Professional Documents
Culture Documents
Barring Gear
Barring Gear
PROCEDURE
ISSUE
REV NO:0
NO:01
Page 1 of 30
DATE OF ISSUE:
Concurred BY
PREPARED
BY
CHECKED BY
REVIEWED
BY
APPROVED
BY
ISSUED BY
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
REVISION LOG
Revision Details
Issue No.
Rev.No.
Details
Date
Page
No.
Preparation Details
Prepared by
Concurred by
Checked by
Approved by
Reviewed by
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
ISSUE
REV NO:0
NO:01
Page 5 of 30
DATE OF ISSUE:
CONTENTS
SL
TITLE CLAUSE
PAGE NO.
NO.
Cover sheet
Revision log
Contents
1.
Purpose
1
3
5
6
Pre-requisites
2.
3.
4.
5.
6.
7.
8.
9.
10.
8
14
15
16
16
28
28
30
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
1.0
Purpose:
The purpose of this procedure is to provide guidelines for
commissioning of the barring gear system.
2.0
Pre-requisites:
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
General method
Check the completion of erection as per the design flow sheets and
drawings. Check the completion of equipments and supports in all oil pipe
systems.
Ensure that at least one oil Vapour exhauster fan is running and the
butterfly valves in the bearing and MOT are adjusted for having
negative pressure in the bearings (approx 10-40 mm WLC).
Ensure there is no leakage and the drain oil flow in each bearing is
o.k.
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
Ensure that the Lub oil duplex filter elements are not in choked
condition.
Start JOP I and adjust the JOP header pressure to 150 kg/cm2.
Install the Dial gauges with Magnetic Base 0-10 mm for measuring
each journal lift.
Adjust the lift of rotor in each bearing (between 0.08 to 0.1 mm)
with dial gauge.
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
Ensure that one seal oil vacuum pump and one generator bearing
chamber exhauster fan is running.
Ensure that there is vacuum in the seal oil tank.
Ensure that seal oil filter elements are installed in the filters.
Ensure that oil is taken in seal oil system and there is normal level
in SOT and IOT.
Run Seal Oil Pump I and ensure proper operation of CPR (Constant
Pressure Regulator) and DPR-I (Differential Pressure Regulator).
Ensure proper operation of the second DPR-II and ensure change
over of CPR.
Adjust the ring relief oil flow.
Ensure that the SOT level is maintained by the SOT Float valve.
Run other AC seal oil and DC seal oil pump one by one and adjust
the CPR of the respective pump.
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
Ensure that the DPR is functioning o.k. with any one seal oil pump.
room.
AOP I/II
DC EOP
JOP I/II
OVE I/II
SOP I/II
DC SOP
SEAL OIL VAC PUMP I/II
GEN BEARING CHAMBER EXHAUSTE I/II
BARRING GEAR VALVE WITH INTRLOCK OF LUB OIL
HEADER PRESSURE
OIL TEMPERATURE CONTROL VALVE
TAPP-3&4 COMMISSIONING
PROCEDURE
ISSUE
REV NO:0
NO:01
Page 12 of 30
DATE OF ISSUE:
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
4.0
Design intents:
TAPP-3&4 COMMISSIONING
PROCEDURE
5.0
JOP pressure
Rotor lift
no.
(Kg/Cm2)
(mm)-
1
2
3
4
5
6
7
6.0
approx.
0.07
0.07
0.07
0.07
0.07
0.07
0.07
Work plan:
a
TAPP-3&4 COMMISSIONING
PROCEDURE
7.0
ISSUE
REV NO:0
NO:01
Page 16 of 30
DATE OF ISSUE:
Brg
no.
Throttle
lift
adjusted
l.o.
Press.
Bef.
throttle
l.o.
Press.
Aft.
Throttle
DP across
throttle
Lub oil
flow
Remarks
1
2
3
4
5
6
7
Mot
inj.
Brg
no.
1
2
3
4
5
6
7
Mot
inj.
Throttle
lift
adjusted
l.o.
Press.
Bef.
throttle
l.o.
Press.
Aft.
Throttle
DP across
throttle
Lub oil
flow
Remarks
TAPP-3&4 COMMISSIONING
PROCEDURE
JOP pressure
(Kg/Cm2)
Rotor lift
(mm)
PARAMETERS
1.
Speed
2.
AOP dish pr
3.
4.
5.
6.
L.o.temp bef
cooler
L.o.temp aft
cooler
7.
