You are on page 1of 1

EROSION CONTROL AT ANGUWAR GABAS DEBA GOMBE STATE

SITE PROGRESS REPORT FOR PERIOD ENDING 30TH APRIL, 2011

1. DETAIL

(I) Contractor: YASMIN INVESTMENT NIG. LTD


(II) Contract Sum: N 95,039,981.88
(III) Date of Award: 14th December, 2011.
(IV) Contract Duration: 4 Months
(V) Advance Payment: NIL

2. SUMMARY OF SCOPE OF WORKS


(I) Site clearance
(II) Gully Reclamation
(III) Construction of concrete drain
(IV) Construction of culvert and pedestrian slabs

3. WORK PROGRESS
(I) Pre-survey and Final Engineering Design 100%
(II) Setting Out Works and site installations 100%
(III) Site clearance and Muck shifting 100%
(IV) Material Procurement 100%
(V) Gully Reclamation & Trench Excavation for piles 90%
(VI) Reinforcement fabrication 100%
(VII) Construction of Concrete drains 90%
(VIII) Formwork and shuttering 100%
(IX) Overall Work Progress 95%

4. CHALLENGES

Transportation of filling and generally working materials from long distance to the site and
recent Post Election civil disturbance in The State and surrounding reduce work progress at
crucial time.

5. CONCLUSIONS
Both work progress and quality of work are considered satisfactory. Payment to the contractor is
recommended.

BABA GANA ALI


ACAO (WHM)

6TH JUNE, 2011.

You might also like