Republic of the Philippines

CIVIL AVIATION AUTHORITY OF THE PHILIPPINES

Project : Repair/Repainting and Waterproofing of NAVAIDS Building


Location : CAAP, Mactan International Airport, Lapu-lapu City
Subject : COMPUTATION OF LIQUIDATION DAMAGES/PENALTY AS PER CLAUSE 9.1 OF
SPECIAL CONDITION OF CONTRACT
______________________________________________________________________________

 CONSTRUCTION SIGNIFICANT DATES:


Start of Project : January 29, 2016
Amended Notice to Proceed : February 22, 2016
Project Duration : 120 calendar days
Date of Termination : January 11, 2017
Completion extended until :
Start of Penalty date : January 11, 2017
Date of Proposed Completion : June 27, 2016

 SPECIAL CONDITION OF CONTRACT CLAUSE 9.1


“The applicable liquidated damages are at least one tenth (1/10th) of one percent of
the cost of unperformed portion of every day of delay.”

 COMPUTATION:
Total number of days of delay : 199 Days
Unperformed portion as of
January 11, 2017 : 42%
Contract Amount : Php 1,109,735.5
Amount Unperformed : Php 466,088.91

Computed Liquidated damages/


Penalty per day of Delay : Php 466.00/day

Total accumulated amount of


Liquidated damages/ Penalty : Php 92,734.00

Prepared and submitted by:

ENGR. REYNOLD D. VELOSO


Project –in- Charge, Area VII
Civil Aviation Authority of the Philippines
Mactan International Airport, Lapu-lapu City