Project Title: Detailed Estimate of the Proposed Construction of the New Oas Evacuation Center

Location: Oas Pavillon, Iraya North, Oas, Albay

PLUMBING ESTIMATES

DESCRIPTION QUANTITY UNIT PRICE TOTAL AMOUNT


1. Water Closet 4 sets 9,000.00 36,000.00
2. Lavatory 3 sets 3,000.00 9,000.00
3. Urinal 1 set 8,000,00 8,000.00
4. Faucet 7 pcs. 150.00 1,050.00
5. Floor Drain 3 pcs. 150.00 450.00
6. ½ dia PPR pipe 9pcs. 335.00 3,015.00
7. ½ dia PPR elbow 10pcs. 13.00 130.00
8. ½ dia PPR tee 12pcs. 16.00 192.00
9. ½ dia gate valve 5pcs. 340.00 1,700.00
10. 2” dia PVC pipe (Orange) 11pcs. 238.00 2,618.00
11. 2” dia PVC elbow (90deg) 5pcs. 95.00 285.00
12. 2”dia PVC P-trap 3pcs. 97.00 291.00
13. 3” dia PVC pipe 35pcs. 509.00 17,815.00
14. 3” dia PVC pipe elbow (90deg) 16pcs. 96.00 1,536.00
15. 3” dia PVC long elbow 2pcs. 95.00 190.00
16. Roof Drain 7pcs. 250.00 1,750.00
17. Neltex Solvent 200cc 2- ¼ qrt. 120.00 500.00
18. 920 Lit. Water Tank 2 unit 12,355.00 24,710.00
19. 1.5 H.P. water pump 1 unit 11,750.00 11,750.00

Material Cost …………………………………………………₱120,000.00


Labor Cost: ……………………………………………30% ₱ 36,294.00
Direct Cost: …………………………………………..
Indirect Cost: ……………………………………….
Tax: ……………………………………………………..12% ₱14,517.84
Grand Total: ………………………………………..