9(27) P&D / 2010


GOVERNMENT OF THE PUNJAB
PLANNING & DEVELOPMENT DEPARTMENT

Dated Lahore the, 3rd March, 2010


To,

The Chief (COORD),


Government of the Punjab,
Planning & Development
Department, Lahore.

Subject: FORMULATION OF DEVELOPMENT PROGRAMME (2010-11) &


MTDF (2010-13)

Kindly refer to Subject cited above.


Planning & Development Department is in the process of Formulation of
Development Programme (2010-11) & MTDF (2010-13). The draft ADP proposal of your sector
required to be submitted by 31-12-2009 which is still awaited. Following scheme is reflected in
ADP 2009-10 and will be ongoing for ADP 2010-11.
Sr.No ADP No. Name of Scheme reflected in ADP 2009-10
1 - PC-II for Planning Support for Approval of Unapproved Schemes included
in ADP 2009-10

You are, therefore, requested to kindly furnish the ADP proposal (2010-11) (Hard
& Soft copy) of your respected sector to this office within two days positively.
The assignment may please be given priority.

(HAMID MAHMOOD)
Assistant Chief (R P)
No. 3(204) RP / P&D / 2009
GOVERNMENT OF THE PUNJAB
PLANNING & DEVELOPMENT DEPARTMENT

Dated Lahore the, 17th February 2010


To,

The Managing Director,


Cholistan Development Authority,
Bahawalpur.

Subject: FORMULATION OF DEVELOPMENT PROGRAMME (2010-11) &


MTDF (2010-13)

Kindly refer to this department letter No.3(204)RP/P&D/2009 dated 22.01.2010,


8-02-2010 respectively on the subject cited above.
Planning & Development Department is in the process of Formulation of
Development Programme (2010-11) & MTDF (2010-13). The draft ADP proposal of your sector
required to be submitted by 31-12-2009 which is still awaited.
You are, therefore, requested to kindly furnish the ADP proposal (2010-11) (Hard
& Soft copy) of your respected sector to this office within two days positively.
The assignment may please be given priority.

( HAMID MAHMOOD )
Assistant Chief (R P)
No. 9(27) P&D / 2010
GOVERNMENT OF THE PUNJAB
PLANNING & DEVELOPMENT DEPARTMENT

Dated Lahore the, 3rd March, 2010


To,

1. The Chief (DERA/R&D), 2 The Chief (IT),


Government of the Punjab, . Government of the Punjab,
Planning & Development Planning & Development
Department, Lahore. Department, Lahore
3. The Additional Secretary (Admn)
Government of the Punjab,
Planning & Development
Department, Lahore.

Subject: FORMULATION OF DEVELOPMENT PROGRAMME (2010-11) &


MTDF (2010-13)

Kindly refer to this department letter No.3(204)RP/P&D/2009 dated 17.02.2010


respectively on the subject cited above.
Planning & Development Department is in the process of Formulation of
Development Programme (2010-11) & MTDF (2010-13). The draft ADP proposal of your sector
required to be submitted by 31-12-2009 which is still awaited. Following schemes are reflected
in ADP 2009-10 and these will be ongoing for ADP 2010-11.
Sr.No ADP No. Name of Scheme reflected in ADP 2009-10
1 4416 Capacity Building of P&D Department for Improved Policy Planning &
Monitoring of Development Process in Punjab.
2 4417 Automation of (Network/ Hardware) P&D Department, Govt. of the Punjab.
3 4425 Capacity Building of Civil Servants for Policy Making
4 4428 Establishment of Poverty reduction Strategy Cell
You are, therefore, requested to kindly furnish the ADP proposal (2010-11) (Hard
& Soft copy) of your respected sector to this office within two days positively.
The assignment may please be given priority.
(HAMID MAHMOOD)