability assessment
Concrete Pile
Qall = 0.25 x fcu x Ac
capacity
fcu = characteristic strength
of concrete
fs = yield strength of steel
Steel Pile
Qall = 0.3 x fy x As
Collection of SI Data
50
100
150
200
250
300
350
400
Depth (m)
6
8
Upper Bound
10
12
6
14
16
8
18
20
Lower
Bound
22
24
Design Line
(Moderately
Conservative)
10
26
12
0
50
100
150
200
250
300
350
400
Collection of SI Data
50
100
150
200
250
300
350
400
100
150
200
250
300
350
400
2
4
Upper Bound
10
12
6
14
Depth (m)
Depth (m)
50
10
12
6
14
16
16
18
Lower
Bound
20
Design Line
18
Upper Bound
20
10
22
22
Lower
Bound
10
Design Line
24
24
26
12
0
50
100
150
200
250
300
350
400
26
12
0
50
100
150
200
250
300
350
400
Moderately Conservative
Design Parameters
z Eurocode
7 definition:
Moderately Conservative
Design Parameters
z If
Extracted from Prof. Brian Simpsons Course Note (2-day Course on Eurocode 7 Geotechnical Design to EC7, 13-14
November 2007, PJ, Malaysia).
compressibility
z Different degree of
Load
Factor of Safety is
(FOS) required for
qsmob
qbmob
5mm
Settlement
3.0
Qs = skin friction
Qb = end bearing
Qbu
Qu = .sus.As + sub.Nc.Ab
Qu = Ultimate bearing capacity of the pile
a = adhesion factor (see next slide)
sus = average undrained shear strength for shaft
As = surface area of shaft
sub = undrained shear strength at pile base
Nc = bearing capacity factor (taken as 9.0)
Ab = cross sectional area of pile base
Preferred
Design Line
0.8
0.6
C/Su
0.4
Adhesion
Factor
0.2
0
25
50
75
100
Su (kN/m2)
125
150
175
Meyerhof
Fukuoka
SPT N
fsu=2.5N
(kPa)
su =
(0.1+0.15N)*50
(kPa)
fsu=.su
(kPa)
2.5
12.5
12.5
12.5
42.5
0.7
29.75
10
25
80
0.52
41.6
15
37.5
117.5
0.4
47
20
50
155
0.33
51.15
30
75
230
0.3
69
40
100
305
0.3
91.5
fsu
(kPa)
70
60
50
40
30
20
10
0
0
10
15
20
25
30
SPT N
Meyerhof
Fukuoka
35
40
45
(kPa)
100
100
200
200
300
300
400
400
500
500
00
00
44
44
Depth (m)
Qsu
Qbu
Qsu + Qbu
88
12
12
88
Qsu + Qbu
2.0
Qsu + Qbu
1.5
3.0
12
12
16
16
16
16
20
20
20
20
00
200
200
400
400
600
600
z Base
Source
Limestone
Authors
Sandstone
0.10quc
Thorne (1977)
Shale
0.05quc
Thorne (1977)
Granite
Where:
RQD =
quc
=
fcu
=
Hf
OGL
Fill
0
s
Clay
3 Month
NO NSF
Design Considerations
Skin Friction
Load
Original Ground Level
Friction Pile
Excessive Settlement
Soil Settlement
Load
Load
Load
Negative
Positive Skin
Friction
Skin
Friction Pile
Friction
Excessive
Settlement
End-Bearing
Pile
Crushing of
Pile!!!
WARNING:
Effect of NSF
Effect of NSF
Filling
z Carry
Out Surcharging
z Sleeve
z Slip
Coating
z Reserve
z Allow
Clay
OGL
Sand
OGL
Qsu
Clay
Qneg
Qsu
Sand
Sand
Qba
Qba
Settlement (mm)
60
50
40
30
20
10
10
15
Settlement Curves &
Axial Compression Force
20
14 May 98
15 May 98
18 May 98
21 May 98
04 Jun 98
09 Jun 98
19 Jun 98
02 Jul 98
13 Jul 98
25
30
35
40
Borehole
BH-1
BH-2
Datum = 36.300m
Maximum
axial load
Qult
FOS
(Qneg + etc)
Qult
FOS
Consolidation
Settlement
pi =
1 0 qn B
Eu
Where
pi = average immediate settlement
qn= pressure at base of equivalent raft
B = width of the equivalent raft
Eu= deformation modulus
1, 0= influence factors for pile group width, B at depth D
below ground surface
1
0
No risk of excessive
settlement
PILE INSTALLATION
METHODS
Diesel / Hydraulic / Drop Hammer
Driving
Jacked-In
Prebore Then Drive
Prebore Then Jacked In
Cast-In-Situ Pile
Hydraulic Hammer
Driving
Jacked-In
Piling
Cast
-In-Situ
Cast-In-Situ
Piles
((Micropiles)
Micropiles)
Types of Piles
TYPES OF PILES
Treated Timber
Piles
Bakau Piles
R.C. Square Piles
Pre-Stressed
Concrete Spun
Piles
Steel Piles
Boredpiles
Micropiles
Caisson Piles
: 150mm to 400mm
zLengths : 3m, 6m, 9m and 12m
zStructural Capacity : 25Ton to 185Ton
