METHOD STATEMENT PEDESTRIAN BRIDGE CONSTRUCTION

RESOURCES
No. STEP OF CONSTRUCTION MANPOWE EQUIPMEN
TOOL MATERIAL
R T
Preparation of site location:
A) Clearing, stock pile yard, temporary shelter,
delivery all materials. Excavator, Tarpaulin,
B) Armco Bridge works: Assemble wooden mat Dozer & small Galam,
1 Labour Hand Tools
as raft foundation and cylindrical Armco boat. Nails.
C) Construct temporary dock for pedestrian
and motorcycle to pass over the river while
bridge will be demolish
Constructing ramp on all bridge approach sides Light truck,
A) Dumping fill material (laterit soil) ± 30 m3 Dozer/Grader
2 Labour Hand Tools Laterit Soil
on one side of bridge. &
B) Levelling and compacting ramp Vibro Roller.
Boulder and
Dumping fill material to rise up river bed Light truck,
3 Stone
elevation, Excavator
(Base coarse)
Rise up middle section of river bed elevation :
A) Filling middle section of river bed with
boulder and stone until achieved 1.3 m height
from existing level. The dimension of filled area
Labour, Boulder and
1) 7.5 m long regarding Armco length 2) 5 m
5 Operator, Pole Stick Excavator Stone (Base
width regarding Armco Dia. 4500 mm
Surveyor coarse)
3) 1.3 m height to rise up Armco elevation up
to 1.3 m or less
B) Measure/Check river bed after filled to
confirm the elevation
Wooden mat/raft foundation: putting down
Labour,
7 wooden mat at the river bed and piling array Steel Wire Excavator Galam
Operator
galam timber to fix the position of Armco
Armco bridge works:
A) Rolling Armco #1 Dia. 3600 mm to move the
precise position using Excavator #1, while the
Excavator #2 that stand on the other side
pulling it using steel cable to stabilize the 2 x Armco
position. Dia. 3600
Labour,
8 B) Rolling Armco #2 Dia. 4500 mm using Steel Wire Excavator mm, Dia.
Operator
Excavator #1, while Excavator #1 pulling it the 4500 mm,
opposite. galam pile
C) Rolling Armco #3 Dia. 3000 mm using
Excavator #1.
D) Pilling galam to hold the Armco on the
required position.
Back Filling work :
Excavator, Galam, Sirtu,
A) Install soil bag to divert water flow &
Labour, Pontoon, Sand/soil
9 protect backfill area between Armco.
Operator Bulldozer, & bags, Manila
B) Back fill the space between Armco using
Dump Truck Rope.
sirtu up to require elevation
Compacting and levelling : Vibratory
Labour, Gravel and
10 Grading & Levelling pavement structure over Roller,
Operator base coarse
the bridge surface to design elevation including Bulldozer
compaction