1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2
1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 30
Site Clearing/Layout
Mobilization
Temporary Facilities
Excavation
Formworks
Footing
CHB Laying
Column
Roof Beam
CHB Laying Pitch
Wall
Roof Framing
Roof Accesories
Electrical Rough-ins
Plumbing Rough-ins
Plastering (Ext. and
Int)
Ground Floor Slab
Painting (Interior)
Downspout and
Catchbasin
Electrical Fixtures
Painting (Exterior)
Clearing and Moving
Out
Gantt Chart
ACTIVITY Week 5 Week 6 Week 7 Week 8
1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3
1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 31
Site Clearing/Layout
Mobilization
Temporary Facilities
Excavation
Formworks
Footing
CHB Laying
Column
Roof Beam
CHB Laying Pitch
Wall
Roof Framing
Roof Accesories
Electrical Rough-ins
Plumbing Rough-ins
Plastering (Ext. and
Int)
Ground Floor Slab
Painting (Interior)
Downspout and
Catchbasin
Electrical Fixtures
Painting (Exterior)
Clearing and Moving
Out
ACTIVITY Week 9 Week 10 Week 11 Week 12
1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2
1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 30
Site Clearing/Layout
Mobilization
Temporary Facilities
Excavation
Formworks
Footing
CHB Laying
Column
Roof Beam
CHB Laying Pitch
Wall
Roof Framing
Roof Accesories
Electrical Rough-ins
Plumbing Rough-ins
Plastering (Ext. and
Int)
Ground Floor Slab
Painting (Interior)
Downspout and
Catchbasin
Electrical Fixtures
Painting (Exterior)
Clearing and Moving
Out