MOT level
8.
Shaft I vib
9.
Shaft 2 vib
10.
Shaft 3 vib
11.
Shaft 4 vib
STAND
STILL
BARRING
GEAR
REMARKS
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
12.
Shaft 7 vib
13.
Brg 1 vib
14.
Brg 2 vib
15.
Brg 3 vib
16.
Brg 4 vib
17.
Brg 5 vib
18.
Brg 6 vib
19.
Brg 7 vib
20.
Brg 1 temp.
21.
Brg 2 temp.
22.
Brg 3 temp.
23.
Brg 4 temp.
24.
Brg 5 temp.
25.
Brg 6 temp.
26.
Brg 7 temp.
27.
28.
A.S.
29.
Diff. Exp
30.
SOP (TE)
31.
SOP (EE)
32.
SO temp
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
DESCRIPTION
RAD BRG HP F TOP LH
RAD BRG HP F TOP LH
RAD BRG HP F TOP LH
RAD BRG HP F TOP RH
RAD BRG HP F TOP RH
RAD BRG HP F TOP RH
RAD BRG HP F BOT LH
RAD BRG HP F BOT LH
RAD BRG HP F BOT LH
RAD BRG HP F BOT HR
RAD BRG HP F BOT HR
RAD BRG HP F BOT HR
AXL BRG FRONT LH
AXL BRG FRONT LH
AXL BRG FRONT LH
AXL BRG FRONT RH
AXL BRG FRONT RH
AXL BRG FRONT RH
AXL BRG REAR LH
AXL BRG REAR LH
AXL BRG REAR LH
AXL BRG REAR RH
AXL BRG REAR RH
AXL BRG REAR RH
AXIAL SHIFT
AXIAL SHIFT
AXIAL SHIFT
BRG VIBR HP FRNTPED
REL SHAFT VIBR HP F
ABS SHAFT VIBR HP F
(MAD11CY021&041)
RAD BRG HP R BOT RH
RAD BRG HP R BOT RH
RAD BRG HP R BOT RH
RAD BRG HP R BOT RH
RAD BRG HP R BOT RH
RAD BRG HP R BOT RH
BRG VIBR HP R-PED
REL SHAFT VIB HP R
ABS SHAFT VIBR HP R
OK/NOT OK
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAD13CT014A
MAD13CT014B
MAD13CT014C
MAD13CT018A
MAD13CT018B
MAD13CT018C
MAD13CY021
MAD13CY041
MAD13FY901
MAD14CT014A
MAD14CT014B
MAD14CT014C
MAD14CT018A
MAD14CT018B
MAD14CT018C
MAD14CY005
MAD14CY021
MAD14CY041
MAD14FY901
MAV10CL001
MAV10CL002
MAV10CL006
MAV10CL007
MAV10CL008
MAV10CL521
MAV21CP001
MAV21CP010
MAV21CP011
MAV21CP012
MAV21CP521
MAV22CP501
MAV23CP501
MAV24CP501
MAV31CP501
MAV32CP501
MAV35CP001
MAV35CP011
MAV35CP016
MAV41CP501
MAV41CP521
(MAD12CY021&041)
RAD BRG LP1 R BOTRH
RAD BRG LP1 R BOTRH
RAD BRG LP1 R BOTRH
RAD BRG LP1 R BOTRH
RAD BRG LP1 R BOTRH
RAD BRG LP1 R BOTRH
BRG VIBR LP 1 R -PED
REL SHAFT VIB LP1 R
ABS SHAFT VIBR LP1 R
(MAD13CY021&CY041)
RAD BRG LP2 R BOTRH
RAD BRG LP2 R BOTRH
RAD BRG LP2 R BOTRH
RAD BRG LP2 R BOTRH
RAD BRG LP2 R BOTRH
RAD BRG LP2 R BOTRH
ABS EXP LP2 CASE R
BRG VIBR LP2 R-PED
REL SHAFT VIB LP2 R
ABS SHAFT VIBR LP2 R
(MAD14CY021&041)
LEVEL IN MAIN OIL TANK
LEVEL IN MAIN OIL TANK
LEVEL IN MAIN OIL TANK
LEVEL IN MAIN OIL TANK
LEVEL IN MAIN OIL TANK
LEVEL IN MAIN OIL TANK
HYD OIL HEADER
HYD OIL HEADER
HYD OIL HEADER
HYD OIL HEADER
SUC LINE MOP
HYD OIL AUX OIL PMP1
HYD OIL AUX OIL PMP2
LUB OIL EMERG OIL PUMP
JACK OIL AFT PUMP1
JACK OIL AFT PUMP2
JACK OIL PRESSURE
JACK OIL PRESSURE
