WORK METHOD STATEMENT FOR


PLASTERING.
Published on December 23, 2015

srinivasan renganathan Follow


10 3 1
Chief Operating Officer at Deep Real Estate Developers

1. SCOPE/PURPOSE 

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 1/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

This procedure covers the methodology to be followed for carrying out plastering and
pointing work over the masonry in line with the approved technical specifications. 
What is LinkedIn? Join Today Sign In

1. CODES / SPECIFICATION 

IS:1661 

1. RESPONSIBILITY 

Responsibilities of all concerned is clearly mentioned with respect to overall
administration and implementation in the approved Organogram. 

1. MATERIALS TO BE USED 

Cement, Sand, Water, Chicken mesh, Waterproofing compound. 

1. SAFETY REQUIRMENT Safety in Plastering and pointing: 

Use double scaffolding always and ensure the scaffolding is adequately braced with
the permanent structure, for working in heights.

Ensure the workers use safety appliances like safety belts in height, helmets, safety
goggles while carrying out chipping etc while carrying out plastering and pointing
in heights.

Ensure the working area is kept clean for easy access and protect edges of opening
by barricading etc while working.
https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 2/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

Ensure the area of working is well lighted (provided with lights) so that work area is
easily accessed and moved around safely by workers. What is LinkedIn? Join Today Sign In

Inspect the scaffolding before starting work.

Access platform/working platform double hand railing to be provided.

Proper illumination to be provided during the work, if required.

Educate the workmen through pep­talk meeting. 

1. DEPLOYMENT OF EQUIPMENT 

As per the requirement and the direction of Project Manager. 

1. DEPLOYMENT OF LABOUR 

As per the requirement and the direction of Project Manager. 

1. IMPLEMENTATION 

Preparatory Works (Before Taking up Plastering): Work Preparation. 

Complete all internal / external works like 

1. Filler walls in structural frame work 

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 3/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

1. Fixing frames of doors, windows and ventilators
What is LinkedIn? Join Today Sign In

2. RCC pre­cast jali works,

3. Fixing and concealing all kinds of pipes (getting concealed in the walls) 

Complete all pipelines works to their final positions and levels for Water supply
lines, Sewer pipelines, Telephone conduits, Electrical conduits, TV Antenna lines &
piping work for other services if any coming on wall surfaces to be completed with
their hood covers fixed and finished to the final surface level of the walls / ceilings. 

All lightning protection like earthing to be completed. 

Surface Preparation: 

Do prepare the surface to be plastered by 

Clearing all dirt and loose matter 

Chipping and clearing of mortar dropping.

Chipping and clearing of unevenness in the masonry, concrete works in ceiling and
walls of rooms.

Chipping and clearing the debris in areas of skirting and dado after marking the
cutoff levels clearly.

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 4/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

Raking out joints if necessary for proper keying 
What is LinkedIn? Join Today Sign In

For concrete surfaces: 

Prepare the surface of concrete members by 

Hacking at close intervals (50 to 70 mm center to center) with bush hammer or with
a chisel and hammer and then wash it thoroughly with water. This will roughen up
the concrete surfaces and ensure a good bond is provided for the plaster.

When concrete surfaces are greasy or oily, washing with acid may be done after the
wall is wetted with water (using a solution of one part muriatic acid diluted in 10­20
parts of water). After this acid cleaning, wash the surface thoroughly with water to
remove all the traces of acid. 

Note: This second washing is to remove all acid traces, so that the alkalinity does not
react with acid causing improper setting of cement and other problems. 

Fresh concrete surfaces are to be roughened with a heavy wire brush or a special
scouring tool.

Note: Form work for concrete meant to receive plaster, should preferably not be given
any oil coating, as these are likely to remain on the concrete, interfering with bonding of
the plaster. Care must be taken to remove the oil coating, before plaster is applied. 

For Brick / Block Masonry Surfaces: 

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 5/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

The surface should be hard, rough and clean. The joints should be raked 10mm deep
and splashed with water. It may be desirable to rough the surface with pick or a
What is LinkedIn? Join Today Sign In

similar tool, if the surface of stone in stone masonry is smooth, splash with water,
allow to dry before Plastering is taken up. 

Fix in position button marks at a spacing not more than one length of the straight
edge (viz 1.2m or 1.5m as the case may be for the entire surface to be plastered).
Check thoroughly all button marks for the thickness whether it is as per
specification. In case the thickness is more, do carry out the making up coat well in 

advance and scratch the surface rough to receive plaster. Similarly when thickness is
less, do carry out chipping where required, so that minimum thickness of plaster is
available at all places. 

Fix in position all plastering accessories like 

1. Chicken wire mesh in joints. 

1. Edge guards, edge stoppers, corner angles, corner beads etc,

2. Panel dividers, pattern marking on the wall / ceiling surfaces. 

Fix erect scaffolding system in advance so that it can be used for survey work,
surface preparation, carrying out plastering, curing. 

