DAILY PROGRESS REPORT 12

DATE / DAY : Weather:


DEVELOPER :
CONTRACTOR: 9 3
CONSULTANT: Page 1 of 1
6
Item Location Activity Remarks Machinaries/Plants/Manpowers
Nos. of General Super- Total
Operational Team:
Rig Workers visor Manpower
Deep Boring Team
Piezocone Team
Trial Pit Team
Hand Auger Team
Mackintosh Probe Team

Todate Progress
Provision
Completed In Progress Out Standing
Scope of Works in the BoQ
(nos.) (nos.) (%) (nos.) (nos.)
(1) Deep Boring (nos.)
(2) Piezocone (nos.)
(3) Trial Pit (nos.)
(4) Hand Auger (nos.)
(5) Mackintosh Probe (nos.)
(6) Standpipe Piezometer (nos.)

Completion Period :
Special Instruction:

Prepared By: Checked By: Verified By:


Date: Date: Date: