You are on page 1of 4

DETAILED COST ESTIMATE

ITEM DESCRIPTION Quantity Unit

I Mobilization/Demobilization
Clearing and blue sack enclosure
Bunkhouse
Testing of Materials
Bonds & Permits
TOTAL - ITEM I
II Earthworks
Excavation
Backfilling
Soil Poisoning
TOTAL - ITEM II
III. Structural Works
1.) Concrete Works
A.Footings
Cement
Sand
Gravel
Gravel bedding
Sub-Total
B. Tie Beams
Cement
Sand
Gravel
Sub-Total
C. Columns
Cement
Sand
Gravel
Sub-Total
D. Beams and Roof beams
Cement
Sand
Gravel
Sub-Total
E. Slab on fill
Cement
Sand
Gravel
Gravel bedding
Sub-Total
F. CHB Wall/Stairs/Plant box/Plastering
CHB 6''
CHB 5''
CHB 4''
Cement
Sand
Gravel
Sub-Total
Total 1 (A-F)
2.) Reinforcing Bars
A. Footings
16mm dia x 6m
12mm dia x 6m
no 16 G.I. Tie wire
Sub-Total
B. Tie Beams
16mm dia x 6m
12mm dia x 6m
10mm dia x 6m
no 16 G.I. Tie wire
Sub-Total
C. Columns
16mm dia x 6m
12mm dia x 6m
10mm dia x 6m
no 16 G.I. Tie wire
Sub-Total
D. Beams and Roof beams
20mm dia x 6m
16mm dia x 6m
Unit Cost Amount