DP FILTR JACK OIL
LUBE OIL BEF COOLER
LUBE OIL BEH COOLER
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAV41CT001A
MAV41CT001B
MAV41CT501
MAV42CP001
MAV42CP011
MAV42CP012
MAV42CP013
MAV42CP014
MAV42CP015
MAV42CP016
MAV42CP017
MAV42CP018
MAV42CP412
MAV42CP413
MAV42CP414
MAV42CP417
MAV42CP418
MAV42CP421
MAV42CP422
MAV42CT001A
MAV42CT001B
MAV42CT501
MAV44CP411
MAV44CP412
MAV44CP413
MAV44CP414
MAV44CP415
MAV44CP416
MAV51CP501
MAV66CP501
MAV66CP503
MAV66CP507
MAV66CP508
MAV66CP511
MAV66CP512
MAV67CP501
MAV67CP503
MAV67CP506
MAV71CT501
MAV71CT502
MAV71CT504
MAV71CT506
MAV71CT511
MAV72CT501
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAV72CT502
MAV91CF516
MAV91CL001
MAV91CL012
MAV91CL521
MAV91CL522
MAV91CL523
MAV91CP011
MAV91CP501
MAV91CP502
MAX16CP011
MAX16CP021
MAX16CP501
MAX16CP502
MAX18CP501
MAX18CP502
MAX31CP001
MAX31CP511
MAX31CP512
MAX31CP516
MAX31CP517
MAX31CP541
MAX31CP542
MAX31CP543
MAX31CP544
MAX31CP545
MAX31CP546
MAX31CP547
MAX31CP548
MAX32CP011
MAX32CP081
MAX32CP511
MAX32CP513
MAX32CP514
MAX41CP001
MAX41CP501
MAX41CP521
MAX41CP522
MAX42CP011
MAX42CP012
MAX42CP013
MAX42CP014
MAX42CP501
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAX42CP502
MAX42CP503
MAX42CP504
MAX42CP511
MAX42CP512
MAX42CP513
MAX42CP514
MAX42CP517
MAX42CP518
MAX42CP519
MAX42CP520
MAX42CP531
MAX42CP532
MAX42CP541
MAX42CP542
MAX42CP543
MAX42CP544
MAX44CP501
MAX45CG001A
MAX45CG001K
MAX45CG001T
MAX45CG002A
MAX45CG002K
MAX45CG002T
MAX45CP001
MAX45CP006
MAX45CP041
MAX45CP042
MAX45CP043
MAX45CP501
MAX46CG001A
MAX46CG001B
MAX46CP001
MAX46CP002
MAX46CP501
MAX46CP502
MAX47CG001A
MAX47CG001B
MAX47CG001C
MAX47CG001D
MAX47CG001F
MAX47CP001
MAX47CP501
MAX48CP201
LP CONTROL FLUID
LP CONTROL FLUID
LP CONTROL FLUID
CNT FLD INJ WTR V 1
CNT FLD INJ WTR V 2
CNT FLD INJ WTR V 3
CNT FLD INJ WTR V 4
CNT FLD INJ WTR V 5
CNT FLD INJ WTR V 6
CNT FLD INJ WTR V 7
CNT FLD INJ WTR V 8
ACCUM 1 CNT CUB
ACCUM 2 CNT CUB
ACCUM1 BYP CNT CUB 1
ACCUM2 BYP CNT CUB 1
ACCUM1 BYP CNT CUB 2
ACCUM2 BYP CNT CUB 2
PRIMARY FLUID
EHYD CONV 1 TURB GOV
EHYD CONV 1 TURB GOV
EHYD CONV 1 TURB GOV
EHYD CONV 2 TURB GOV
EHYD CONV 2 TURB GOV
EHYD CONV 2 TURB GOV
SEC FLD HP-GOVVALVE
SEC FLD HP-GOVVALVE
SEC FLD HP-GOVVALVE
SEC FLD HP-GOVVALVE
SEC FLD HP-GOVVALVE
SEC FLD HP-GOVVALVE
SPEED CHANGER
SPEED CHANGER
SEC AUX FLUID 1
SEC AUX FLUID 2
SEC AUX FLUID 1
SEC AUX FLUID 2
STARTING DEVICE
STARTING DEVICE
STARTING DEVICE
STARTING DEVICE
STARTING DEVICE
START-UP FLUID
START-UP FLUID
START-UP AUX FLUID
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAX48CP202