Light the area well in advance. 

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 6/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

work method for plastering Mortar Preparation
What is LinkedIn? Join Today Sign In

If mortar is to be prepared manually, the mortar for plastering has to be prepared
on a firm, neatly finished platform surface or on metal sheets only. A small
capacity mechanical mortar mixer can also be used. 

The sand /aggregate has to be sieved for proper gradation.

The sand aggregate has to be washed to remove impurities like mud, if required, and
sufficiently dried before plastering work is taken up.

In case wet sand is to be used, check for quantity of water in mortar and allow for
bulkage of sand while mixing to get consistency of mortar.

For stucco plastering, aggregate to be thoroughly washed sieved, hand picked to
remove unwanted coloured aggregates, flaky particles, which when used will spoil
the quality of plaster. 

Prepare the mortar in clear area in proportion as specified.

Mix mortar in a number of batches, a batch being the quantity (or volume of
mortar), which can be consumed with in next 2 hours.

Add water to the dry mix of sand and binder (not other wise).

If specified in the contract, do add the admixture to the mixed mortar and mix again
thoroughly.

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 7/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

Mix proportion required is 1:4. 
What is LinkedIn? Join Today Sign In

Plastering: 

The work procedure shall be: 

Wet the surface to receive plaster one hour before, so that while starting plastering,
the surface is skin dry.

Ceiling plaster shall be completed before commencement of wall plaster.

Plastering shall be started from the top and worked downwards to the floor

Throw the mortar for an area coverable by the straight edge, both vertically and
horizontally in one stretch. 

Level the surface using the straight edge. 

Float the surface and finish as per specification. 

Repeat this operation for the entire area in stages.

While proceeding with the work, do float and finish the joints in I stage and then in
subsequent stages properly. This is to ensure the stages, in plastering work, is not
apparently visible. 

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 8/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

Intermittently do check the surface for plumb, line and level and make up all
deficiencies.  What is LinkedIn? Join Today Sign In

−    Provide 12 mm thick single coat plaster in internal surfaces of concrete and masonry
wall in CM as specified & 10 mm thick single coat plaster on ceiling with CM as
specified.

Provide 20mm thick double coat plaster for external surface of wall as described below
– 

1. First coat 12 mm thick in CM of specified mix. Curing to be done for 7 days. 

1. After completion of first coat curing, provide second coat 8 mm thick of specified
thick. Curing to be done for 7 days.

Trueness of plastered surface when checked with the straight edge of 2 mts length
shall not be greater than 4mm at any place. 

Do and Don’ts in plastering works: 

Dos: 

Check thoroughly before and immediately after plastering, the line and levels.

Check thoroughly before and immediately after plastering, the surface areas for
unevenness, surface blemishes etc so that all rectification (if required) can be carried

https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 9/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

out with in the final setting time, with out much additional costs. 
What is LinkedIn? Join Today Sign In

Clean the floor area where plastering is to be taken up, to ensure plastering remains
to quality (without dust settling on wet surface).

Cure the plastering well for required number of days.

Restrict the access to area where plastering is complete (This will ensure better
protection of edges, corners, angles etc).

Finish the plaster touch up works near the skirting, after skirting and dado works are
completed. Also Do ensure a neat work is done.

Ensure all touch ups are done neatly after pre­cast slabs are embedded in position,
working platforms are inserted in position, and sanitary fixtures are fitted (merging
the surfaces being touched up with original surfaces). 

While stopping the work for the day, do ensure the surface end line is cut inclined at
45 degrees or 60 degrees. When starting the work next day, join the new plastering
and old plastering with neat workmanship (so that the joint is not showing up
badly).

Stop the work preferably in corners, jambs, stoppers or at grooves etc. This will
avoid cracks at joints. Do ensure these joints are finished neatly.

Round the edges than to keep sharp 90 degree edges (pencil round namely a small
curvature of less than 5mm radius). Similarly at the junction of ceiling to wall, Do
round off the junction. 
https://www.linkedin.com/pulse/work­method­statement­plastering­srinivasan­renganathan 10/13
12/11/2016 WORK METHOD STATEMENT FOR PLASTERING. | srinivasan renganathan | Pulse | LinkedIn

Don’ts: 
What is LinkedIn? Join Today Sign In

Do not allow mortar mixing on unclean area, with out a platform and in large
quantities.

Do not allow usage of partially set mortar.

Do not allow of free sprinkling of dry cement in the mortar or on the surface being
plastered, as this may cause uneven shrinkage and lead to development of shrinkage
cracks. 

Do not mix different bands of cement in same room / same area as this will show
colour difference (till plastered surface are covered with some other finish).

Do not allow any breaking or chipping open the plastered areas, for laying pipes etc
once plastering is completed

Tagged in: plastering

srinivasan renganathan
Chief Operating Officer at Deep Real Estate Developers Follow
166 articles

3 comments Recommended