zMaterial : Grade 40MPa Concrete
zJoints: Welded
zInstallation Method :
Drop Hammer
Jack-In
RC
Square
Piles
Pile Marking
Pile Lifting
Pile
Positioning
Pile Joining
Considerations in Using RC
Square Piles
Pile Quality
Pile Handling Stresses
Driving Stresses
Tensile Stresses
Lateral Loads
Jointing
: 250mm to 1000mm
zLengths
zStructural
zMaterial
zJoints:
Welded
zInstallation
Method :
Drop Hammer
Jack-In
Spun Piles
Steel H Piles
zSize
: 200mm to 400m
zLengths : 6m and 12m
zStructural Capacity : 40Ton to 1,000Ton
zMaterial : 250N/mm2 to 410N/mm2 Steel
zJoints: Welded
zInstallation Method :
Hydraulic Hammer
Jack-In
Steel H
Piles
OverDriving
of Steel Piles
: 450mm to 2m
(Up to 3.0m for special case)
z Lengths : Varies
z Structural Capacity : 80Ton to 2,300Tons
z Concrete Grade : 20MPa to 35MPa (Tremie)
z Joints : None
z Installation Method : Drill then Cast-In-Situ
Drilling
Borepile Construction
Advance Drilling
Borepile Construction
Borepile Construction
Drill to Bedrock
Borepile Construction
Lower
Reinforcement
Cage
Borepile Construction
Lower Tremie
Chute
Borepile Construction
Pour Tremie
Concrete
Borepile Construction
Completed
Borepile
Borepile Construction
BG22
Rock Reamer
Cleaning Bucket
Rock Auger
Rock Chisel
Harden Steel
DRILLING EQUIPMENT
Cleaning
bucket
Coring
bucket
Soil auger
BENTONITE PLANT
Desanding
Machine
Water
Tank
Mixer
Slurry
Tank
Drilling
Lower
Reinforcement
Place
Tremie
Concrete
Completed Boredpile
Borepile Cosiderations
Borepile Base Difficult to Clean
Bulging / Necking
Collapse of Sidewall
Dispute on Level of Weathered Rock
Micropiles
zSize
zLengths
: Varies
zStructural
zMaterial
zJoints:
None
zInstallation
Method :
Cast-In-Situ
Piles
(Micropiles)
H-Section Shoe
Do more harm in
inclined rock surface!
Piling Supervision
Uniform Building By
Law (UBBL)1984
PILING SUPERVISION
Ensure That Piles Are Stacked Properly
Ensure that Piles are Vertical During Driving
Keep Proper Piling Records
Ensure Correct Pile Types and Sizes are Used
Ensure that Pile Joints are Properly Welded with
NO GAPS
Ensure Use of Correct Hammer Weights and Drop
Heights
PILING SUPERVISION
(Contd)
Ensure that Proper Types of Pile Shoes are Used.
Check Pile Quality
Ensure that the Piles are Driven to the Required
Lengths
Monitor Pile Driving
FAILURE OF PILING
SUPERVISION
Failing to Provide Proper Supervision
WILL Result in
Higher Instances of Pile Damage
& Wastage
Pile Damage
Damage to
RC Pile
Head
Damage to
RC Piles
Piling Problems
Results in
High Rates of Pile Damage
High Bending Stresses
Seriously damaged
pile due to severe
driving stress in soft
ground (tension)
Problems of
defective pile head
& overdriving!
Cracks&
fractured
Sinkholes caused by
installation methoddewatering?
Results in
Negative Skin Friction (NSF) & Crushing of Pile Due
to High Compressive Stresses
Uneven Settlements
Solution #1
Use Oslo Point Shoe To Minimize Pile Damage
Pile
Joint
Extension Pile
First Contact
B/W Toe and
Inclined Rock
Continue
Sliding of
Toe
Solution #2
Detect Cavities through Cavity Probing then
perform Compaction Grouting
Presence of Cavity
Pile Sitting on
Limestone
with Cavity
Application of
Building Load
Application of
Building Load
Roof of Cavity
starts to Crack
Building Collapse
Pile Plunges !
Collapse of
Cavity Roof
Solution #3
Carry out analyses to check the settlement
compatibility if different piling system is adopted
Cracks!!
Renovation:
Construct
Extensions
Original House
on Piles
Piling in Progress
No Settlement
Soft
Layer
Piles
transfer
Load to
Hard
Layer
No
pile
Settlement
Hard Layer
SPT>50
Piling in Progress
Soft
Layer
Hard Layer
SPT>50
Piling in Progress
Soft
Layer
Soft!
