This document provides a progress report for the Myanmar Aquarium Project by Min Dhama Co;Ltd as of the end of September 2017. It shows the percentage of work completed for each building - Block A is 24.33% complete, Block B is 45.83% complete, and Block C is 6.72% complete. The overall progress of the entire project is reported as 79.48% complete.
This document provides a progress report for the Myanmar Aquarium Project by Min Dhama Co;Ltd as of the end of September 2017. It shows the percentage of work completed for each building - Block A is 24.33% complete, Block B is 45.83% complete, and Block C is 6.72% complete. The overall progress of the entire project is reported as 79.48% complete.
This document provides a progress report for the Myanmar Aquarium Project by Min Dhama Co;Ltd as of the end of September 2017. It shows the percentage of work completed for each building - Block A is 24.33% complete, Block B is 45.83% complete, and Block C is 6.72% complete. The overall progress of the entire project is reported as 79.48% complete.
TOTAL % % ACTUAL ITEM DESCRIPTION CONTRACT OF ITEM CONTRACT 1 Block -A / F&B Building 30% 81.11% 24.33% 2 Block -B / Aquarium Building 55% 83.33% 45.83% 3 Block - C / Service Building 7% 96% 6.72% 4 Extranal Work etc; 8% 33% 2.60%