Delay due to Dewatering

S.No Facility Duration Plan Start Plan Finish Actual Start Actual Finish Actual Duration Delay

1 Admin Block
Excavation 14-Sep-17 20-Sep-17 16-Sep-17 16-Sep-17 1 -3
7
Dewatering 14-Sep-17 20-Sep-17 17-Sep-17 23-Oct-17 37 34
Granular Backfill 7 24-Oct-17 24-Oct-17 1

2 Cafeteria
Excavation 15-Sep-17 17-Sep-17 16-Sep-17 18-Sep-17 3 2
3
Dewatering 15-Sep-17 17-Sep-17 19-Sep-17 21-Oct-17 33 35
Granular Backfill 2 22-Oct-17 22-Oct-17 1
lean
4 Maintainence Block
Excavation 1-Oct-17 14-Oct-17 15-Oct-17 19-Oct-17 5 6
14
Dewatering 1-Oct-17 14-Oct-17 20-Oct-17 25-Oct-17 6 12
Granular Backfill 4 26-Oct-17 26-Oct-17 1

5 Driver's Waiting Area


Excavation 1-Nov-17 4-Nov-17 7-Nov-17 8-Nov-17 2 5
4
Dewatering 1-Nov-17 4-Nov-17 9-Nov-17 14-Nov-17 6 11
Granular Backfill 3 15-Nov-17 15-Nov-17 1

6 Mosque
Excavation 15-Dec-17 21-Dec-17 16-Sep-17 18-Sep-17 3 -93
7
Dewatering 15-Dec-17 21-Dec-17 19-Sep-17 4-Oct-17 16 -77
Granular Backfill 5 5-Oct-17 5-Oct-17 1

7 Security Post
Excavation and Dewatering 21-Dec-17 22-Dec-17 15-Nov-17 18-Nov-17 4 -33
2
Dewatering 21-Dec-17 22-Dec-17 19-Nov-17 12-Nov-17 -6 -39
Granular Backfill 2 13-Nov-17 13-Nov-17 1

8 Sub-Station
Excavation 1-Dec-17 5-Dec-17 1-Nov-17 6-Nov-17 6 -28
5
Dewatering 1-Dec-17 5-Dec-17 7-Nov-17 14-Nov-17 8 -20
Granular Backfill 3 15-Nov-17 15-Nov-17 1

Negative delay shows that we start activity ahead of our plan