You are on page 1of 22

TOPIC 2 : ANALYSIS OF STEADY

FLOW IN PIPELINE
2.1 Introduction and general approach
2.2 Incompressible flow through pipes
2.3 Flow through pipes in series
2.4 Flow through pipes in parallel
2.5 Flow through branching pipes
2.6 Pipe networks
2.7 Quantity Balance Method

9/9/2014

LECTURE 2.7
ANALYSIS OF STEADY FLOW
IN PIPELINE

Quantity Balance Method

9/9/2014

HARDY CROSS METHOD


(QUANTITY BALANCE METHOD)
Can be used when the heads,h at various points in a

pipe network are known


Necessary to calculate the quantities flowing in each
pipe
An estimate is made of the flow rate,Q for each pipe
Head, h between the junctions at each end of the
pipe is calculated for each pipe from the difference
of head, h
Resistance coefficient K, using equation

9/9/2014

Figure 2.8 head at D has been overestimated by an

amount h relative h to the head at A, B and C


Values of QAD and QBD will be too small
Value of QDC will be too great
Differentiating the equation

Where K= Resistant coefficient (s2m5)


Q= Volumetric flow rate (m3/s)
9/9/2014

Therefore

Since

9/9/2014

The original estimate of the final D is reduced by

an amount h, the flows in AD and CD will be


increased to

&
7

9/9/2014

If the flows are correct, inflow and outflow at D

will balance:

9/9/2014

If hAD , hBD and hDC

are the assumed losses


of head in pipes AD,
BD and DC used to
calculate QAD, QBD,
and QCD

9/9/2014

Substituting the previous equation,

10

9/9/2014

Since Darcy Darcys s equation is used, the equation can be

written as

Where,

= Algebraic sum of the flows towards


the junction
11

9/9/2014

When h has been calculated, the new value of

the head at D can be used to determine revised


values of QAD, QBD, and QDC
The process is repeated until Q has been reduced
to a negligible quantity
Example 2.6 shows the application of this method
to the three reservoir problem

12

9/9/2014

EXAMPLE 2.6

13

9/9/2014

SOLUTION FOR EXAMPLE 2.6


The following equations will be used

14

9/9/2014

Procedure

i. Assume the head at junction D, HD


ii. Calculate the head loss between AD, BD and CD
iii. Calculate the value of K for each pipe
iv. With assumed h values and the calculated K
values, compute Q values through the equation
h = KQ2 for each pipe

15

9/9/2014

The correction for the head can be obtained using the

following equation,

Note: For this example, the assumed head at junction D

is 50m
16

9/9/2014

1ST TRIAL
X10-3

17

9/9/2014

2ND TRIAL

hnew = hold + h
X10-3

18

9/9/2014

3RD TRIAL

hnew = hold + h
X10-3
17.687

0.0873

6.29X10-3

2.468X10-3

0m

6.29X10-3
19

9/9/2014

Since the correction has reached zero,

assumed head at junction D is at a elevation


80 17.687
18.057 = 62.3m
61.9m elevation

20

9/9/2014

21

9/9/2014

EXERCISE

22

9/9/2014

You might also like