You are on page 1of 5

SCM Section Y

Mytreya Reddy Kamani


UM16212
Flow Supplier Factory

Sales/ Consumption per


Sl. No. Item
month (Rs Lakhs)
1 At supplier end 45
2 At Factory
RM (Consumption) 80
WIP (Production Value) 120
FG (Sales value) 160
3 Wholesaler 40
4 Retailer 25

End to End Supply Chian 122.7


Cycle time (in days)

Average Funds blocked in 336.86


the System (Rs Lakhs)
Wholesaler Retailer

Inventory turnover based on Average Inventory (Rs Quantity Ordered - Q


monthly sales Lakhs) (Rs Lakhs)
4 11.25 22.50

1.33 60.15 120.30


1.2 100.00 200.00
2 80.00 160.00
0.6 66.67 133.33
1.33 18.80 37.59
Reorder Point (Rs Time for Conusming Q Transportation
Lead Time - Days
Lakhs) Days Time -Days
50 8 16.7 0.0

23 45.1 0.0
25 0.0
15 0.0
50 89.1 7.5
16 23 9.4 0.0
Total Time - Days

16.7

96.6
9.4