To: Dr.

Bruce
From: Hank Dickey, Team Zephyr
Device: Insignia NS-F12R6-SS
Team tag: CSUF-BRUCE-F18S2G1

Progress Report #4

Purpose
The intent of this document is to update Dr. Bruce on Team Zephyr’s progress on their iFixit
project.

Summary
This document includes a breakdown of the problems encountered by our team, our current
schedule, and anticipated outcomes.

Problems Encountered
The biggest challenge for our team thus far was conducting a successful photoshoot. It took two
attempts and post-processing to produce photos that meet iFixit’s standards. Most of our team
does not have experience with this type of photography, but the robust guides provided by iFixit
helped us overcome this challenge. Please find a detailed list of our team’s progress below.

Progress to Date
Completed Tasks
 Team Charter
 Progress Report #1
 Proposal
 Troubleshooting Pages
 Progress Report #2
 Device Page
 Progress Report #3
 Device Guides
Tasks in Progress
 Review Troubleshooting Pages
 Review Device pages
Future Tasks to Complete
 Evaluation Memo
 Peer Review
 Project Folder

Conclusion
Our group’s ability to work effectively as a team has resulted in the timely completion of quality
work. As a team we are focused on reviewing the deliverable components of our project to
make sure they meet iFixit’s expectations. Overall, we are proud of our work and our
performance as a team.
Time Summary
Hank: 30 hours Tina: 11 hours Sheena: 12 hours Therese: 15 hours