Load
transferred to
Soft Layer,
Extension
still Settles
Hard Layer
SPT>50
Cracks at Extension
Solution #4
-Strip footings / Raft
-Floating Piles
Foundation for
Low Rise Buildings (Soil Settlement)
Settlement
Exposed Pile
Conceptual Design of
FOUNDATION SYSTEM
1.
Fill
Strip / Raft
System
25-30m
Soft Clay
Stiff
Stratum
Hard Layer
Comparison
Building on Piles
Fill
25-30m
Soft Clay
Strip
System
Stiff
Stratum
Hard Layer
Fill
25-30m
Soft Clay
Strip
System
Stiff
Stratum
Hard Layer
Advantages of
Floating Piles System
1. Cost Effective.
2. No Downdrag problems on the
Piles.
3. Insignificant Differential
Settlement between Buildings and
Platform.
Bandar Botanic
Solution #5
-Modifications to test set-up
-Change of pile installation method
-Adequate soil plug to prevent toe softening
Testing Set-up
z Long
used
z Case
histories:
ERRATIC results
Reference: Weele (1993)
Ref: A.F.
van Weele,
1993
Tested
using
anchor
piles
Tested
using
kentledge
1100kN
Approx. 2
2100kN
times
smaller
using
reaction
piles!
Reaction
piles
Zone of
interaction
with test
pile
Test
pile
Testing Set-up
z Latest
Testing Set-up
z ASTM
D1143
z Potential
hydraulic/basal heave
failure resulting in lower soil strength
z Effect
behaviour COMPLICATED!
SAND
UPHEAVAL
AFTER 3
HRS
Pressure from
Soil + Water
Pressure from
Soil + Water
>
Pressure from
Drilling Fluid
z Probable
After 32 days
After 94 days
z Recommendations:
Open-ended spun pile or steel pipe pile with
Result for
Empty
Casing
Result for
Concreted
Pile
Pile performs
satisfactorily
within
acceptable
settlement
limits!!!
The Pile is
Stiffer after
Concreting !!
Larger Residual
Settlement due to
Disturbance from
RCD work !!
Piles founded in
SOIL: PL/AE
Piles founded in
ROCK: 3/4 PL/AE
Result for
Concreted Pile
Settlement
is in
accordance
to
prediction!
!
Depends on:
E Elastic Modulus of Pile Material
A Cross-sectional Area of Pile
L Pile Length
Pile Size
Pile Material (e.g. steel, concrete, etc.)
Pile Length
z Unrealistic
Myths in Piling
MYTHS IN PILING #1
Myth:
Dynamic Formulae such as Hileys Formula
Tells us the Capacity of the Pile
Truth:
Pile Capacity can only be verified by using:
(i) Maintained (Static) Load Tests
(ii)Pile Dynamic Analyser (PDA) Tests
MYTHS IN PILING #2
Myth:
Pile Achieves Capacity When It is Set.
Truth:
Pile May Only Set on Intermediate Hard
Layer BUT May Still Not Achieve Required
Capacity within Allowable Settlement.
MYTHS IN PILING #3
Myth:
Pile settlement at 2 times working load must
be less than certain magnitude (e.g. 38mm)
Truth:
Pile designed to Factor of Safety of 2.0.
Therefore, at 2 times working load:
Pile expected to fail unless capacity underpredicted significantly
CASE HISTORIES
z Case
z Case
2: Distresses at houses
CASE HISTORY 1
Distortion & Distresses on 40
Single/ 70 Double Storey Houses
z Max.
Distresses on Structures
Void
70
Piling Contractor A
Offset 36.2m
R e d u c e d L e v e l (m )
60
Building
Platform
Offset 13.1m
Offset 13.1m
Offset 13.1m
Original
Ground Profile
50
N=34
?
N=30
40
? ?
N=5
30
N=29
?
?
N=25
N=40
20
0
40000
80000
120000
Coordinate-X (mm)
Filled ground
Original Ground
Hard Stratum
Borehole
Pile Toe
Pile Toe of Additional
Piles
160000
200000
Piling
Contractor A
80
Piling Contractor B
R e d u c e d L e v e l (m )
70
Offset 9.1m
Offset 9.1m
60
N=34
50
Building Platform
N=28
N=41
?
?
N=30
40
N=5
N=29
30
0
40000
80000
120000
Coordinate-X (mm)
Filled ground
Original Ground
Hard Stratum
Borehole
Pile Toe
Pile Toe of Additional
Piles
160000
200000
Prevention Measures
z Design:
Consider downdrag in foundation design
Alternative strip system
z Construction:
Proper QA/QC
Supervision
CASE HISTORY 2
Distresses on 12 Double Storey
Houses & 42 Townhouses
z Filled
Sagging
Ground
Floor Slab
e > Vc
V <V
PILECAP
PILE
BLOCK 2
Temporary
earth drain
BLOCK 1
Prevention Measures
z Planning:
Proper building layout planning to suit terrain
SUMMARY
z Importance
of Preliminary Study
z Understanding
z Carry
z Selection
z Pile
of Suitable Pile
Design Concepts
SUMMARY
z Importance
of Piling Supervision
z Typical
z Present