1. High light the features of Bar Chart.
2. Draw a bar chart for the sequence of activities indicated in the table below;
Sr. No. Activity
Description
Duration
Sequence
in days
1
A
Site Clearence
02
First activity
2
B
Lay out for the Building
01
Follows activity A
3
C
Excavation for foundation
6
Follows activity B
4
D
PCC 1:5:10 for bed concrete
4
Can
commence
after 4 days of
progress of C
5
E
Un coursed rubble (UCR) masonry
8
Follows activity D
in Foundation
6
F
PCC 1:2:4 in plinth
3
Follows activity E
7
G
First class brick masonry in super
15
Follows activity F
structure.
8
H
Providing stone slab window sills
2
Can
commence
after 6 days of
progress of activity
G
3. Detail the sequence of activities for the Bar Chart shown below;
A SIMPLE BAR CHART
A
0
6
DURATION IN DAYS
10
12
4.
F
C
E
Optimistic to
5
3
4
2
5
3
Pessimistic tP
10
7
10
5
9
8