MAX48CP501
MAX51CG005C
MAX51CG005E
MAX51CG006C
MAX51CG006E
MAX51CG205C
MAX51CG205E
MAX51CG206C
MAX51CG206E
MAX51CG211B
MAX51CG211C
MAX51CP001
MAX51CP013
MAX51CP016
MAX51CP017
MAX51CP018
MAX51CP021
MAX51CP022
MAX51CP023
MAX51CP209
MAX51CP210
MAX51CP211
MAX51CP212
MAX51CP221
MAX51CP222
MAX51CP223
MAX51CP226
MAX51CP227
MAX51CP228
MAX51CP501
MAX51CP522
MAX51CP523
MAX51CP527
MAX51CP528
MAX52CG005C
MAX52CG005E
MAX52CP211
MAX52CP212
MAX52CP213
MAX52CP214
MAX52CP501
MAX53CG001A
MAX53CG001T
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MAX53CG002A
MAX53CG002T
MAX53CG003A
MAX53CG003T
MAX53CG004A
MAX53CG004T
MAX53CP031
MAX53CP032
MAX53CP033
MAX53CP034
MAX53CP035
MAX53CP036
MAX53CP037
MAX53CP038
MAX53CP501
MAX53CP502
MAX53CP503
MAX53CP504
MAX61CP215
MAX62CG001B
MAX62CG001C
MAX62CP211
MAX62CP212
MAX62CP213
MAX62CP501
MAX89CL001
MAX89CL015
MAX89CL521
MAY01EP001A
MAY01EP001B
MAY01EP001C
MAY01EP001D
MAY01EP001E
MAY01EP001F
MAY10CG001
MAY10CG001C
MAY10CG001E
MAY10CG002
MAY10CG002C
MAY10CG002E
MKA02FE001A
MKA02FE001A
MKA02FE001B
MKA02FE001C
TAPP-3&4 COMMISSIONING
PROCEDURE
COMMISSIONING PROCEDURE FOR
BARRING GEAR SYSTEM
MYA01CS011
MYA01CS012
MYA01CS013
MYA01CS014
MYA01DS001A
MYA01DS001B
MYA01FS001A
MYA01FS001B
MYA01FS001C
MYA01FS002
MYA01GS005
PGB20CT001A
PGB20CT001B
PGB21CT501
PGB21CT502
PGB22CT501
PGB22CT502
PGB23CT001A
PGB23CT001B
8.0
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
TURBINE SPEED
LAMP TEST
PUSH BUTTON SW
CLG WTR BEF OIL CLR
CLG WTR BEF OIL CLR
CLG WTR BEF OIL CLR1
CLG WTR BEH OILCLR1
CLG WTR BEF OIL CLR2
CLG WTR BEH OIL CLR2
CLGWTR BEH OILCLR
CLGWTR BEH OILCLR
Reference
TAPP-3&4 COMMISSIONING
PROCEDURE
ISSUE
REV NO:0
NO:01
Page 29 of 30
DATE OF ISSUE:
APPENDIX
VERIFICATION TABLE
COMMISSIONING PROCEDURE FOR BARRING GEAR SYSTEM
SL.
NO
ACTIVITY
VERIFIED
ACCEPTANCE
CRITERIA
VERIFYING
AGENCY
Pl refer
4.0
Pl refer 4.0
INSPECTION
WITNESS
FUNCTION
-AL TEST
RESULT
VERIFICA
-TION
GENERAL
REMARKS
TAPP-3&4 COMMISSIONING
PROCEDURE
ISSUE
REV NO:0
NO:01
Page 30 of 30
DATE OF ISSUE:
ANNEXURE
NUCLEAR POWER CORPORATION OF INDIA LIMITED
(A Govt. of India Enterprise)
TARAPUR ATOMIC POWER PROJECT3&4
COMMISSIONING PROCEDURE ACCEPTANCE NOTE
Contractor commissioning procedure number ___________________________ for
the commissioning of BARRING GEAR SYSTEM submitted by BHEL under the
contract number ______________ is received and found conforming to the
requirement of NPCIL specifications & Norms & hence accepted.
_____________________________________
Approved by:
NPC Design
Group
SIGNATURE