DOCKING LIST OF MT BEE 1

DUE TIME ON JUNE 2016

NO OBSERVATION REQUIRE APPROVAL


DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016
1 FORE CASTLE DECK 1. a. Anchor port and stbd need to lay 1a.
Anchor chain port and starboard side thin down. down for checking chain conditions
Remarks: - Port side and stbd anchor chain because condition is thin
shackles from 1 to 4 shackles badly corroded b. anchor swivel need to replace b.
-anchor swivel port and starboard c. fairlead is stuck and need to replace or c.
side is bad condition heating is necessary d.
Type: Grade U2 Steel Stud Link d. air vent mask is rusty and thin nedd to
Anchor Chain, diameter: 50 mm replace 2.
Roller/ fairlead anchor portside and stbd is stuck 2. anchor machine not work well net to
Air vent mask rusty, bad condition check or maintenance 3.
2 Anchor machine need to test and repair for 3. chain fender and shackle need to change
maintenance Chain to be change with belting @1.5
3 Chain fender and shackle rusty and bad condition mtrs(1500mm length) total 35 pcs
MAIN DECK all around
4 Tent/ canopy pipes above flow meter broken/ thin Shackle need to replace 70 psc size 5/8 4a.
And must higher inch
5 Manhole pin chain connection, between body and pin 4.a. Tent above flow meter for bunker
broken operation need to change/ replace and
6 Manhole lock S1 need to repair build higher (for navigation, bridge cannot b.
7 Cable pipe bad condition rusty and thins navigated forward )
8 Scupper plug is not good conditions and some was b. lamp boxes at forward near manhole 1
broken Wings need to fixed lower for safety
9 Hose for bunker Ø3 inch male and female leaking navigation 5.
and thin 5. manhole PIN joiner is broken need to
10 Slop tank manual pump rusty and stuck inside not join for preventing from disappear 6.
working 6. manhole at S1 need to repair because to
POOP DECK tight and cannot lock 7.
11 Doors at portside and stbd cannot close properly 7. Cable pipe is thin, need to replace
12 Tarpaulin at astern bad condition 8. Scupper plug at main deck 2 pcs 8.
Canopy pipes at astern rusty and thin broken,2 pcs not in good condition, 2 pcs
at astern not fixed, conduct to SOP (Safety
Operation Procedure)
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016
NO OBSERVATION REQUIRE APPROVAL
9. Bunker hose at amin deck is not good 9.
condition ang head of connection need to replace
between connection there is have 2 connection,
male and female

10. Slop tank manual pump bad condition stuck 10.


inside need to repair or replace
11
11. Doors at poop deck need to reconstruction,
position of doors cannot open fully 12a.
12 a. Canopy pipes at astern need to change and
reconstruction more breadth b.
b. Tarpaulin also need to change
MACHINERY DEPARTMENT
13 Inlet sea water for cooling FW cooler 13. Repair and reconstuction pipes
14 Sea water connection for toilet 14. Repair pipe leaking 13.
15 Outlet air conditioner water 15. Reconstruction, accordingly previously water 14.
flow to bilgest, require direct flow to overboard
15.
16 Outlet cooling air condition 16. Repair, pipe leaking( crack)
16.
17 Sucktion valve bilgest 17. Replace, according loose
17.
18 Generator port and starboard 18. overhaul generator due running times
18.

PICTURE :
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

1A AND 1B 1C 1C

1D 2 2*
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

3 4 4*

5 5* 6
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

7 7*

8 9 9*
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

10 11 11*
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

12 12* 13

14 15
DOCKING LIST OF MT BEE 1
DUE TIME ON JUNE 2016

16 17

MASTER / CHIEF ENGINEER


MT. BEE 1