The measurement for payment for the traffic management team shall be man-month basis
supplied throughout the construction period.
Item Coverage
The rates for the traffic management team shall be for the duration of the Contract and shall
include:-
(a) The wages and other enumerations paid to the site staff inclusive of overtime payments.
(b) Cost and expenses incurred consequent upon the employment for hiring of the site
staff including payment of employee provident fund, insurance, medical and
hospitalization
(d) Substitution of site staff when the appointed traffic management staff is absent or on
leave.
Unit
MM9 /1
(h) Flashing arrows in Number (nr),
Measurement
Item Coverage
The item for providing temporary traffic devices shall be in accordance with the Preamble to
the Bill of Quantities including:-
(a) Supply and installations of each and every item shown as per drawing for all temporary
diversions.
(c) Provide replacement at no extra cost when any of the specified items is damaged or lost.
(e) Complying with “Arahan Teknik (J) 2C/85 Temporary Signs and Work Zones
Control” specifications on the quality and size.
Unit
Measurement
(a) the installed length measured along the centre line of the beams from the end of terminal
section to the start of the other end terminal section for the Galvanised W Beam
Guardrails,
MM9 /2
Item Coverage
The measurement of temporary guardrail shall be in accordance with the Preambles to the Bill
of Quantities General Directions and shall include:-
(a) Supply and install W Beam Guardrail including attachment, fixings, and stiffeners
and adjustment of beam to flowing alignment,
(c) galvanizing,
(e) posts, spacers, terminal sections, terminal buffer end, 90° twist and anchorages,
(f) driving post in any material except rock or drill in rock, concrete and pavement for the
fixing of bolts or other fixtures for the installation of the posts,
Unit
The units of measurement for the temporary signs shall be in Number (nr).
Measurement
The measurement of all temporary signs shall be of the numbers of completed installation and
accepted by the S.O.
Item Coverage
The items for traffic signs shall be in accordance with the Preambles to Bill of Quantities
General Directions and shall include:-
(b) excavation for bases of sign post and disposal of surplus excavated material,
backfilling with concrete and compaction,
(d) all materials necessary inclusive of bolt , nuts, m.s. angle, protective system and fixing,
MM9 /3
(f) drilling or forming holes and pockets in structure or foundation and casting in bolts,
sockets, base plates and anchorage assemblies,
(i) in the case of illuminated signs, all electrical equipment, wiring and connection
excluding network cabling,
(k) backboard,
(m) Maintenance and replacement of defective parts and components throughout the
contract period.
Unit
Measurement
The measurement for payment for the above items shall be the completed works measured on
site
Item Coverage
(c) The item for road marking shall be referred to MOM (Section 6)
(d) The item for removal of temporary road diversion shall be in accordance with the
Preambles to Bill of Quantities General Directions and shall include:
MM9 /4
(ii) levelling to grade and levels
Unit
The unit of measurement for traffic management plan and method statement shall be Lump
Sum (sum).
Measurement
The measurement for payment for the traffic management plan and method statement shall be
the acceptance of the traffic management plan and method statement in accordance to the
format and copies as stipulated in the guideline / specification and bill of quantities.
Item Coverage
The item for traffic management plan and method statement shall be in accordance with the
Preambles to the Bill of Quantities General Directions and shall include the costs of
literatures, references and consultation in the production of the traffic management plan and
method statement.
Unit
The unit of measurement of traffic management and road safety report shall be Lump Sum
(sum).
Measurement
The measurement for payment for the traffic management and road safety report shall be the
acceptance of the traffic management and road safety report in accordance to the format and
copies as stipulated in the guideline / specification and bill of quantities.
Item Coverage
The item for traffic management road safety report shall be in accordance with the Preambles
to the Bill of Quantities General Directions and shall include:-
(a) on-site traffic management evaluation and the procurement of road accident data in the
production of the traffic management and road safety report.
MM9 /5