JOB SAFETY ANALYSIS

Job Title
Location
Leader
Crew List

: Cuttting Anchor chain A-4 from Mini Platform


: Sepanjang Jetty
: Max Polla
: Djoko Susilo, Welder & Riggers.

Date
Work Permit
Hot Work Permit

: 5 January 2008
: YES
: YES

HSE Notes :
PPE Standard : Coverall; Safety Shoes; Safety Hat; Safety Glass; Hand Gloves and Life Jacket.
Issue Hot Work Permit and conduct tool box meeting before commencement of the job.
Working above or on the water and personal transfer by boat, personnel should wear work vest or life jacket if needed.
Communication among personnel in charge should be well maintained.
NO

WORK STEPS
Basic Step & Tool Used

HAZARDS
IDENTIFICATION
How can People
Get Injured.
Use Checklist on Form 2

HAZARDS EFFECT

RISK FACTOR

SAFETY MEASURES &


PREVENTION

RESIDUAL
RISK FACTOR

Type of

Injury,
Worst Case

HE

RF

Assign Responsible Person for Each Action

HE

RF

Work Site preparation

Slip, Squeeze &


Bad Weather

Twisted, Bruised

L2

1. Be aware because the location is slippery


2. Do not hurry.
3. Double check equipment/materials needed.
4.Wind speed < 15 knot & wave , 1meter
5. Perform the work at low tide.

L2

Cutting chain on mini platform


bridge.

Skin contact with flame.


Spark get into eye

Burnt skin
Body injured
Bruised

L
L
L

M
M
L

M4
M4
L2

1. Wear welding glove, face shield and welding


sleeve.
2. Watch body position.
3. Wear safety harness as necessary.
4. Direct cutting flame away from body.

L2

L
L

L
L

L2
L2

Prepared by :

Approved by :

Max Polla.

Joko Susilo

PT Arah Prana - Castle Rigg.

KEI Representative