ACCM Tutorial 1

05/08/14
1. High light the features of Bar Chart.
2. Draw a bar chart for the sequence of activities indicated in the table below;
Sr. No. Activity
Description
Duration
Sequence
in days
1
A
Site Clearence
02
First activity
2
B
Lay out for the Building
01
Follows activity A
3
C
Excavation for foundation
6
Follows activity B
4
D
PCC 1:5:10 for bed concrete
4
Can
commence
after 4 days of
progress of C
5
E
Un coursed rubble (UCR) masonry
8
Follows activity D
in Foundation
6
F
PCC 1:2:4 in plinth
3
Follows activity E
7
G
First class brick masonry in super
15
Follows activity F
structure.
8
H
Providing stone slab window sills
2
Can
commence
after 6 days of
progress of activity
G
3. Detail the sequence of activities for the Bar Chart shown below;
A SIMPLE BAR CHART

A
0

6
DURATION IN DAYS

10

12

4.

Number the events in the network shown below;

F
C
E

5. Write down the sequence of activities in the network shown above.


6. Calculate the estimated time for the activities of the network in Fig 2 from the data
given below;
Activity
A
B
C
D
E
F

Optimistic to
5
3
4
2
5
3

Time estimates in days


Most Likely tM
7
4
7
3
7
5

Pessimistic tP
10
7
10
5
9
8